[5] Unless otherwise indicated, I accept the evidence given in the various statements as to the following facts.
[6] Mr. Richard Chester, the owner of a property at 57 Carew Street, Nundah, Queensland entered into a Master Builders Residential Contract, dated 10 November 2006, with a builder Thunder Corp Pty Ltd for the performance of building work at the property for a price of $31,000.00. The builder's representative was Mr Matthew Hadad_._
[7] Building work commenced on 30 January 2007. The contract provided for a construction period of 110 days. Annexure 1 to the contract (said to take precedence) provided for "start within 3 weeks of contract sign and completion 22 weeks or uninterrupted construction time".
[8] The owner was in occupation of the house at the time of commencement of work until the end of March 2007.
[9] Drainage approval was not obtained by the owner until April 2007. Little work was performed prior to April 2007. This affected the originally planned sequence of works.
[10] On 3 July, Mr Hadad advised the owner in writing of a time estimate for the works, with Practical Completion to occur on 10 October 2007. No formal complaint appears to have been made about this time estimate at the time it was given.
[11] During the period August 2007 to December 2007 there was consistent rainfall which affected the progress of the works, in particular the steepness of the site made access difficult as a result of the rain. Mr Hill's statement attaches Bureau of Meteorology rainfall records which indicate that during the period May to December 2007, rainfall occurred on 63 days. During the period 16 August to 30 December 2007 there were 45 days where it rained. This left only 47 working days during that four and a half month period where it did not rain.
[12] A building boom taking place at the time made it difficult to engage tradesmen in a timely way.
[13] Variations were requested by the owner, including an additional concrete patio slab, additional stumping, a block and blanket variation and additional bathroom plumbing.
[14] On 9 October 2007 the applicant informed the owner that the estimated completion time was a further 37 days, and that taking into account delays, the contract was 16 days behind as at 9 October 2007. No formal complaint was made about the time estimate at the time it was given.
[15] On 9 October 2007 the builder sent the owner a progress claim for $28,128.00 in accordance with a new payment schedule, including the costs of additional work to the bathroom and under roof blanket.
[16] By email dated 15 October 2001, the owner sent the applicant a list of "Defects, Omissions or Concerns".
[17] On 22 October 2007 the applicant notified the owner of a suspension of work due to non payment of a $28,128.00 progress claim. The owner paid the sum of $28,000.00 on 30 October 2007.
[18] The owner states that he does not recall the builder returning to site from then on, however, as at 12 November 2007 a revised layout for the external and internal stairs was received by Mr Hadad from the owner and he notified the owner of rain preventing site access. During November the owner and Mr Hadad were discussing an engineer's inspection of the footings and that was being attended to. It is also apparent that in December, Mr Hadad met the carpenter Mr Spinelli on site to discuss future work and that he met the foreman and skilled labourer, Mr Robert on site and arranged for them to commence work in January 2008. In December 2007 the concreter was booked to re-commence in January 2008.
[19] Mr Hadad advised the owner in early December 2007 that he had booked tradesmen to perform work in January. That is supported by the statements of Mr Spinelli, Mr Healy and Mr Robert. Mr Hadad advised the owner that he was taking 4 weeks leave from the Christmas/New Year period and that trades and suppliers all stop work over that period.
[20] On 6 December 2007 the owner emailed Mr Hadad making complaint about delays and requesting an answer by Sunday, 9 December 2007 as to Mr Hadad's intentions in relation to fulfilling the contract. He attached the document headed "Defects Omissions or Concerns".
[21] The builder and the owner exchanged proposals in relation to completion of the contract outside the contract's terms on 10 and 11 December 2007. Neither proposal was accepted.
[22] In an email sent on 10 December 2007 Mr Hadad told the owner that "projected completion is now around mid March".
[23] Mr Hadad went on Christmas holiday. He told the owner he was going on holiday, although it is not clear exactly when he told him or when he left for his holiday.
[24] On 19 December 2007 the owner forwarded to the applicant, by facsimile transmission a Notice of Intention to Terminate contract and attached the list of Defects, Omissions and Concerns.
[25] The owner made several attempts to deliver the Notice of Intention to Terminate, including emailing the applicant and sending the notice to Mr Hadad's father's business address.
[26] Despite this the applicant says that the Notice of Intention to Terminate did not come to his attention until after his return from holiday in January 2008. By then the time frames set by the owner had expired.
[27] On reading the 19 December 2007 fax, Mr Hadad says that he did not think the applicant was in breach of the contract.
[28] Mr Hadad says he assumed the owner had engaged another builder. Mr Hadad asserts the owner had threatened to do so in a number of earlier conversations between them. (This is denied by the owner and I make no finding in this regard.)
[29] Mr Hadad did not contact the owner, but instead cancelled the tradesmen he had booked and treated the contract as at an end.
[30] On 14 February 2008 the respondent informed the applicant that a complaint had been received from the owner. Changed postal and contact details were provided to the respondent on 15 February 2008.
[31] The respondent subsequently sent notice of a site inspection to the builder at a wrong address and it was not received.
[32] Mr Huttunen, of the respondent attended a site inspection with the owner and prepared a report, dated 25 February 2008. I make no findings in relation to the contents of the report but note that it concluded:
- the owner has provided a comprehensive list of works that he considers defective or incomplete. However this work cannot be said to be defective in that it is still in the process of construction and most areas are constructed to industry standards.
- 95% of frame stage.
- licensee appears to have abandoned the work prior to the owner termination of the contract.
- recommendation: file to insurance for assessment as licensee is bankrupt see folio text.
- obvious defects