TQM Design & Construct Pty Ltd & Anor v Romeo & Anor
[2011] NSWDC 143
At a glance
Source factsCourt
District Court of NSW
Decision date
2011-09-28
Catchwords
- (1964) 112 CLR 125 Randhawa v Serrato [2009] NSWSC 170 Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52
Source
Original judgment source is linked above.
Catchwords
Judgment (10 paragraphs)
Notice of motion 1This is a notice of motion filed by the plaintiffs on 3 August 2011 seeking interlocutory orders that the defence and any cross claim by the defendants against the plaintiffs be struck out pursuant to Uniform Civil Procedure Rules 2005 Pt 14 Div 5 r 14.28 and s 15(4)(b) of the Building and Construction Industry Security of Payments Act 1999 ("the BCISP Act "].
Factual background 2The dispute underlying these proceedings involves two stages of building work in relation to premises situated at 18 - 20 Park Street, Mona Vale, NSW. The works involved the erection of a building containing 18 residential apartments, 6 retail units and a 46 vehicle basement car park. 3The first component of such works comprised the principal works which were the subject of a contract to which the Home Building Act 1989 applied. Those works gave rise to a second category of works comprising some agreed rectification of the principal works. There was a question as to whether those rectification works were the subject of an agreement to which the BCISP Act applies. 4On 12 May 2005, the plaintiffs and defendants entered into a construction contract. Subsequently, on 23 November 2007, the plaintiffs and defendants entered into an agreement in relation to various disputes that had arisen under that contract. The agreement included terms that the defendants were to pay the plaintiffs an amount of $137,500 upon execution of the deed to the agreement. The agreement also required the provision of some identified documents as well as requiring the commencement of rectification work to the front facade of an awning on the premises. There was provision for the payment of a further sum of $137,500 within 7 days of the plaintiffs notifying the defendants of completion of the rectification works. 5On 1 March 2010, the plaintiffs wrote to the defendants and notified them of the completion of the rectification works in accordance with clause 2.1(b) of the agreement for rectification works. At that time a payment claim was issued by the plaintiffs purporting to be in accordance with s 13 of the BCISP Act. At no stage did the defendants raise a relevant dispute by means of serving a payments schedule on the plaintiffs, as contemplated by s 14 of the BCISP Act . 6It was common ground that in the course of the principal works, the plaintiffs had issued a number of payment notices and had served those notices on the defendants in accordance with the BCISP Act . However, prior to the issue of the payment claim, the subject of these proceedings, the plaintiffs had not issued any previous payment claims relating to the rectification works. 7In this application there was a dispute as to the entitlement of the plaintiffs to issue the payment claim in question, and there were disputes over the validity of service of the payment notice. For the purposes of determining this interlocutory application it is not necessary to consider the detail of the works. 8The plaintiffs filed their amended statement of claim on 13 May 2011. The plaintiffs have sued on the agreement to perform rectification works claiming those works were "construction works" within the meaning of s 5 of the BCISP Act. On 27 June 2011 the defendants filed a defence to the amended statement of claim. That defence sought to raise matters arising out of the construction contract.