Sydney City Council v Li
[2011] NSWLEC 165
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2011-08-24
Before
Preston CJ, Mr P
Source
Original judgment source is linked above.
Judgment (11 paragraphs)
PROCEEDINGS ARE BROUGHT TO ENFORCE A FIRE SAFETY ORDER 1The Council of the City of Sydney ("the Council") brings civil proceedings to enforce compliance with an order given under item 6 of s 121B of the Environmental Planning and Assessment Act 1979 ("the EPA Act" ) to ensure or promote adequate fire safety or fire safety awareness ("the Fire Safety Order") within the premises at 193 Regent Street, Redfern. 2The Fire Safety Order was served on the owners of the premises, Mr Carlos Alberto Li and Mrs Yi Hong Chen Li. The premises comprise a two-storey building and is currently used as a fruit shop on the ground floor and a three bedroom residence on the first floor. 3Officers of the Council inspected the premises on 6 October 2009 and discovered fire safety issues. On 24 November 2009, the Council gave notice to the respondents under s 121H of the EPA Act of the intended Fire Safety Order. 4On 15 December 2009, the Council made the Fire Safety Order under s 121B item 6 and served it on the respondents. The Fire Safety Order specified the circumstances justifying the giving of the order as being: "(a) Provisions for fire safety or fire safety awareness are not adequate to prevent fire, suppress or prevent the spread of fire or ensure or promote the safety of persons in the event of fire; (b) Maintenance or use of the premises constitutes a significant fire hazard." 5The Fire Safety Order specified the works required to be done. The works were to be undertaken in three stages:
- Stage 1 within 30 days (ie by 14 January 2010);
- Stage 2 within 150 days (ie by 14 May 2010); and
- Stage 3 within 180 days (ie by 13 June 2010). 6All works were therefore required to be completed by 13 June 2010. After all the requirements of the order have been complied with, the respondents are required to cause a copy of the final fire safety certificate for the premises to be given to the Council. 7An inspection by the Council on 15 January 2010, one day after the due date for completion of the stage 1 works, revealed that the respondents had completed the stage 1 works, being the work required by terms 2.01 (good housekeeping), 2.02 (egress paths to be kept clear) and 2.03 (removal of storage in and around the exit stair). 8An inspection by the Council on 7 May 2010 revealed that no stage 2 works had been commenced, one week before the due date of 14 May 2010 for completion of the stage 2 works. However, an inspection on 1 June 2010, two weeks after the due date of 14 May 2010 for completion of the stage 2 works, revealed that the works in terms 1.02 (provision of balustrades to the stairwell) and 1.03 (provision of handrails to the stair) of the stage 2 works had been completed. No other stage 2 works and no stage 3 works had been commenced. 9An inspection by the Council on 26 August 2010, over two months after the due date for completion of all works, including stage 3 works, revealed that the only additional work done was that required by term 1.04 (provision of nonslip finish to stair treads) of the stage 2 works and still no stage 3 works had been commenced. 10An inspection by the Council on 19 November 2010 revealed that the only further works undertaken were those required by term 5.01 (installation of portable fire extinguishers). 11Subsequent inspections by the Council on many occasions revealed that the respondents had not carried out any further works required by the Fire Safety Order. 12The works which still needed to be done, at the date of commencement of the proceedings of 11 April 2011, can be briefly summarised as: 1.01 Provision of an egress door to Regent Street 1.05 Installation of exit signs 1.06 Preparation and implementation of fire safety and evacuation procedures 1.07 Certification of existing emergency lighting system to current standards 1.08 Certification of exit signs to current standards 1.09 Confirmation that the same tenant is occupying ground floor shop and first floor residence 1.10 Submission of final fire safety certificate 3.01 Installation of an automatic fire detection and alarm system 3.02 Installation of warning system which sounds upon activation of automatic fire detection and alarm system 3.03 Connection of automatic fire detection and alarm system to NSW Fire and Rescue via third party service provider 4.01 Sealing of wall and ceiling penetrations 4.02 Certification of fire stopping materials 4.03 Construction separating the first floor residence from the ground floor shop including installation of door to the bottom of the stairway 4.04 Certification of existing ceiling serving ground floor shop 4.05 Enclosing of cupboard located beneath stairway with fire-resistive construction and installation of fire door 4.06 Certification confirming fire resistance walls bounding 191 and 193 Regent Street