© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2002] VSCA 195
Court of Appeal (Vic)
2002-12-04
CALLAWAY, BUCHANAN and VINCENT, JJ.A.
Original judgment source is linked above.
[ 2002] VSCA 195
Contract for hire of trucks - Separate hire rates for "working hours" and "standby hours" - Guaranteed minimum of 21,000 working hours - Whether owner entitled to additional payment in respect of standby hours.
"We reference your facsimile from Trawool and accept payment terms and methodology outlined in your schedule. Accordingly, we now believe that the matters outlined in the various correspondences are resolved and agreed. We are making tentative arrangements to attend site on Tuesday for an inspection prior to finalisation of our agreement. We would be pleased to receive your confirmation by way of a letter of intent pending further formal documentation and your advice of any other matters that we should consider."
"Where parties who have been in negotiation reach agreement upon terms of a contractual nature and also agree that the matter of their negotiation shall be dealt with by a formal contract, the case may belong to any of three classes. It may be one in which the parties have reached finality in arranging all the terms of their bargain and intend to be immediately bound to the performance of those terms, but at the same time propose to have the terms restated in a form which will be fuller or more precise but not different in effect. Or, secondly, it may be a case in which the parties have completely agreed upon all the terms of their bargain and intend no departure from or addition to that which their agreed terms express or imply, but nevertheless have made performance of one or more of the terms conditional upon the execution of a formal document. Or, thirdly, the case may be one in which the intention of the parties is not to make a concluded bargain at all, unless and until they execute a formal contract."
"We refer to your Plant Hire Order No 83301. Following a visit to the site of the works, supplementary discussions with yourself and site personnel, we herewith confirm the terms and conditions under which the hire arrangements will operate between Thiess and Howtrac. * Equipment supply: 6 No 773B Dump Trucks * Hire rate: $95 AUD/working hr (Keinzle measure) $60AUD/standby hr * Minimum Guaranteed 21,000 working hours aggregate Hours of Hire: based on 4 trucks Ex Japan being delivered to site prior to the end of September and the final two trucks by 15 Oct. * Period of hire: 25th September 1997 to 25 November 1998. * Payment Terms: 30 days from the end of the month of invoice and as detailed in special conditions attached."
"SPECIAL CONDITIONS
* Minimum paid hours per month per unit is 250 hours or Keinzle clock hours, whichever is the greater. * Standby hours paid at $60/hr only * Working hours paid at $95/hr * Example of monthly payment calculations and treatment of standby hours prior to achievement of minimum aggregate hours.
* Minimum guaranteed hours for all units 21,000 Keinzle hours subject only to availability of trucks by Howtrac. To achieve these total hours units will need to be available for a minimum of 100 hrs work per week (6 days, 2 x 10 hour shift). Total hours to be available within 14 months starting 25th September 1997 and completing no later than 25th November, 1998.
...
Plant will not be paid for when plant broken down and/or not available to work.
..."
* Howtrac is to be paid for a minimum of 250 hours per month per unit. Working hours are to be paid for at the rate of $95 per hour and standby hours at the rate of $60 per hour.
* In the second month the truck works 250 hours. There is no need for any make up. Howtrac is paid for those hours at the working rate.
* In the third month the truck works more than the minimum 250 hours. Prima facie Howtrac is entitled to be paid for all those hours at $95 per hour, but Thiess is allowed a credit for the 50 standby hours at $60 per hour that it paid for in the first month to make the hours up to the minimum of 250.
* In the fourth month the truck works 350 hours. Howtrac is paid for all those hours at the working rate. Thiess is not allowed a credit, because there are no longer any standby hours for which it paid in a previous month that have not already been credited to it. It does, however, acquire a credit of 100 hours.
* In the fifth month the truck again works only 200 hours. Howtrac is entitled to be paid for those hours at the working rate and, as we saw in the first month, would be entitled to be paid for a further 50 hours at the standby rate. But it is not paid for those 50 hours. Thiess draws on the credit of 100 hours that it acquired in the fourth month.
* In the sixth month Thiess acquires a further 100 credit hours. In the fifth month it used 50 of the 100 credit hours acquired in the fourth month. Accordingly it carries forward a credit of 150 hours, to be used as and when working hours fall below the minimum of 250 hours.
"The minimum 21,000 working hours could have been achieved within an eight months' period. If the reasonable bystander had put a question to the contracting parties on 12 August 1997 that if the works progressed for eight months without interruption and then there was a period of some two months during which the plant was rarely used, would it be expected in those circumstances that Howtrac would be paid standby? In my opinion the parties acting reasonably at that time would have both answered in the affirmative. Both expected the works to continue without interruption and both could not deny the possibility of an interruption which may be substantial which would affect Howtrac's ability to derive income from the hire of its plant. These large trucks were sent to New Zealand. Howtrac's business is located in Victoria. It would hardly be in its commercial interest to not expect to be paid standby time when its trucks were standing idle for extensive periods of time. It is not as if it could take back the trucks and re-hire them for a short period to someone else. "
"The payment regime was to ensure payments were made each month at minimum levels. But this was not inconsistent with a final reconciliation and full payment for standby time at the end of the job. It was never intended by the parties at the time of the agreement that there would be a large amount of standby time. The works were intended to continue without interruption. However, due to unforeseen events, particularly the necessity to alter the scope of the works, involving reshaping the right abutment requiring the removal of extra rock and excavation of rock spurs within the cut-off trench, the excavation process was considerably slowed down. As a result, in the period between December, 1997 and February, 1998 trucks remained idle for a large period of the time and were only used intermittently, even though they were still required to be made available for use. As a result, the trucks were on standby for long periods. It was to cover this kind of unexpected contingency that an entitlement to be paid for standby was clearly incorporated into the agreement. The 21,000 minimum working hours was the incentive provided to Howtrac to acquire and make the trucks available in new Zealand, not to cover risk of unforseen standby time due to events beyond the control of Thiess." (Appeal book references omitted.)
unnecessary to refer to Thiess's correspondence with the Electricity Corporation of New Zealand.
[2] There was a further limitation, "prior to achievement of minimum aggregate hours", which did not apply, because the minimum was not achieved: see the table in [11] and [13] below.
[3] The notice of appeal does not expressly refer to the statutory interest but it is obviously meant to be included. The "orders sought" part of the notice asks that the judgment in respect of Howtrac's entitlement to standby charges be set aside and in lieu thereof it be adjudged that Howtrac was not entitled to any of the standby charges which it claimed. No declaration having been sought in the pleadings, variation of the judgment would be sufficient.
[4] [1954] HCA 72; (1954) 91 C.L.R. 353 at 360.
[5] That being so, it is unnecessary to decide the significance of Mr Golvan's submission that Thiess's argument as to the composition of the contract had been significantly different at trial.
[6] See the first sentence of the extract from Mr Howard's fax set out at [9].
[7] The standard conditions also included an "entire agreement" clause. Mr Golvan referred to that clause but, in the light of the conclusion I have reached as to the composition of the contract, it is unnecessary to consider it.
[8] There was a dispute as to that mode of calculation, but the judge accepted Howtrac's calculation and it is no longer challenged.
[9] Neither side attached importance to the fact that the table applies to each unit and not to all six units, so that, for example, there is no credit if one truck works for 260 hours and another truck for 240 hours.
[10] The relationship is part of the essential background. It is the way in which "credit hours", including credit dollars, are dealt with that is important.
[12] Reference was made to Lewison, The Interpretation of Contracts (2nd ed 1997), s2.05; Squarey v. Harris-Smith (1981) 42 P. & C.R. 118 at 129 and Ladbroke Group Plc v. Bristol City Council [1988] 1 E.G.L.R. 126 at 128.
[13] Cf. Macdonald v. Longbottom [1859] EngR 635; (1859) 1 El. & El. 977; 120 E.R. 1177.
[14] [1982] HCA 24; (1982) 149 C.L.R. 337 at 352.
[15] As it would not alter my conclusion in this case, I leave for another day the significance of terms being progressively agreed.
[17] It is unnecessary to consider what the position would have been if plant had been broken down and/or not available to work for such long periods that it was not reasonably practicable for Thiess to achieve 21,000 working hours.
[18] FAI Traders Insurance Co. Ltd. v. Savoy Plaza Pty. Ltd. [1993] VicRp 76; [1993] 2 V.R. 343 and Ryan v. Textile Clothing & Footwear Union of Australia [1996] VicRp 67; [1996] 2 V.R. 235 at 237-238 and 261-262.
Thiess Contractors (NZ) Ltd
Howtrac Rentals Pty Ltd [2002] VSCA 195