The effect of suspension of the works on statutory warranties
29Section 18B of the HBA implies warranties into all contracts for residential building works. It relevantly provides -
The following warranties by the holder of a contractor licence, or a person required to hold a contractor licence before entering into a contract, are implied in every contract to do residential building work:
(a) a warranty that the work will be performed in a proper and workmanlike manner and in accordance with the plans and specifications set out in the contract,
(b) ...
(c) a warranty that the work will be done in accordance with, and will comply with, this or any other law,
30Those warranties may not be excluded, Section 18G provides -
A provision of an agreement or other instrument that purports to restrict or remove the rights of a person in respect of any statutory warranty is void.
In the case of the works performed by TQM for the developers the statutory warranties were implied with respect to those parts of the works that are residential building work.
31Section 18C provides that the immediate successors in title to developers are entitled to the benefit of the statutory warranties applicable to the work done on their behalf. As a consequence, the Owners Corporation and the purchasers of the individual residential apartments forming part of the works were entitled to the benefit of those warranties.
32The warranties are generally enforceable for 2 years, but run for 6 years where the defects are structural. Section 18E provides -
(1) Proceedings for a breach of a statutory warranty must be commenced in accordance with the following provisions:
(a) proceedings must be commenced before the end of the warranty period for the breach,
(b) the warranty period is 6 years for a breach that results in a structural defect (as defined in the regulations) or 2 years in any other case,
(c) the warranty period starts on completion of the work to which it relates (but this does not prevent proceedings from being commenced before completion of the work),
(d) if the work is not completed, the warranty period starts on:
(i) the date the contract is terminated, or
(ii) if the contract is not terminated-the date on which work under the contract ceased, or
(iii) if the contract is not terminated and work under the contract was not commenced-the date of the contract,
(e) if the breach of warranty becomes apparent within the last 6 months of the warranty period, proceedings may be commenced within a further 6 months after the end of the warranty period,
(f) a breach of warranty becomes apparent when any person entitled to the benefit of the warranty first becomes aware (or ought reasonably to have become aware) of the breach.
(2) The fact that a person entitled to the benefit of a statutory warranty specified in paragraph (a), (b), (c), (e) or (f) of section 18B has enforced the warranty in relation to a particular deficiency in the work does not prevent the person from enforcing the same warranty for a deficiency of a different kind in the work (the other deficiency) if:
(a) the other deficiency was in existence when the work to which the warranty relates was completed, and
(b) the person did not know, and could not reasonably be expected to have known, of the existence of the other deficiency when the warranty was previously enforced, and
(c) the proceedings to enforce the warranty in relation to the other deficiency are brought within the period referred to in subsection (1).
33Structural defect is defined in clause 71 of the Home Building Regulation 2004. It provides -
(1) For the purposes of sections 18E (1) (b) and 103B (2) of the Act, structural defect means any defect in a structural element of a building that is attributable to defective design, defective or faulty workmanship or defective materials (or any combination of these) and that:
(a) results in, or is likely to result in, the building or any part of the building being required by or under any law to be closed or prohibited from being used, or
(b) prevents, or is likely to prevent, the continued practical use of the building or any part of the building, or
(c) results in, or is likely to result in:
(i) the destruction of the building or any part of the building, or
(ii) physical damage to the building or any part of the building, or
(d) results in, or is likely to result in, a threat of imminent collapse that may reasonably be considered to cause destruction of the building or physical damage to the building or any part of the building.
(2) In subclause (1):
structural element of a building means:
(a) any internal or external load-bearing component of the building that is essential to the stability of the building or any part of it, including things such as foundations, floors, walls, roofs, columns and beams, and
(b) any component (including weatherproofing) that forms part of the external walls or roof of the building.
34From the time TQM first became aware of the complaints about the defects TQM has taken the position that, because the works were and remain suspended, its obligations under the statutory warranties were similarly suspended. TQM relies on the provision the Building and Construction Industry Security of Payment Act 1999 ("the BCISOP Act") to support this contention. Specifically, it relies on s 27 of that Act which provides for the suspension of works. It says -
(1) A claimant may suspend the carrying out of construction work (or the supply of related goods and services) under a construction contract if at least 2 business days have passed since the claimant has caused notice of intention to do so to be given to the respondent under section 15, 16 or 24.
(2) The right conferred by subsection (1) exists until the end of the period of 3 business days immediately following the date on which the claimant receives payment for the amount that is payable by the respondent under section 15 (1), 16 (1) or 23 (2).
(2A) If the claimant, in exercising the right to suspend the carrying out of construction work or the supply of related goods and services, incurs any loss or expenses as a result of the removal by the respondent from the contract of any part of the work or supply, the respondent is liable to pay the claimant the amount of any such loss or expenses.
(3) A claimant who suspends construction work (or the supply of related goods and services) in accordance with the right conferred by subsection (1) is not liable for any loss or damage suffered by the respondent, or by any person claiming through the respondent, as a consequence of the claimant not carrying out that work (or not supplying those goods and services) during the period of suspension.
35Claimant "means a person by whom a payment claim is served under section 13": s 4. Section 13 is concerned with payment claims, while section 14 requires persons on whom a payment claim is made to provide the claimant with a payment schedule specifying when the payment is to be made, and if the payment is less than that claimed, the reasons for withholding payment. Section 16 then provides that if payment is not made in accordance with the payment schedule that the claimant may take action to recover the unpaid moneys and may serve notice of intention to suspend (s 16(2)(b)).
36It is important to note that s 7(2)(b) provides that the Act does not apply to-
(b) a construction contract for the carrying out of residential building work (within the meaning of the Home Building Act 1989) on such part of any premises as the party for whom the work is carried out resides in or proposes to reside in, ...
That provision did not operate to exclude from the operation of the Act the contract between TQM and the developers. This is so because it was for the construction of both commercial and residential premises, and that residential work consisted of 18 separate apartments: see Shorten v David Hurst Constructions Pty Ltd [2008] NSWCA 134.
37TQM relied on the decision in Turner Corporation Limited (Receiver and Manager Appointed) v Austotel Pty Ltd [1994] 13 BCL 378 to argue, as I understand it, that the only means by which it could be required to remedy any defective works was by the service on it by the developer of the necessary notices required under the contract. As the contract was and remained suspended this could not have happened. In Turner Corporation Cole J found that a proprietor working under a JCCA contract could not rely on its common law right to have incomplete works and defects completed by persons, other than the builder, at the builder's costs: but was bound to follow the procedure set out in the contract.
38In my opinion this submission, insofar as it seeks to make an analogy between a proprietor's common law rights and the statutory warranties implied by s 18B of the HBA, must fail. This is so as the warranties are implied by the HBA and cannot be excluded by contract.
39The warranties applied to all the work done by TQM. In my opinion there is nothing in the wording of s 27 of the BCISOP Act which suspended TQM's obligations with respect to the statutory warranties. While TQM is undoubtedly correct that, due to the suspension it was under no obligation to compete the contract works, that suspension did not operate to relieve it of the obligations imposed by the statutory warranties.