The Owners Corporation SP 70798 v Bakkante Constructions Pty Limited
[2014] NSWSC 147
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2014-02-24
Before
Pembroke J
Source
Original judgment source is linked above.
Judgment (15 paragraphs)
Introduction 1This is an unusual interlocutory application brought by the plaintiff owners corporation. It is eight months since I gave what I thought was effectively a final judgment disposing of proceedings that had been referred to me as Expedition Judge: [2013] NSWSC 848. In my judgment I answered the questions posed for determination. Those questions were designed by the parties to encompass the issues in dispute. The last question was 'Is the consequence of (a) to (d) that the proceedings must be dismissed?'. The answer I gave was 'Yes'. I then ordered the plaintiff to pay the defendants' costs. 2The central issue was whether the proceedings against the first defendant (a builder) had been commenced and conducted by the plaintiff (an owners corporation) in contravention of Section 80D of the Strata Schemes Management Act 1996 (NSW). I will not set out the terms of Section 80D but its relevant purpose and object is to ensure that an owners corporation does not initiate legal action unless a resolution is passed at a general meeting of the lot owners approving the taking of the action. The relevant statutory language is 'must not initiate legal action unless ...' 3I held that there had been non-compliance with Section 80D and that the consequence was that the proceedings were invalid and unauthorised, and hence that they should be dismissed. I made the following observations in paragraph [83] of my first judgment: The natural corollary of this regime is that actions taken by an executive committee in contravention of Section 80D, and without complying with the requirements for exemption set out in Regulation 15, should be treated as invalid and unauthorised. 'Must' means 'must'. It is an imperative - expressing necessity, obligation and compulsion. There is no halfway house; no reason for attempting to ameliorate the outcome because of the particular consequences in a given case of wasted costs or aborted legal action. Consequences such as those are the inevitable result of invalidity. They cannot control the meaning and effect of the statutory regime. In a case such as this, the executive committee, and particularly its chairman, only have themselves to blame. 4No question of ratification arose for my consideration at the first hearing although it was a natural question that might well have been raised if circumstances permitted. In fact, one of the separate questions posed for my consideration was whether any non-compliance with Section 80D had been cured by reason of a resolution of the owners corporation on 19 December 2011. However at the commencement of the hearing, senior counsel informed me that ratification was not pressed and that separate question (d) need not be determined. Ratification did not therefore arise and no prospective ratification was foreshadowed. My observations about the effect of contravention of Section 80D were not made with the possibility of ratification in mind. The issue was neither mentioned nor considered.