11 This report clearly suggests that it is technically feasible to cut the slab as proposed in options 3 and 5.
12 I consider that Mr Nash has provided a useful report which proposes a number of options which would ameliorate the impacts of the structure on the Applicants' properties. The alternative to not making orders allowing additional work to be done in a set timeframe is that I order demolition of the structure entirely. I consider it is appropriate that I make most of the orders sought by the Applicants, which largely implement the options identified by Mr Nash. The only order sought by the Applicants I will not make is in relation to the complete removal of the spa from the structure. Spas are generally complying development under the relevant environmental planning instrument according to the Council. The spa will have to be moved within the structure if the further work is undertaken by the Second Respondent. If the Second Respondent decides that he does not wish to undertake this work for whatever reason the structure will need to be demolished.
13 The Second Respondent has represented himself since the substantive hearing in which he was represented by counsel. I realise that these orders involve the Second Respondent in further expense if he chooses to undertake the work and that could involve financial hardship. He submitted I should order the Council to pay the costs of complying with any orders. My power to make such an order is unclear and I decline to do so. It is up to the Second Respondent to consider if he has a claim against the Council in another forum in light of the extra expense he incurs in complying with these orders. I will allow a longer period than the period sought by the Applicants in which to undertake this work. Following a further submission from the Second Respondent concerning financial hardship caused by the cost of the additional work, I consider ten months is an appropriate period to allow for the work to be done, whether alterations to the structure and landscaping, or demolition.
14 It is important that if the Second Respondent does undertake the work set out in proposed Order 2 that he is placed in a position that he can apply for, and have a high likelihood of obtaining, a building certificate under s 149D of the Environmental Planning and Assessment Act 1979 ("the EP&A Act") from the Council. Once a building certificate is issued s 149E sets out the protection afforded to the holder of a certificate against any action by a council in relation to the repair, demolition, alteration, addition or rebuilding of a structure the subject of a certificate. An application for such a certificate is made under s 149B of the EP&A Act. Counsel for the Council has proposed that a mechanism to achieve this result is that the works in Order 2 must be supervised by an appropriately qualified structural engineer who at the conclusion of the works should provide both Respondents with a certificate certifying the adequacy of the works. This certificate would be the basis for the Second Respondent applying to the First Respondent for a building certificate. Given this approach emerged from discussions in the course of determining what final orders ought be made it is preferable that the Second Respondent be advised in writing that this course of action is appropriate to the First Respondent. Any additional matter the First Respondent anticipates requiring if a building certificate is applied for by the Second Respondent should also be identified now in writing. For example, will the First Respondent require the engineer to say what inspections he or she has conducted in the course of the work being undertaken? A letter to the Second Respondent stating that the use of a qualified structural engineer is appropriate, outlining his or her supervisory role, and identifying any additional matters the Council is likely to raise if an application for a building certificate is made by the Second Respondent should issue forthwith. What I am seeking to achieve is complete clarity for the Second Respondent as to what is required for the building certificate application so that there is a high likelihood that it will be issued by the Council if the requirements specified in the letter are complied with. If necessary I can make an order requiring that the letter be written but if the Council is able to attend to this within say two weeks there is no need for an order in my view. I have been informed that the Council has agreed to provide the required letter to the Second Respondent within two weeks.
15 As referred to in the previous paragraph, to ensure adequate supervision of the works and to increase the likelihood of a building certificate being obtained the works referred to in order 2 below should be supervised by an appropriately qualified structural engineer who, at the completion of the works, should provide both the First and Second Respondents with a certificate certifying the structural adequacy of the works as altered. I will not require this in an order but note that it is an appropriate course in the circumstances.
16 I also note there is an order giving liberty to the Second Respondent to apply to the Court for the amendment of any time specified in the orders.
Orders
17 The Court makes the following orders:
- The Second Respondent obtain, within two months of this order, the opinion of a suitably qualified structural engineer to determine a means of cutting the slab of the pergola in the manner set out in order 2(b) and (c) below whilst enabling the remainder of the pergola slab and supporting piers to remain.
- In accordance with the recommendations of the structural engineer's report obtained pursuant to order 1, the Second Respondent carry out the following works within eight months of the date of this order:
(a) Remove the curved roof element of the pergola structure and erect a flat roof in lieu thereof.
(b) The eastern portion of the slab and supporting columns are to be cut back to a point 3000mm from the eastern boundary and the pergola structure set back by 3000mm from the eastern boundary.
(c) The slab of the pergola is to be cut back by 1000mm and six structural support piers removed from the northern edge of the pergola. The pergola structure is to be set back by 1000mm on top of the slab in accordance with the attached sketch ("Annexure A").
(d) Lattice screening of 1000mm in height is to be erected from the underside of the slab along the northern face of the slab.
(e) The balustrades on the northern side of the pergola are to be replaced with non-reflective material.
(f) Erect fixed horizontal louvres of 600mm in height above the railing of the pergola in accordance with the attached sketch ("Annexure A"), along the entire length of the northern side of the pergola and fixed louvres angled upwards at 45 degrees along the eastern side and for 2m along the southern side of the pergola from the south-eastern corner.
(g) Carry out landscape planting along the northern boundary of the site in accordance with the report of Narelle Sonter "alternative screen solution" dated 3 March 2005.
(h) Carry out supplementary landscaping along the eastern boundary of the site with lilly pilly trees in order to screen the pergola structure.