Procedural History of the Proceeding, the Parties' Exhibits for Hearing, and the Parties' Written Submissions following the Hearing.
- The Proceeding was case managed in the usual manner by the Tribunal with prior directions' hearings (on 1 November 2022, and 14 March 2023) when directions were made (including, at the second directions' hearing, extensions of time) for the parties to file and serve all documents, such as lay and expert evidence, on which each sought to rely for the hearing.
- The Owner filed and served her lay evidence by 17 December 2022, and her expert evidence by 6 March 2023. As indicated above, her expert evidence served on 6 March 2023 contained quantification of the Owner's claim for defective works. I observe that such quantification of damages is only required in circumstances where an order to pay money (HB Act, s 48O(1)(a)) is being sought.
- At the second directions' hearing (on 14 March 2023), the Tribunal had extended the time for the Builder to file and serve its lay and expert evidence, to 17 April 2023. In fact, no evidence was filed by that date.
- On 19 April 2023, the Tribunal issued a Notice of Hearing to the parties. The Notice informed the parties that the Proceeding had been listed for a two-day hearing on 11 and 12 July 2023.
- The parties had been granted leave for legal representation in the Proceeding at the first directions' hearing on 1 November 2022: see order 2. In fact, the Owner was represented by the same solicitors throughout the Proceeding, who instructed counsel for the hearing on 11 and 12 July 2023 and for a later hearing (referred to below) on 21 November 2023.
- The Builder had engaged solicitors (Fortis Law) to represent it in the Proceeding. On 19 June 2023, the Builder's solicitors made an application to the Tribunal on behalf of their client requesting an extension of time within which to file and serve their client's lay and expert evidence, and for an adjournment of the hearing on 11 and 12 July 2023.
- On 22 June 2023, the Builder's application was refused by the Tribunal. The Tribunal made the following orders and gave the following reasons:
1. The Respondent's further request to extend the time for its compliance with the procedural directions first made on 1/11/2022 is refused.
2. The application to adjourn the hearing set down for 11 and 12 July 2023 is refused.
Reasons:
The Respondent has failed to provide an acceptable explanation for its continuing delay in compliance with the Tribunal's procedural directions. The applicant is entitled to determination of the claim within a reasonable time having regard to the Tribunal's Guiding Principle which is just, quick, and cheap resolution of the real issues in the proceedings.
- On 27 June 2023 the Builder filed a further application to adjourn the July hearing, which was refused by the Tribunal on 30 June 2023.
- On 4 July 2023, the Builder's then solicitors (Fortis Law) withdrew from acting for the Builder, i.e., a matter of days only prior to the scheduled hearing.
- On 10 July 2023, the day before the hearing, the Builder served its Points of Defence, and its lay and expert evidence. The Points of Defence expressly raised s 48MA of the HB Act (see [12]), and the lay evidence (see the Witness Statement of Mr Delawar at [20] - [25]) expressly addressed matters pertinent to the nature of the relief the Tribunal should grant.
- Mr Delawar as director of the Builder represented Delcon at the hearing on 11 and 12 July 2023. The Builder then retained new solicitors during September 2023, who instructed counsel and represented the Builder at the later hearing on 21 November 2023.
- For the hearing on 11 and 12 July 2023, the parties filed and served their own separate bundles of documents. The Owner's bundle (Exhibit 1) included her application lodged on 21 September 2022 with points of claim, the Owner's witness statement of 17 December 2022 and her exhibit NS -1, Mr Ghafur's witness statement of 17 December 2022 and his exhibits SG - 1 and SG - 2, Mr Iskowicz's expert report of 6 March 2023, and Mr Iskowicz's Scott Schedule of 28 February 2023, and some documents produced on summons by Sydney Building Certifiers.
- The Builder's bundle (Exhibit 2) included a letter dated 10 July 2023 requesting an adjournment of the July hearing (Builder's Third Adjournment Application), the Points of Defence to the Owner's Points of Claim, the witness statement of Mr Delawar dated 10 July 2023 and his exhibit WS - 1, a witness statement of Waise Delawar also dated 10 July 2023 and Waise's exhibit WS - 2, and the expert report and Scott Schedule of Mr Cunniffe.
- On the first day of the hearing, 11 July 2023, I refused the Builder's Third Adjournment Application. It was opposed by the Owner's counsel. Referring to the procedural history and to the Builder's failed first and second adjournment applications, I further noted that the Builder had since the advent of the Proceedings, the benefit of legal representation (and accordingly, an opportunity to obtain advice in respect of the Proceeding, and to prepare for the hearing) up until its solicitors' withdrawal on 4 July 2023; see also Transcript Day 1 (11.7.2023) 10.28 - 12.7. Further, even though the Builder's bundle of documents (including expert report) had been served out of time, I admitted the documents into evidence, as Exhibit 2, as the Owner's counsel indicated that he was able to deal with the late evidence without the need for the Proceeding to be adjourned. Furthermore, I was unpersuaded that the hearing could not proceed with Mr Delawar as the Builder's director presenting the Builder's case, and in circumstances where Mr Delawar could put questions to the Owner by way of cross examination as regards the nature of the relief (including work order) that the Tribunal should grant. Although recognising that Mr Delawar has no formal legal qualifications, as an architect by trade, I considered he could, and should, understand technical matters, especially as regards scopes of works for rectification of home building defects, such as would enable him to ask informed questions when the parties' experts gave their evidence in joint session. In this regard, the Builder's expert, Dr Cunniffe, was present for the hearing and available to give oral evidence, as was the Owner's expert, Mr Iskowicz.
- Accordingly, I determined in all those circumstances that granting the Builder's Third Adjournment Application would be inconsistent with the Tribunal's guiding principle in s 36(1) of the Civil and Administrative Tribunal Act 2013 NSW (NCAT Act), and that adjourning the Proceeding to a later date would not facilitate the just, quick, and cheap resolution of the real issues in the Proceeding.
- Moreover, as no evidence was taken on the first day of the allocated time (2 days) for the hearing, as a matter of procedural fairness, Mr Delawar was given further time to obtain professional advice (if he wished to do so) and to prepare for the hearing the following day. This was because I had directed the parties' experts to use the rest of the first day of the hearing, to confer and then to prepare a joint report (in the form of a Scott Schedule) identifying their areas of agreement and disagreement, and in respect of their disagreements, the reasons for the disagreements.
- As matters transpired, the experts' differences as to the quantum of the remediation/rectification costs to the Owner were in fact, narrowed very significantly because of the preparation of their Joint Report, which was available at the commencement of the second day of the hearing, on 12 July 2023, and became Exhibit 3. Ultimately, Dr Cunniffe adopted the same methodology and hourly rate as Mr Iskowicz, and their disagreement was confined to the number of personnel and hours to perform the various remediation/rectification works.
- Also, on the second day of the hearing (12 July 2023), I asked the Owner a question that went directly to the nature of the relief the Tribunal should grant (i.e., why a money order, and not a works' order). Indeed, my question to the Owner was prompted by Mr Delawar. He had put the issue of s 48MA (raised in the Builder's Points of Defence) to Mrs Syed in cross-examination, when suggesting to her the possibility of the Builder going back to the Property to "repair the works". My question as to her reasons for a money order then arose when Mrs Syed had rejected that possibility.
- At the conclusion of the hearing on 12 July 2023, I reserved my decision and directed the parties to file and serve written submissions including the findings of fact and law for which each party contended in their respective cases. With an extension of time allowed, the Tribunal then received the Owner's Closing Written Submissions dated 12 September 2023 (Owner's Closing Submissions) with a transcript of the hearing (Transcript).
- On 19 October 2023, which was before the Builder had lodged its closing submissions, the Builder's new solicitors lodged on their client's behalf, an application to re-open the case: see the Application for miscellaneous matters (Application to Re-open), the affidavit of Mr Delawar dated 19 October 2023, and the supporting written submissions of six (6) pages prepared by the Builder's counsel. The Builder sought leave to file and serve additional evidence on whether the Tribunal should make a work order under s 48MA and/or s 48O(1)(c) of the HB Act (the Work Order Issue).
- At a hearing on 21 November 2023, I declined the respondent's Application to Re-open (as to why, see later in these Reasons). I also extended time for the respondent's closing written submissions and the applicant's submissions in reply.
- The Tribunal has now received the Builder's Closing Written Submissions dated 6 December 2023 (Builder's Closing Submissions) and the Owner's Submissions in Reply dated 31 January 2024 (Owner's Submissions in Reply).