Suprima Bakeries Pty Ltd v Australian Weighing Equipment Pty Ltd
[2016] NSWSC 998
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2016-07-11
Before
McDougall J, Part P
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Introduction
- Mr Weinberger submitted that the Adjudicator had not dealt, in an appropriately reasoned way, with its claim for defects. That, he submitted, was a breach of the Adjudicator's essential statutory function. Alternatively, he submitted, it amounted to a denial of natural justice.
- Mr Weinberger relied on a number of decisions. Without being disrespectful either to him or to the decisions that he cited, I think that the position for which he contended emerges sufficiently from the judgment of Vickery J in SSC Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd [2015] VSC 631. His Honour said at [76] that the task of adjudication requires, at least, "a determination as to whether the construction work the subject of the claim has been performed and its value", and that a failure to undertake this task "is a failure to comply with a basic and essential requirement of the [Victorian] Act".
- Although of course Vickery J was dealing with the Building and Construction Industry Security of Payment Act 2002 (Vic), I think that the two Acts are sufficiently analogous to make his Honour's observations directly applicable. I note that at [77] to [84], Vickery J referred with apparent approval to a number of decisions of the Courts in this State.
- Vickery J summarised the work required of an Adjudicator at [101] of his reasons. I set that paragraph out in its entirety: [101] Drawing the threads together, the following may be said of an adjudicator's assessment of a payment claim under the Act in Victoria: (a) The adjudicator is required to determine and apply what the adjudicator considers to be the true construction of the Act in the light of the current case law. (b) The adjudicator is required to determine and apply what the adjudicator considers to be the true construction of the construction contract. (c) In addition to the matters to be determined and considered under ss 23(1) and (2), and excluded under s 23(2A) of the Act, an adjudication requires, as a minimum, the following critical findings to be made (the "critical findings"): (i) a determination as to whether the construction work the subject of the claim has been performed (or whether the relevant goods and services have been supplied); and (ii) the value of the work performed (or the value of the goods and services supplied). (d) Construction work carried out or related goods and services supplied are to be valued in accordance with the terms of the construction contract (if the contract contains such terms) pursuant to ss 11(1)(a) and 11(2)(a). (e) In the absence of any express provision in the construction contract providing a mechanism for an adjudicator to undertake the assessment of value, the valuation assessment is to be undertaken in accordance with s 11(1)(b) (for work) and s 11(2)(b) (for goods and services), having regard to the matters set out in those sub-sections, namely: (i) the contract price for the work or the goods and services; (ii) any other rates set out in the contract; (iii) if there is a claimable variation, any amount by which the contract price or other rate or price set out in the contract, is to be adjusted as a result of the variation; and (iv) if the work or goods are defective, the estimated cost of rectifying the defect. (f) If a construction contract contains a binding schedule of rates within the meaning of s 11(1)(b)(ii) (for work) and s 11(2)(b)(ii) (for goods and services), the adjudicator is required to have regard to the schedule in assessing value if s 11(1)(b) or s 11(2)(b) apply. Further, the adjudicator should state in the adjudication determination whether and how the schedule of rates was applied in the assessment of value, if it in fact was applied, or state why the schedule of rates was not applied. (g) However, without measures, evidence or submissions being provided to the adjudicator in a coherent fashion in respect of defined categories of work (or goods and services) the subject of a contractual schedule of rates, in most cases it would not be possible for an adjudicator to safely apply the schedule in assessing the value of the claim. In such circumstances the adjudicator may have regard to a schedule of rates, but would not be remiss in not applying it. (h) The adjudicator is obliged to make the critical findings on the whole of the evidence presented at the adjudication. (i) The adjudicator, having decided that the respondent's submissions and material should be disregarded, cannot simply adopt the amount claimed by the claimant (for example, in the payment claim or in the adjudication application). (j) The adjudicator must proceed to make the critical findings by: (i) fairly assessing and weighing the whole of the evidence which is relevant to each issue arising for determination at the adjudication; (ii) drawing any necessary inferences from the evidence, or from the absence of any controverting material provided by the respondent, including an inference that if there is no controverting material, no credible challenge can be made to the value of the claim advanced by the claimant. Such an inference may be considered in the context of the evidence as a whole; (iii) arriving at a rational conclusion founded upon the evidence; (iv) in so doing, is not called upon to act as an expert; and (v) is not entitled to impose an onus on either party to establish a sufficient basis for payment or a sufficient basis for withholding payment. (k) Pursuant to s 23(3) of the Act, the adjudicator must include in an adjudication determination both the reasons for the determination and the basis upon which any amount or date has been decided. In providing these reasons the adjudicator must summarise the central reasons for the making of the critical findings in the adjudication determination with as much completeness as the time permitted under the Act will allow.