Conclusion and findings
24It is common ground that the proposed development is permissible with consent pursuant to the provisions of SEPP Infrastructure. The council does not press any contentions other than those matters raised by objectors and detailed in contention 2 of Exhibit 2 and outlined at [18] above. In accordance with the provisions of s 79C(1)(d) of the EP&A Act, these matters must be taken into consideration when determining the application.
25I will deal specifically with those issues. With regard to contamination, a Preliminary Site Investigation has been undertaken and assessed by the council. In addition, the council has investigated asbestos dumping at the site. That report demonstrates that the proposed site is outside the waste disposal area and would not compromise the landfill cap. The report noted that it is likely that the site has been impacted by migration of leachate and landfill gases such as methane and that there is some contamination of ground water in the vicinity of the site. No evidence of asbestos was found on the site of the proposed tower. The report recommends certain protection measures and the preparation of environmental management plans for construction works and these recommendations have been assessed by the council and found to be satisfactory. The recommendations of the report have been incorporated into the agreed consent conditions. Having regard to the evidence, I am satisfied that the issues associated with contamination and groundwater can be satisfactorily addressed through the imposition of those conditions.
26In relation to koala habitat and Threatened Species issues, the council has assessed a flora and fauna survey conducted for the proposal and is satisfied that there are no issues that warrant refusal of consent. That report concludes "Whilst some localised impact on amphibians and lower-order prey communities such as insects and/or avoidance behaviour by birds, micro-chiropteran bats and larger mammals may result from increases in EME in the area surrounding the proposed facility, we consider any such impact to be insignificant for purposes of Sec. 5A of the Environmental Planning and Assessment Act 1979." Based on this evidence, there is no reason to refuse consent.
27The proposed tower will be visible from the playing fields when constructed and the release area to the south when developed. At the present time the vegetation associated with the koala corridor and adjacent pine species provide screening of the tower from the north. The Court notes that these pines may be removed as part of the council's work within the corridor however does not consider that the loss of those trees is such that the visual impact of the tower is unacceptable when viewed from adjoining properties, particularly given the separation distance to dwelling houses.
28The objectors suggest that a standard higher to that recommended by ARPANSA (RPS3) should apply particularly in relation to the proposed school site and threatened species considerations.
29According to its website, ARPANSA is the Australian Government's primary authority on radiation protection and nuclear safety. ARPANSA regulates Commonwealth entities using radiation with the objective of protecting people and the environment from the harmful effect of radiation. ARPANSA undertakes research, provides services, and promotes national uniformity and the implementation of international best practice across all jurisdictions.
30This issue has been considered by the Court on a number of occasions. The Chief Judge, in Telstra Corporation Limited v Hornsby Shire Council [2006] NSWLEC 133 considered this issue including the siting of towers near to schools. At [98], [99], [100] [101] and [102] he states:
98 It is not appropriate for a court to set aside or disregard such an authoritative and scientifically credible standard as the Australian Standard RPS3.........
99 Nor is it appropriate for a court to pioneer standards of its own. The creation of new standards is the responsibility of other authorities with special expertise, such as ARPANSA. ...
100 The Court should accept and apply the Australian Standard RPS3.........
101 The Australian Standard RPS3 embraces a precautionary approach. The exposure limits set are conservative relative to the scientific evidence on biological effects of exposure to RF fields. There are margins for safety in the basic restrictions and associated reference levels. The reference levels are based on worst case assumptions.......
102 Another precautionary approach advocated by the Australian Standard RPS3 is, in relation to the general public, to adopt the principle of: "Minimising, as appropriate, RF exposure which is unnecessary or incidental to achievement of service objectives or process requirements, provided this can be readily achieved at reasonable expense. Any such precautionary measures should follow good engineering practice and relevant codes of practice. The incorporation of arbitrary additional safety factors beyond the exposure limits of this Standard is not supported": section 5.7(e) of Australian Standard RPS3 at p.29.
31Having regard to the evidence, I am satisfied Telstra has followed this precautionary approach. The maximum EME level is 0.27% of the Australian Standard. The proposal in effect generates a maximum EME almost 400 times less than the ARPANSA standard.
32The Department of Education's policy states "While the Department cannot state a specific separation distance between a proposed mobile telecommunications facility and a school or TAFE campus, the Department has a preference for a distance of at least 500 metres from the boundary of the property." No scientific basis for this distance was put to the Court and, based on my comments in relation to compliance with the ARPANSA standard, I do not consider the location of the proposed tower would ultimately mean that a school could not be constructed on that land identified in the Concept Plan as Community/Educational purposes. Other constraints such as its floodprone nature and proximity to a substation are also issues that would need to be considered however it is not for this Court to go behind the process that has led to the decision to identify the site for that purpose.
33I am satisfied that the agreed conditions will ensure noise generated from the plant associated with the tower will be within acceptable limits.
34The proposed tower is to address the proposed residential development at Kings Forest but also to assist with improving in-building coverage to houses and buildings currently experiencing reduced service. Given that there has been an approval issued for the first stage of the release area and there are existing service gaps, it is not considered to be a development that is premature, it will ensure that adequate services are available for that development.
35The Court has become the consent authority so any perceived conflict of interest between the council as owner of the land and undertaking its assessment role is irrelevant.
36Two alternate sites have been suggested however, based on the available evidence, they are not satisfactory. One would require penetrate the landfill cap and the other would be more visible and not meet service requirements. Accordingly, without detailed analysis, I dismiss those options.
37I am satisfied that the proposal is lawful, is permissible under LEP and complies with the relevant provisions of the applicable State Planning Policies, the LEP and the relevant controls of the DCP as well as the objectives of the EP&AAct. The agreed conditions of consent address the issues raised in submissions.
38There being no reason why the Consent Orders should not be made, by consent, the Orders of the Court are:
(1)The appeal is upheld.
(2)Development Application DA13/0201 for a proposed telecommunications facility including a 30-metre monopole, two panel antennas and an equipment shelter at Lot 1 DP 397082, known as 80 Depot Road, Kings Forest is determined by granting consent to that application, subject to the conditions in Annexure "A".
(3)The exhibits, other than exhibits A, B, 1 and 2, are returned.
Sue Morris
Commissioner of the Court
Annexure A