8 On 30 November 2007, DA 07/1354 was lodged for the construction of a dwelling. The proposed dwelling generally occupies the form approved by DA 04/0354 including the same setback to the MHWM. This development application proposes the construction of a new dwelling and not alterations and additions to the original dwelling as it was found during building preparation activities on the site that the original dwelling foundations were not structurally capable of accommodating the proposed alterations and additions. The majority of the original dwelling has been removed with the exception of two small sections of the existing walls. Council refused DA 07/1354 on 15 February 2008. The assessment was undertaken through the provisions of Sutherland Local Environmental Plan 2006 (LEP 2006). As with LEP 2000, LEP 2006 provides for a 20 m FBL measured from the MHWM. This refusal is the subject of Appeal No 10462 of 2008.
9 Council refused a s 82A review application on 26 June 2008.
Relevant planning controls
10 The site is within Zone 1-Environmental Housing (Environmentally Sensitive Land) under LEP 2006. Clause 11 provides objectives for Zone 1. The objectives are:
Zone 1-Environmental Housing (Environmentally Sensitive Land) 1 Objectives of zone
The objectives of this zone are as follows:
(a) to allow development of a scale and nature that:
(i) complements the natural landscape setting of the zone, and
(ii) protects and conserves existing vegetation and other natural features of the zone,
(b) to limit development in the vicinity of the waterfront so that the environment's natural qualities can dominate,
(c) to minimise the risk to life, properly and the environment by restricting the type, or level and intensity, of development on land that is subject to either natural or man-made hazards,
(d) to minimise the impacts of development in the vicinity of heritage items,
(e) to allow the subdivision of land only where the size of the resulting lots makes them capable of development that will not compromise the sensitive nature of the environment,
(f) to ensure sharing of waterfront views between occupiers and users of new and existing buildings.
11 Clause 17 provides requirements for buildings or works on land traversed by a FBL. The relevant parts of the clause state:
17 Buildings or works on land traversed by foreshore building line
(1) Application of clause
This clause applies to land that is traversed by a foreshore building line.
(2) Objectives
The objectives of this clause are as follows:
(a) to avoid adverse ecological effects on waterways,
(b) to protect and enhance significant natural features and vegetation on riparian land,
(c) to retain endemic vegetation along foreshore areas,
(d) to restore and revegetate foreshore areas to improve estuarine flora and fauna habitat,
(e) to minimise any adverse impact from development on water quality and, so far as is practicable, to improve the quality of urban run-off entering waterways,
(f) to minimise any adverse visual impact of development when viewed from adjacent land and waterways by using a design and materials that complement the natural landscape of the land to which this clause applies,
(g) to minimise any adverse impact of development on the natural landform of foreshore areas and waterways by integrating structures into the site with minimal change to the natural topography of the land to which this clause applies,
(h) to achieve an appropriate balance between private development and the public use of waterways,
(i) to maintain and improve public access to the intertidal area of waterfronts where there will be minimal environmental impact,
(j) to conserve and enhance structures on waterfronts that are of heritage significance,
(k) to minimise the obstruction of water views from public land,
(I) to ensure that there is no development below any foreshore building line, except as provided by this clause.
.
.
.
(9) Nothing in subclause (7) or clause 11 prevents consent being granted to the erection of a dwelling, or any addition to an existing dwelling, on land between a foreshore building line and any waterway or waterfront reserve in respect of which the line is fixed if:
(a) the consent authority has considered the objectives of this clause, and
(b) the consent authority is satisfied that:
(i) the new dwelling or addition will not be erected any further forward of the foreshore building line than any existing dwelling on the land, and
(ii) the new dwelling will not dominate the locality in which it is erected as a result of its height, bulk, design, colour or detailing, and
(iii) the natural qualities of the foreshore are retained or restored as far as practicable through the retention or reinstatement of natural levels and endemic vegetation, and
(iv) in the case of the erection of a dwelling - there is no reasonable alternative that would allow a new dwelling to be located behind the foreshore building line.
12 Clause 18 provides requirements for development in or adjacent to waterways. The clause states:
18 Development in or adjacent to waterways
(1) This clause applies to any of the following land:
( a) land in Zone 16-Environmental Protection (Waterways),
(b) land traversed by a foreshore building line,
(c) land below the mean high water mark.
Note . The mean high water mark referred to here is the mean high water mark as it currently exists.
(2) The objectives of this clause are as follows:
(a) to ensure that any development does not result in the obstruction or interference with navigation in waterways,
(b) to ensure restoration of land below any foreshore building line, to a natural state (so far as is practicable), with a minimum intrusion of man-made structures,
(c) to reduce the number of structures below any foreshore building line, particularly following the redevelopment of a site,
(d) to promote the public use of intertidal areas below the mean high water mark or high water mark, where appropriate.
(3) The consent authority must not consent to development on land to which this clause applies unless the consent authority is satisfied that the following building or work will be removed before, or within a reasonable time after, the development is carried out:
(a) any building or work, other than an excluded building or work, that is:
(i) on the lot concerned or an adjoining lot owned by the person carrying out the development, and
(ii) between a foreshore building line and any waterway or waterfront reserve· in respect of which the line is fixed,
(b) any building or work (other than a watercraft facility) that is:
(i) on the lot concerned or on an adjoining lot that is owned by a person carrying out the development, and
(ii) below the mean high water mark.
(4) Subclause (3) does not require the removal of any building or work if:
(a) the proposed development is the erection or installation of any of the following:
(i) a fence or retaining wall between a dwelling and the street on which the dwelling is located,
(ii) a garage or carport adjacent to a dwelling or located between a dwelling and the street on which the dwelling is located,
(iii) a deck or verandah,
(iv) an awning or canopy, or
(b) the consent authority is satisfied that the use of the building or work is lawful, or
(c) the consent authority is satisfied that the removal of the building or work:
(i) would be inconsistent with, or is not necessary to achieve, any of the objectives of this clause, or
(ii) is unreasonable or unnecessary in the circumstances of the case.
13 Clause 33 provides requirements for building height. The applicant submitted an objection under State Environmental Planning Policy No 1Development Standards (SEPP 1) to show why strict compliance with the provisions of cl 33 was unreasonable and unnecessary in the circumstances of the case.