(2) In those circumstances, the claimant:
(a) may:
(i) recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or …
6 Section 14(4) is in the following terms:
14 Payment schedules
…
(4) If:
(a) a claimant serves a payment claim on a respondent, and
(b) the respondent does not provide a payment schedule to the claimant:
(i) within the time required by the relevant construction contract, or
(ii) within 10 business days after the payment claim is served,
whichever time expires earlier,
the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates.
7 It is not in issue that the claim was a payment claim within the meaning of s 13 of the Act.
8 It is also not in issue that the defendants did not within the time period provided by s 14(4)(b) of the Act serve a payment schedule.
9 No document which could constitute a payment schedule was served until 9 May 2008 when a document dated 5 May 2008 (which it is accepted by the plaintiffs would have constituted a payment schedule within the meaning of the Act) was delivered to the plaintiffs.
10 The period of 10 business days provided for in s 14(4)(b)(ii) expired on 14 May 2008. Accordingly unless s 14(4)(b)(i) applies (because the contract requires the service of a payment schedule as contemplated by that section at an earlier point in time), that is before 9 May 2008, the service of the payment schedule would be effective.
11 The first issue between the parties was whether the contract so provides.
12 On 17 June 2008 the defendants filed a Technology and Construction List Response, which in addition to responding to the first issue claimed that the plaintiffs, in the circumstances, by serving the claim in the form it took engaged in conduct which was misleading or deceptive or likely to mislead or deceive in contravention of s 52 of the Trade Practices Act 1974, or engaged in conduct which was unconscionable within the meaning of s 51AA of that enactment.
13 Before me, the plaintiffs were represented by Mr Christie and Miss Culkoff of counsel and the defendants by Mr Corsaro of senior counsel and Mr Miller of counsel.
14 During the course of the hearing the parties through their respective counsel agreed and informed the Court that if the defendants succeeded on the first issue it would not be necessary to deal with the second issue, which I otherwise would have done. The effect of this agreement is that the plaintiffs agreed to accept as final and conclusive defeat, a loss on the first issue. There would in that event be no necessity for me to make a finding either way as to whether the plaintiffs had engaged in the conduct complained of.
15 Turning then to the first issue, although I was referred to no authority dealing expressly with the approach to be taken in determining whether a provision in a contract satisfies the requirement of supplanting the period provided in s 14(4)(b)(ii) of the Act, the parties agreed that the test is whether, on the proper construction of the Contract, the parties intended that its provisions were to supplant the provisions of s 14(4)(b)(ii).
16 There was further agreement that, in the present context, as was stated by Mason P in Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448 at 458 (in a different context), there must be clear contextual support for the necessary implication that the Contract provided an answer to the particular problem.
17 The only candidate put forward as being a provision under which the Contract required a payment schedule earlier than under the Act is cl 14.3A which is in the following terms:
"The Trustee must issue a payment schedule within 4 Business Days of receipt of the payment claim (including the payment claim made pursuant to clause 14.6(a)). The payment schedule must identify the payment claim to which it relates and if it is for an amount less than the claimed amount, the payment schedule must indicate why the amount stated in the payment schedule as payable is less and if it is less because the Trustee is withholding payment for any reason, the Trustee's reasons for withholding payment, provided that the amount stated in the payment schedule may not be less than the amount certified by the Independent Verifier under the certificate referred to in clause 14.2(a) except as otherwise expressly provided by this deed, including clauses 14.5, 14.10 and 14.12."