Whether written request received
Whether approval given
Value of variations agreed
Percentage completion at 20/12/04
Amount of back charges
Comments as at 2/12/04
35 The first two headings and the fifth heading are likely to truly be "reasons for withholding payment" which did not appear in the payment schedule.
36 If one studies the individual items there are three items, namely, 8, 26 and 27 where the only question raised is the amount of work completed. These three claims totalled $15,321 and they were allowed in the adjudication response in an amount of $3,375. The response gave an explanation why the amount was less. However, as items 26 and 27 were not dealt with in the payment schedule the Adjudicator could not consider them. One is left, item 8, which is the additional aluminium domino façade panels on the Riley Street elevation.
37 The payment claim was for the balance of the 100% of the total value of this item, namely, $6,000. The payment schedule allowed it in full but the adjudication response sought to bring that previous concession back to 30%. In these circumstances the adjudication response indicates a matter which was not indicated in the payment schedule and correctly was not taken into account by the Adjudicator.
38 Thus there appears to be no matters in the adjudication response which the Adjudicator should have taken into account on the variations.
39 If there had been such a breach it would have been one of the more detailed requirements of the Act and does not of itself make the determination void. It may have, however, been a breach of the rules of natural justice a point I will consider below.
Application of the rules of natural justice
40 In careful submissions the plaintiff brought to my attention a series of cases where Court considered the content of the requirement to give natural justice. As an example reference was made to Xuereb v Viola (1989) 18 NSWLR 453 where Cole J, who was considering whether a referee's report should be adopted, had the following to say (at 469):
"Quite apart from Pt 72, r 11(c), natural justice requires that a referee give reasons for his opinion. This is not just to permit the court better to exercise its functions under Pt 72, r 13. The deeper reason is that it enables the parties and the disinterested observer to know that the opinion of the referee is not arbitrary, or influenced by improper considerations but is the result of a process of logic and the application of a considered mind to factual circumstances. I adopt, with respect, the passage in the judgment of Samuels JA in Strbak v Newton (Court of Appeal, 18 July 1989, unreported), in speaking of the requirements for reasons in the judgment of a District Court judge, as being an appropriate statement of principle applicable to the statement of reasons required by a referee:
... "it is going too far to suggest that in every case a judge must submit the material before him or her to the most meticulous analysis and carry into judgment a detailed exposition of every aspect of the evidence and the arguments. What is necessary, it seems to me, is a basic explanation of the fundamental reasons which led the judge to his conclusion. There is no requirement, however, that the reasons must incorporate an extended intellectual dissertation upon the chain of reasoning which authorises the judgment which is given.
In the present case, the reasons are certainly succinct; but that is often to be regarded as a judicial virtue. Trial judges must always endeavour to balance their duty to explain with their duty to be brief".
41 In their submissions the plaintiff referred to cases which had followed this approach and also a line of cases which suggested to the contrary. These cases were ones that dealt with courts, tribunals, or other bodies rather than an Adjudicator under the Act. However the problem has been addressed specifically by the Court of Appeal in Brodyn Pty Ltd v Davenport [2004] NSWCA 394. In the majority judgement Hodgson J distinguished between the basic and essential requirements and the more detailed requirements for the purposes of determining whether a breach may make the determination void. He said:
"53 What then are the conditions laid down for the existence of an adjudicator's determination? The basic and essential requirements appear to include the following:
1. The existence of a construction contract between the claimant and the respondent, to which the Act applies (ss.7 and 8).
2. The service by the claimant on the respondent of a payment claim (s.13).
3. The making of an adjudication application by the claimant to an authorised nominating authority (s.17).
4. The reference of the application to an eligible adjudicator, who accepts the application (ss.18 and 19).
5. The determination by the adjudicator of this application (ss.19(2) and 21(5)), by determining the amount of the progress payment, the date on which it becomes or became due and the rate of interest payable (ss.22(1)) and the issue of a determination in writing (ss.22(3)(a)).
54 The relevant sections contain more detailed requirements: for example, s.13(2) as to the content of payment claims; s.17 as to the time when an adjudication application can be made and as to its contents; s.21 as to the time when an adjudication application may be determined; and s.22 as to the matters to be considered by the adjudicator and the provision of reasons. A question arises whether any non-compliance with any of these requirements has the effect that a purported determination is void, that is, is not in truth an adjudicator's determination. That question has been approached in the first instance decision by asking whether an error by the adjudicator in determining whether any of these requirements is satisfied is a jurisdictional or non-jurisdictional error. I think that approach has tended to cast the net too widely; and I think it is preferable to ask whether a requirement being considered was intended by the legislature to be an essential pre-condition for the existence of an adjudicator's determination.
55 In my opinion, the reasons given above for excluding judicial review on the basis of non-jurisdictional error of law justify the conclusion that the legislature did not intend that exact compliance with all the more detailed requirements was essential to the existence of a determination: cf. Project Blue Sky Inc. v. Australian Broadcasting Authority (1998) 194 CLR 355 at 390-91. What was intended to be essential was compliance with the basic requirements (and those set out above may not be exhaustive), a bona fide attempt by the adjudicator to exercise the relevant power relating to the subject matter of the legislation and reasonably capable of reference to this power (cf. R v. Hickman; Ex Parte Fox and Clinton (1945) 70 CLR 598), and no substantial denial of the measure of natural justice that the Act requires to be given. If the basic requirements are not complied with, or if a purported determination is not such a bona fide attempt, or if there is a substantial denial of this measure of natural justice, then in my opinion a purported determination will be void and not merely voidable, because there will then not, in my opinion, be satisfaction of requirements that the legislature has indicated as essential to the existence of a determination. If a question is raised before an adjudicator as to whether more detailed requirements have been exactly complied with, a failure to address that question could indicate that there was not a bona fide attempt to exercise the power; but if the question is addressed, then the determination will not be made void simply because of an erroneous decision that they were complied with or as to the consequences of non-compliance."
42 It is plain that a failure to make a bona fide attempt to exercise the relevant power and a substantial denial of the measure of natural justice, that the Act requires to be given can lead to a determination being void. His Honour went on to describe the measure of natural justice that the Act requires in paragraph 57, in these terms:
"57 The circumstance that the legislation requires notice to the respondent and an opportunity to the respondent to make submissions (ss.17(1) and (2), 20, 21(1), 22(2)(d)) confirms that natural justice is to be afforded to the extent contemplated by these provisions; and in my opinion, such is the importance generally of natural justice that one can infer a legislative intention that this is essential to validity, so that if there is a failure by the adjudicator to receive and consider submissions, occasioned by breach of these provisions, the determination will be a nullity. On this basis, I agree with the result reached in Emag Constructions Pty. Ltd v. Highrise Concrete Contractors (Aust) Pty. Ltd [2003] NSWSC 903. I note there is some controversy as to whether denial of natural justice generally results in voidness or voidability (see for example Ridge v. Baldwin [1964] AC 40, Durayappah v. Fernando [1967] 2 AC 337, Banks v. Transport Regulation Board (Vic ) (1968) 119 CLR 222 at 233, Calvin v. Carr [1980] AC 574 at 589-90, Minister for Immigration v. Bhardwaj (2002) 209 CLR 597 at 630-34); but in my opinion, in cases such as this where there is a disclosed legislative intention to make a particular measure of natural justice a pre-condition of validity, failure to afford that measure of natural justice does make the determination void."
43 The provisions to which His Honour refers are of course the provisions for submission of various responses to the Adjudicator in the course of making his determination. His Honour has indicated the ambit of the measure of natural justice the Act requires by extending it beyond the basic and essential requirements, which he identified in paragraph 53, to cover the particular process during the adjudication that he there identified. His Honour had earlier noted that the requirement to give reasons was not one of the basic and essential requirements.
44 The particular question did not arise for decision in Brodyn. However His Honour's classification of the status of the provision of reasons is a strong indication that it is not one, a failure of which might extend the reach of the measure of natural justice that the Act requires to be given. I appreciate the force of the reasons given by Cole J for extending the rules of natural justice to a failure to give reasons. In paragraph 51 of his judgment, Hodgson JA refers to the legislative scheme, the intention to give a quicker entitlement to progress payments with a minimum of delay and the minimal opportunity for court involvement. In particular His Honour pointed to the necessity for confining the ambit of court intervention.
45 In these circumstances it seems to me that the measure of natural justice that the Act requires to be given does not extend to giving of reasons under s 23 of the Act but does extend to a failure to consider submissions under s 22(2)(d) of the Act.
The failure to provide adequate reasons
46 Under section 22(3)(b) of the Act it is provided that:
"The adjudicator's determination must:
(a) …
(b) include the reasons for the determination (unless the claimant and the respondent have both requested the adjudicator not to include such reasons in the determination)."
47 The "reasons" provided by the Adjudicator for two crucial findings in paragraphs 14(b)(iv) and 16(f) of his Adjudication Determination were said by the plaintiff to be grossly inadequate. Those paragraphs are as follows: