(1) Decisions upon particular classes of applications are exempt from review, see s. 82(2)(3).
(2) The focus must therefore be upon the application which the responsible authority decided.
(3) In the present case there was but one application for a permit.
(4) It was an application to use land in particular ways, to demolish an existing building and to construct a building or construct or carry out works.
(5) The application required consideration of a series of planning controls, each of which required permission before the responsible authority could decide to grant a permit.
(6) There was nothing wrong in a single application being made which required consideration of a number of planning controls. Indeed, that was made permissible by s. 47(1) of the Acts. Further, it was consistent with the principle that piecemeal applications should not be made with respect to use of land[5] that a single application for use and development be made.
(7) In the present case, with respect to individual required permissions, there were some exemptions from review. Nonetheless, the Tribunal's review jurisdiction was a jurisdiction to consider all aspects of the application for use and development. That was so because:
(A) The exemptions each applied in the case of an application to construct a building or construct or carry out works[6]. Here the application, viewed as it must be singly - "disaggregation" was impermissible - did not meet that description. In addition to being an application to construct a building or construct or carry out works it was an application to demolish, and for a section 2 use.
(B) Even if individual exemptions applied, they did not extend to every planning control which the application required to be considered. In those circumstances, the decision to grant a permit was properly before the Tribunal and its jurisdiction was a jurisdiction to consider all relevant town planning arguments - regardless whether such arguments pertained to a permission the application with respect to which was exempt from review.
(8) To understand the operation of the Act in such a way was consistent with a purposive approach to construction. The Second Reading Speech[7] showed that the purpose of the 1993 amendment to ss. 52, 64 and 82 of the Act was to avoid delay and expense, not to limit review rights once a matter was properly before the Tribunal.
(9) To understand the operation of the Act in the manner contended for was consistent with dicta in National Trust of Australia (Vic) v Australian Temperance and General Mutual Life Assurance Society Ltd and Anor[8]. The ambit of the Tribunal's enquiry was to be determined by the purposes or objects of the discretion to be exercised under the planning scheme.
(10) If the review was limited by quarantining from consideration decisions pertinent to particular planning controls, it was likely to produce a distorted decision not reflecting all relevant planning considerations.
(11) The areas of exemption from review should be strictly construed and confined. Objectives of the legislation are to provide third parties with an opportunity to have input into the decision of the responsible authority and also to provide a mechanism for review. Section 82(1) is remedial in character.
(12) Decisions of the Tribunal denying a right in an applicant to challenge decisions of a responsible authority to the extent that the same were decisions upon applications subject to exemption were wrong.