Terence Eve and Lindy Eve v John Boyd t/as Kalana Homes
[2014] NSWCATCD 152
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2014-06-25
Source
Original judgment source is linked above.
Judgment (5 paragraphs)
Application 1Having read the submissions by both parties received on 18, 24 and 25 July 2014 respectively the Tribunal now publishes its orders and reasons for the decision on costs. 2On 14 November 2014 Mr and Mrs Eve (the applicants) sought an order for costs pursuant to section 53(2) of the Consumer Trader and Tenancy Tribunal Act 2001 (the Act). I have read and considered the contents of the applicants' submissions. The applicant's sought the following orders: "The respondent pay the costs of the applicant as agreed or assessed. In the alternative that the respondent pay 80% of the costs of the applicant as agreed or assessed." 3The legal representative for the respondent wrote to the Tribunal opposing the orders: "The respondent submits that the parties have settled the proceedings and it is appropriate that they should bear their own costs; this is consistent with the starting point for any award of costs in Tribunal.... In the alternative... it is appropriate for the Tribunal to apportion their costs.... In accordance with their ultimate success as compared to their claim ... some 11.4% of their claim or alternatively .... The applicants have successfully recovered $50,000 against a claim for $102,732 or some 48.7% of their claim."
The applicants' case on costs 4The applicants entered into a contract with the respondent on 25 February 2010 for the construction of a dwelling at xxxxx Woodrising, NSW. Following completion in or about March 2011 the applicants identified a series of defects. The applicants requested and the respondent returned to rectify the defects. When this was not done to their satisfaction the applicants complained to the Department of Fair Trading. 5The current proceedings were commenced on 14 November 2014. The applicants filed an application against the respondent and as originally particularised, the applicants sought damages for breach agreement and breach of statutory warranties pursuant to section 18B of the Home Building Act 1989 in the sum of $102,732. The report of Pink Slip Building Reports filed with the application form squarely raised the issue of encroachment and the amount claimed was particularised as TBC 'to be confirmed'. 6The claim pursued at hearing was considerably more than originally claimed. Following the realisation that local government authority easement had been encroached by up to 900mm the damages and sought included demolition and rebuilding of the dwelling and the amount claimed was amended to $305,961. Once a 30% margin was added the applicants' total claim for damages amounted to $437,524.23. This amount was calculated on the basis of demolition of the entire dwelling and the construction of a new identical dwelling set back approximately 900mm away from the road. 7On 25 June 2014 the Tribunal made consent orders that the respondent pay $50,000 to the applicant. 8The applicants submitted that they were successful in their claim before the Tribunal and that a costs order should follow. There must be some special circumstances to justify depriving the successful litigant from costs (Latoudis v Casey [1990] 170 CLR 434). Further it was submitted there are few, if any, exceptions when awarding costs to the general approach that costs follow the event other than conduct by the successful party which disentitles the successful litigant to a costs order in his favour. It was submitted that the applicants have been wholly successful in these proceedings and there has been no adverse conduct which should deprive them of an order for costs. 9The applicants submitted they should not be criticised for commencing proceedings on all bases, including item one in the Scott schedule, the demolition and rebuild of the premises. Ultimately the local council granted an easement. At the time the proceedings were commenced there was a real and distinct possibility that the home may have to be demolished and rebuilt. The fact remained that the home was built encroaching upon an easement for batter in favour of the local government authority. At the time proceedings were commenced it was not certain whether the local government authority would grant an easement in respect of the encroachment. 10Should the local council have refused to release part of the easement and required the partial or total demolition of the dwelling, item one in the scott schedule was open for determination by the Tribunal at the hearing. It was therefore not unreasonable to maintain a claim for demolition until the local government authority granted the easement. 11It was submitted that had item one in the Scott schedule not been claimed the applicant would have been precluded from having the issue determined at the hearing. It was therefore prudent to plead the issue and to have the issue dealt with. The final confirmation in writing from the local government authority was not provided until about 24 March 2014, or some 12 weeks before the hearing. 12It is further submitted that the bulk of the experts' costs and disbursement were incurred in relation to the determining liability and quantum in relation to item 2 and following in the scott schedule (the defects). Any costs in relation to item one (the encroachment) was a surveyor's report only. The applicants submitted that virtually no costs were incurred by either party in relation to the encroachment for the determination of liability on the case of encroachment as the issue was not in dispute. The respondent's surveyor's report was requested to provide advice as to the release or partial release of the easement from the local government authority. 13The applicants submitted that Regulation 20(4) applied and sought orders that costs be payable on the ordinary basis. 14As there was no evidence before the Tribunal to suggest that the applicants acted "unjustly or unreasonably" the applicant sought orders that costs follow the event. 15On 24 June 2014 the applicants made an offer in writing that the respondent pay the applicants $50,000 plus costs of $25,000 inclusive of all legal and expert costs within 28 days of acceptance of the offer. It was a further term of the Calderbank offer that the builder carry out the balance of "legal and associated work with respect to the partial release of easement at his own costs". This offer was rejected. 16The Tribunal orders for payment of $50,000 (clear of any potential costs orders) was comparable with the applicants' offer of 24 June 2014.