The Owners - Strata Plan No 77559 v Touma; Touma v The Owners - Strata Plan No 77559
[2022] NSWCATAP 186
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2021-03-15
Source
Original judgment source is linked above.
Judgment (17 paragraphs)
Background
- The strata scheme comprises 64 residential lots. The construction of the property was carried out by Statewide Developments Pty Ltd (Statewide). Mr Mounir Touma was appointed a director of Statewide on 26 October 2010. The works to build the property were contracted for in 2006 and an occupation certificate for the scheme, essentially excluding the penthouse, was issued on 7 February 2007. Mr Touma purchased the penthouse in the Strata Plan from Statewide on 16 March 2011. The penthouse extends over a number of levels which include bedrooms, a main living area, a raised swimming pool with a vergola and an open terrace containing landscaped gardens with planter boxes.
- It is not in dispute that water penetrated the penthouse. In 2012 the Owners Corporation engaged RHM Consultants to inspect and report on the water ingress. A report identified 28 items related to water ingress from the level 6 terrace and included a scope of work to rectify the water entry. The report identified internal water damage within the penthouse at levels 6 and 7. Statewide carried out rectification work including external tiling to level 6.
- In 2013 remedial building works were commissioned by the Owners Corporation to waterproof the level 6 terrace. The works involved the removal of the planter boxes, removal of tiles, waterproofing and re-tiling on level 6. The joint experts agreed that those works have not rectified that defect.
- In January 2015 the Lot Owner observed damage to the garage doors servicing his garage spaces. The Owners Corporation carried out works to the garage doors. The works did not rectify the defective garage doors.
- Water penetrations in the penthouse were reported by Mr Touma in April 2015 and January 2016. An electrical fire occurred on 16 March 2017 attributed to further water penetration rendering the penthouse's vergola, the C-bus system and other electrical equipment inoperable.
- On 22 February 2018 Mr Touma made an application to the Tribunal. Mr Touma sought orders against the Owners Corporation for repairs to common property of the strata scheme, carrying out of works to his lot necessitated by water penetration through the common property roof, windows, doors, tiling and waterproof membrane defects and repair of damage allegedly caused to his lot by the Owners Corporation tradespersons entering the lot to conduct works. In the alternative Mr Touma was seeking damages. By the time the matter came to hearing Mr Touma was also seeking orders under s106 of the SSMA regarding the Owners Corporation's failure to comply with the statutory obligations to maintain the common property, including ongoing water penetration in the applicant's lot, damage to the applicant's garage door and damage occasioned to other parts of his unit by previous repair attempts by the Owner's Corporation.