The proper construction of the Development Agreements
35Mr Roberts referred to Casa Maria Pty Ltd v Trend Properties Pty Ltd [1998] NSWCA 53 and Midori v Newkarna (Supreme Court of New South Wales, Coll J, 20 April 1994, unreported) and submitted that those cases stood for the propositions that: -
(a)a contract may contemplate that work be carried out under a separate building contract with another builder but still itself be a contract to do residential building works; and
(b)the true test is whether or not there is an enforceable agreement in the first contract to get the building works done.
36Mr Roberts submitted that a conventional building contract is one "to get the work done, more often than not by subcontractors". He pointed to s 6(1)(a) of the Act which provides that s 7 of the Act (which specifies, amongst other things, that a building contract must be in writing) applies to contracts under which the holder of a contractor licence undertakes "in person, or by others" residential building work. Thus, Mr Roberts submitted, the Act contemplates that a building contract to which the Act applies may provide for the work to be done by someone other than a party to the contract.
37These submissions may be correct, as a matter of generality. However, in my opinion, the answer to the question before me lies in the proper construction of the terms of these Development Agreements.
38Statements made in the context of differently worded agreements are of little, if any, assistance.
39There was no debate before me as to the principles to be applied in relation to the construction of commercial contracts.
40They were recently restated in Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012] NSWCA 184. Bathurst CJ (with whom Macfarlan and Meagher JJA agreed) said (at [52]): -
"The principles underlying the construction of written contracts are well established and it is not necessary to deal with them at length. A contract is to be construed by reference to what a reasonable person would understand by the language in which the parties have expressed their agreement having regard to the context in which the words appear and the purpose and object of the transaction: Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451 at [22]; Toll (FGCT) Pty Ltd v Alphafarm Pty Ltd [2004] HCA 52; (2004) 219 CLR 165 at [40]; International Air Transport Assn v Ansett Australia Holdings Ltd [2008] HCA 3; (2008) 234 CLR 151 at [53]. At least in the case of ambiguity, resort can be had to the surrounding circumstances known to the parties in interpreting the particular provision: Codelfa Construction Pty Ltd v State Rail Authority of NSW [1982] HCA 24; (1982) 149 CLR 337 at 352; Western Export Services Inc v Jireh International Pty Ltd [2011] HCA 45; (2011) 282 ALR 604."
41Under the Development Agreements, Metro agreed to provide the "Services".
42Schedule 1 of the Development Agreements provided that "in relation to the Project" Metro must "under take the project to" perform the various tasks specified in subparagraphs (a) to (l) of Schedule 1.
43The words "Project" and "project" are used in consecutive lines. That appears to me to be a typographical error; I understand the parties to mean "project" to have the same meaning as 'Project": see generally Lewison and Hughes, The Interpretation of Contracts in Australia, (2012) at [9.02].
44I do not read cl 2.1 and Schedule 1 so as to impose upon Metro an obligation to "under take the project". That is because, in Schedule 1, the word "to" appears after the words "under take the project". In my opinion, a reasonable person would understand from this language that the parties intended Metro's obligations to be to perform the services in subparagraphs (a) to (l), and thereby "under take" "the Project"; and not to itself "under take the Project".
45None of those services constitute doing the building work itself.
46I accept, however, another reading of Schedule 1 is available, namely to read "to" as if it meant "by". If that were the better reading of Schedule 1, it would impose on Metro an obligation to undertake the Project "by" performing the enumerated services. However, this is not the reading of Schedule 1 that I favour.
47Even if I am wrong and Schedule 1 should be construed as I have set out in the preceding paragraph, further ambiguity arises by reason of the definition of "Project".
48That definition refers to the "management of the approval process" and the "design and development" of the Property and then adds, somewhat obscurely, "by the constructions of the Works".
49Those words can be read two ways; as either including in the definition of "Project" no more than obligations to manage the approval process and design and development of the land. Or they could be read as including a further obligation, namely to carry out one or both of those functions "by the construction" of the Works.
50There are two factors at play that may assist resolving these ambiguities. Unfortunately, they each point in opposite directions.
51The first is that Recital (d) (see [29] above) states that Baron had appointed Metro to undertake not only the project management and development of the Project but also the "construction" of the Project.
52The Recitals to a contract can be used as an aid in construction, at least to determine the meaning of an ambiguous operative provision: Franklins Pty Ltd v Metcash Trading Ltd [2009] NSWCA 407; (2009) 76 NSWLR 603 at [380]; and see Lewison, The Interpretation of Contracts, 5th ed (2011) at [10.13]; (there appears to be no corresponding reference in the Australian edition of this work).
53Recital (d) suggests that the parties contemplated that Metro was to "undertake ... construction" of the Project. However, I do not find the suggestion to be a strong one, especially in light of the fact that the immediately preceding recitals state that Metro has agreed to "develop" (not "construct") the Project on behalf of Baron and that Metro has engaged Baseline "to construct" the Project. I appreciate that Metro is described in the agreements as "head contractor" (see [34(b)] above), and that head contractors commonly engage subcontractors. Nonetheless, I do not consider recital (d), when read together with the earlier recitals, to be of great assistance in resolving the ambiguities to which I have referred.
54On the other, if the Development Agreements are to be construed as a contract by Metro to do residential building work, Metro, by entering into the contract, was in breach of s 4 of the Act as it did not hold a contractor licence as required by that section.
55That would be a strange result, especially in circumstances where, in cl 2.4 of the Development Agreements (see [34(a)] above), the parties have, in terms, addressed the requirements of the Act. In cl 2.4 Metro promised that it would not perform any work requiring a licence under the Act, unless it held such a licence.
56If a contract is ambiguous, the construction of a contract which results in the parties (or one of them) acting lawfully is to be preferred to a construction which results in the party or parties acting unlawfully: Global Network Services Pty Ltd v Legion Telecall Pty Ltd [2001] NSWCA 279 at [102] per Mason P citing with approval Lewison, The Interpretation of Contracts, 2nd ed (1997) at [6.09]; repeated in the 5th ed at [7.11] and in Lewison and Hughes at [7.10].
57The construction for which Mr Roberts contended attributes to Metro an understanding that it should not, and a promise that it would not, perform any work requiring a licence under the Act unless licensed; but an intention to contract to do work requiring a licence without having such a licence, thereby putting itself in breach of the Act. That is, Mr Roberts' construction attributes to the parties an intention that Metro act unlawfully.
58It seems to me most unlikely that the parties so intended. This fortifies my conclusion that my reading of Schedule 1 set out at [44] above is the correct one.
59My conclusion is therefore that, by the Development Agreements, Metro did not agree to do residential building work.