35 Given the intervention of the Christmas period, and the transition of jurisdiction from the Town Planning Appeal Tribunal to the State Administrative Tribunal, when looked at objectively the time between institution of the appeal and its final hearing was relatively short. At least four weeks of that period is attributable to the applicant's request to adjourn the January directions hearing essentially for reasons of convenience of the applicant.
36 It is true that, immediately before the hearing, the respondent made concessions in relation to a number of the disputed conditions. The applicant contends that those concessions should have been made earlier, and in particular, after receipt of the applicant's solicitors' letter of 10 February 2005. It is desirable that parties make appropriate concessions as early as possible in the proceedings and do not leave it to the door of the hearing room before doing so. Delay in making concessions can result in unnecessary expense to the other parties. It is a reality, however, that in the course of final preparation for a hearing, with the benefit of the exchange of witness statements, parties will undertake a re-assessment of the position they have adopted on particular issues to that time. That process often leads to last minute concessions, and frequently complete settlement of matters, just before the hearing is due to commence. The continuous assessment of a party's position on the issues in a matter is to be encouraged, even if it creates an appropriate change of position immediately before, or even during, a hearing.
37 In this case, the applicant's letter of 10 February 2005 was given detailed consideration and received a timely response by the letter of 17 February 2005. Thereafter the respondent unsuccessfully sought to arrange mediation, and endeavoured by telephone conferences during March to further discuss and resolve some issues.
38 It is not contended by the applicant that there was no justification for a hearing in relation to the parking issues.
39 In our view, it simply cannot be said that the respondent has failed to genuinely attempt to enable and assist the Tribunal to make a decision on its merits or that the respondent unreasonably drew out or delayed the determination of the proceedings. In relation to the applicant's conduct within the proceedings, apart from the matter giving rise to the necessity for supplementary evidence from Ms Jelley, the respondent did not cause the applicant to incur wasted costs. It was regrettable that the issue as to the consent of the "owner" of the road reserve was a matter raised only during the course of the hearing. That caused enquiries to be made by the applicant as to the question of care and control of the road reserve. It being a matter of jurisdiction for the Tribunal, once the issue became apparent to the respondent, it was proper for it to be raised. Had it been raised earlier, the same sorts of enquiries which ultimately became necessary would have been made, albeit at an earlier stage. The same cost and inconvenience is likely to have arisen whenever the issue was raised. The costs which were incurred were, therefore, not wasted costs, even though the issue was ultimately decided in favour of the applicant's position.
40 The applicant does not complain only of the respondent's conduct in relation to the application for review. The applicant's position is the respondent did not genuinely attempt to make a decision on the merits of the application for approval prior to the institution of the application for review on 4 December 2004. Undoubtedly the applicant was anxious to proceed with its proposed development. It, and its consultants, undoubtedly experienced frustration that the application was not brought before the council of the respondent by October 2004 or November 2004. Delays by reason of staff shortages, of which Mr Callow was warned within a week of lodgement of his application, undoubtedly played their part. No doubt the position was not helped by the original planning officer dealing with Mr Callow leaving the respondent's employment during October 2004.
41 The applicant may regret its conscious decision to delay instituting an appeal against the "deemed refusal", but rather to continue to endeavour to resolve the matter with the Shire. Nevertheless, the provisions in town planning schemes which deem an application refused are designed to provide a remedy to applicants where an application for development approval is not dealt with in a timely way. Even if s 87(3) does, as the applicant contends, give jurisdiction to the Tribunal to award compensation to an inconvenienced applicant as a result of delay by a decision-maker prior to the institution of an application for review, the Tribunal would be slow to award compensation where the applicant chooses not to exercise its right to bring the matter before the Tribunal following a deemed refusal, but rather to continue to pursue the matter with the original decision-maker.
42 Given that there was a necessity to advertise the application made to the respondent, it could not realistically be expected that the application would be dealt with by the council of the respondent earlier than its October meeting. Indeed, in his affidavit, Mr Callow asserts that, if the planning officer's report to council had been prepared more expeditiously, the development application should, in his experience, have enabled consideration by council at "either its October 2004 or November 2004 meetings".
43 During October there were communications between the applicant's representatives and the respondent's planning officers concerning issues which the respondent had identified in relation to the original application. Revised plans were lodged at the beginning of October. Meetings and correspondence continued through November and the matter was then dealt with at the council's meeting in December. We accept Mr Callow's assertion that, in the usual course, it would be reasonable to expect that the application would have been dealt with by the November meeting of council. However, the fact that it was not dealt with until the next meeting after the November meeting does not indicate inordinate delay.
44 The applicant relies, as a foundation of its application, on Mr Callow's contention that the actions of the Shire unnecessarily delayed the development by nine months. He makes that assertion based on the fact that the matter should have been dealt with at the October or November 2004 meetings of council which would have allowed documentation to proceed and a building licence to be applied for so that construction could have commenced in early January 2005. He said in his affidavit sworn 13 July 2005 that the earliest that construction could now commence is October 2005. He also asserts that if the development application had been approved at the December 2004 council meeting, he would have advised the applicant to appeal against any unacceptable conditions but otherwise to seek to progress the implementation of the development. Finally, he asserts that, based on his experience, the actions of the Shire caused the applicant to unnecessarily engage experts and incur costs that would not ordinarily be required to assess the development application of this scale.
45 A number of observations can be made about Mr Callow's assertions. The first is that there is no explanation as to why there would have been a delay of only six weeks to commence construction if approval was granted in November 2004, but there would be a delay of at least four months between the Tribunal's approval of the development in June 2005 and the commencement of construction.
46 The second is that it is clear that, whenever council had considered the matter, its approval would have included the conditions which the applicant found unacceptable, and which became the subject of the proceedings before the Tribunal. The applicant would have appealed against those conditions. It is highly likely that the appeal proceedings would have hindered the implementation of the development.
47 Given the fact that the total period from initial lodgement of the development application with the respondent to delivery of the Tribunal's reasons amounted to approximately nine months, the suggestion that the actions of the respondent caused a delay of nine months appears quite untenable.
48 Based on his personal experience with the applicant, Mr Callow deposes to the fact that the applicant has not had to engage the services of a town planner or legal consultant to gain a development approval in respect of similar developments before. Presumably, that assertion is made to support Mr Callow's proposition that the engagement of consultants in this case was necessary because of "the actions of the Shire in processing the development application". Precisely which actions Mr Callow is referring to are not specified. Presumably what is referred to are the earlier difficulties to which Mr Callow deposes in obtaining information from and generally dealing with officers of the respondent.
49 It is well known that developers frequently engage the assistance of consultants to assist in the development approval process. A decision to do so is a matter entirely within the discretion of the developer. No doubt, some local governments are more demanding than others as to requirements they impose upon applicants in the development process. In this matter, the respondent's officers did raise concerns about aspects of the proposed development in the months after the application was lodged. There was no suggestion that the concerns were baseless, and indeed the applicant revised its plans to cater for some of the concerns raised. Whatever frustrations the applicant may have felt about issues raised by the respondent, there is no basis in the evidence for concluding that the raising of those issues was in any way unreasonable.
50 Although the applicant complained that, at the meeting of 20 December 2004, the council of the respondent if properly advised, would have granted a conditional approval, rather than resolved to endorse the officer's recommendation for conditional approval, in our view, the distinction is of little substance. It was quite clear, from 20 December 2004 onwards, that the respondent was willing to approve the development subject to specified conditions. It contemplated the execution of the consent order to that effect in the Tribunal proceedings. The appeal proceeded in precisely the same manner as it would have proceeded were it an appeal against the conditions of an approval granted on 20 December 2004. In our view, the evidence does not support the proposition that the respondent did not genuinely attempt to make a decision on the merits of the application.