Timber Supply, Timber roof installation & Roof sheeting supply & install
- Schedule of payments is same for each of the blocks
- For purchase of timber, full payment is required prior to order for each of the blocks
- For other payments for each block:
10% prior to commencement of work
30% on delivery of material
30% progress payment
Balance and final payment 30 days from end of the month."
- By 2021, there had been a significant increase in cost of both labour and material caused, I infer at least in part, by the COVID pandemic. On 2 November 2021, there was an e-mail sent by the First Defendant to the Plaintiff. That e-mail ("the 2 November E-mail") was created and physically sent by the Second Defendant, who was at all relevant times the sole director and guiding mind of the First Defendant.
- The 2 November E-mail's subject heading was "Price increase", and it was in the following terms:
"Hi ash
There is a price increase from 1 November
15 percent on all timber and if the payment is not done you will have to pay for every increase on the whole job I have sent the invoice to you as per agreement of the contract to be paid You have till tomorrow to pay the invoice One the payment we can deliver all materials on site and give you a letter of ownership of all materials Regards multibuild constructions"
- The Plaintiff contends it paid the sum of $55,000 as a consequence of its receipt of that e-mail and it says that two statements in the e-mail amount to misleading and deceptive conduct. It is the 2 November E-mail and the payment of the $55,000 which is the subject of the Australia Consumer Law part of the claim. It is relevant to the contract aspect of the claim because it forms the context of the conduct that follows, said to amount to repudiation of the Agreement.
- Sometime in March 2022, there was a conversation between Mr El-Khoury of the Plaintiff and Samear Machlouche, the Second Defendant (Mr Machlouche). Mr Machlouche was the sole director of the First Defendant.
- Mr El-Khoury's recollection of the conversation is as follows:
"Samear: The price of material has increased a lot. I have to increase the Subcontract Sum in the Agreement.
Me: You can't do that. We have an agreed contract price. Send us what you have, and we will look at it.
Samear: Okay, I will. Is the job still going ahead?
Me: Yes, but we will need to review the numbers."
- Mr Machlouche denied the conversation in his evidence in chief, but under cross-examination conceded that there was a conversation along those lines, albeit he denied that Mr El-Khoury said anything to the effect that "you can't do that, we have an agreed contract price". Mr Machlouche also said that the context of the conversation was, what he described as, variations to the contract, which had been requested by the Plaintiff. He gave no detail of what those variations were at all. There is no written record of any variations.
- On balance, and in particular having regard to the very hazy nature of Mr Machlouche's evidence and by reference to the documents each created around this time, some of which I am about to come to, I accept that something to the effect of the evidence given by Mr El-Khoury was said in a discussion between him and Mr Machlouche. The gist was that Mr Machlouche said that the contract price needed to be increased because the cost of labour and material had increased, Mr El-Khoury's position was that was not permissible under the contract but that he would look at any proposal. I do not accept that there was any discussion about variations or that there had in fact been any variations.
- On 14 March 2022, what was described as a "quote of works" was provided by the First Defendant to the Plaintiff which costed the entire job, the subject of the Agreement, at $1,927,605.19 cents, which was a significant increase from the actual contract sum of $1,284,219.
- Mr El-Khoury gave evidence that shortly after that quote was received, he spoke to his assistant Nadine, and they had a conversation to the following effect:
"Mr El-Khoury: Nadine, please call Samear (Machlouche) and find out what these numbers are. The increase is way too high, and we never agreed to pay increased labour costs.
Nadine: Okay."
- Shortly thereafter, Nadine reported back to Mr El-Khoury:
"Nadine: I have spoken to Samear (Machlouche). I told him the updated quote was way too high, and I questioned him about the delay. I also said that the updated quote also included increases in labour, and I asked him why. He said that labour has increased as well. I said I would speak to you and get back to him. There are also a few e-mails back and forth with him.
[Nadine then showed Mr El-Khoury some e-mails with Samear Machlouche regarding the price increase]
Mr El Khoury: It is too high. We need to call him back and let him know we not accept the increases."
- Nadine gave evidence. She, however, gave no evidence as to the above conversations. I infer that she does not remember it. I therefore need to be very cautious before accepting and acting on Mr El-Khoury's recollection of what Nadine said had occurred at the time.
- The existence of such a conversation is, however, consistent with two things. The first is telephone records to confirm that around that time there was a three-minute conversation between Nadine and the Second Defendant (Exhibit E), and moreover, on 15 March 2023 Mr Machlouche sent to the Plaintiff a bundle of documents described as "all price notifications attached from October 2021". The only apparent purpose being to demonstrate that there had in fact been a dramatic increase in both labour and material costs. In light of those two objective facts, I find that a conversation between Nadine and Mr Machlouche along those lines set out above probably occurred.
- At around this time, the end of March, the Plaintiff started negotiating with other contractors to quote for the work, the subject of the Agreement. By 4 April 2024, the Plaintiff had in fact entered into a contract with another contractor(s) for the same work. Also, during this period, the communication between the Plaintiffs and the Defendants all but dried up. It was described in evidence and submissions as "ghosting" by the defendants. No communication about the Agreement or indeed any work under the Agreement takes place in April, May, or June.
- On 22 June 2022, the First Defendant, by its solicitors, wrote a letter recording the history of the matter and said the following:
2. The Subcontract contained, inter alia, the following clauses:
(a) Clause 6.1: Unless otherwise stated herein, the Subcontract Sum is the amount stated in Item 6 of the Subcontract Details and the Subcontract Sum is calculated in accordance with the Pricing Schedule and is not subject to any adjustment on account of any rise and/or fall in labour rates (including any extra amounts payable on account of the conditions in which any work is carried out and any change in the cost of statutory and/or other overheads) cost of materials and plant rates on any account whatsoever.
(b) Item 6 of the Subcontract Details - Subcontract Sum: $1,284,219 (excluding GSR) (Subcontract Sum)
3. On 2 November 2021, Samear Machlouche, a representative of Multibuild, represented to Nicholas El-Khoury of STPG that payment of the deposit due under the Subcontract in the sum of $98,290.50 (including GST) (Deposit) would lock in the price of the material required to complete the works pursuant to the Contract (Representation). The Representation also accorded with the Subcontract such that the Subcontract Sum specified in item 6 of the Subcontract Details was fixed pursuant to clause 6.1 of the Subcontract.
4. STPG paid the Deposit to Multibuild as follows:
(a) the sum of $43,290.50 on 27 October 2021; and
(b) the sum of $55,000 on 2 November 2021.
5. On 14 March 2022, Multibuild informed STPG that the Subcontract Sum had increased to $2,017,346.35 (excluding GST), being an increase in the sum of $733,127.35 (excluding GST). In doing so, Multibuild sought to unilaterally change the Subcontract Sum in breach of clause 6.1 of the Subcontract. It follows that by attempting to change the terms of the Subcontract without any entitlement to do so, Multibuild has repudiated the Subcontract by evincing an intention not to be bound by the terms of the Subcontract (Repudiation).
6. STPG is therefore entitled to accept the repudiation and sue Multibuild for damages or to affirm the Subcontract.
7. STPG hereby accepts the Repudiation.