© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2003] VSC 84
Supreme Court of Victoria
2003-04-24
OSBORN J.
Original judgment source is linked above.
[2003] VSC 84
COMMERCIAL ARBITRATION ACT - Manifest error of law - Interpretation of commercial documents by Arbitrator - Requirement that errors identified potentially vitiate decision - Proper approach where both parties agreed on the method of interpretation which was adopted by Arbitrator and such interpretation turned in part on matters of fact.
"(a) with the consent of all the other parties to the arbitration agreement; or (b) subject to s.40, with the leave of the Supreme Court."
"(5) The Supreme Court shall not grant leave under s.s.(4)(b) unless it considers that - (a) having regard to all the circumstances, the determination of the question of law concerned could substantially affect the rights of one or more parties to the arbitration agreement; and (b) there is - (i) a manifest error of law on the face of the award; or (ii) strong evidence that the arbitrator or umpire made an error of law and that the determination of the question may add or may be likely to add, substantially to the certainty of commercial law."
* The Development and Concession Agreement dated 27 March 1997 made between the Minister for Conservation and Land Management for and on behalf of the State and the company ("the DCA");
* The lease relating to the Seal Rocks site made between the same parties on the same date ("the lease"); and
* The Co-operation, Operation and Maintenance Agreement ("the COMA") also of the same date and made between the same parties together with the Phillip Island Nature Park Board of Management ("PINP").
(a) a series of manifest errors of law on the face of the award; and/or
(b) strong evidence of errors of law the resolution of which may add substantially to the certainty of the commercial law.
"Thus, at common law, according to the Australian authorities, want of logic is not synonymous with error of law. So long as there is some basis for an inference - in other words the particular inference was reasonably open - even if that inference appears to have been drawn as a result of illogical reasoning there is no place for judicial review because no error of law has taken place."
"There should ... before leave is granted be powerful reasons for considering on a preliminary basis without any prolonged adversarial argument that there is on the face of the award an error of law."
"Obviously, there is difficulty in the word `manifest'. What may be `manifest' to one judicial officer may fail to persuade another. The criterion cannot be the swiftness of mind of the sharpest intellect. Nor can it be the perception of one whose career has been devoted to examining and reflecting upon building contracts. An objective, not a subjective, test for what is `manifest' is contemplated. But the word will not go away. Against the background of its history in this context it requires swift and easy persuasion and rapid recognition of the suggested error."
"From time to time a case will arise in which any preconceived guidelines will be found not wholly sufficient. In the end, whether leave is granted or not must always depend upon the justice of the case, as it appears to the court from whom leave is sought."[10]
For this reason I do not regard the fact that the application was the subject of relatively prolonged adversarial argument before me as necessarily demonstrating it must fail, although it must be a circumstance which is not particularly helpful to the State.
(a) the full terms of the contractual documents and in particular those that demonstrate it was the parties' intention that in appropriate circumstances environmental considerations and associated duties relating to the welfare of penguins may prevail over commercial objectives and associated rights;
(b) the legislative regime in which the obligation of the State to use reasonable best endeavours is to be understood. Such regime it was said is critical to a proper understanding of that obligation and preserved an absolute independent statutory discretion with respect to relevant actions by the State; and
(c) the proper ambit of the relevant "best efforts" clauses.
(a) that the DCA makes clear the parties are not to be regarded as joint venturers. Clause 1.6 provides:
"Nothing in any of the Project documents will be construed or interpreted as constituting the relationship of the State and the company as that of principal and agent, partners or joint venturers or imposing a fiduciary relationship upon either of them."
(b) clause 2.2 of the COMA further provides that nothing in that document is to be deemed to create a partnership or fiduciary relationship between the parties.
(c) the DCA includes an express acknowledgment by the company that no risks or responsibilities in relation to the Project are accepted by the State except where expressly assumed under the document (clause 31); and
(d) the DCA contains an express assumption of risk by the company with respect to operational considerations including change of regulation (clause 33).
"46.6 Approvals not to affect company's obligations The giving of any approval or the making of any direction or appointment or the exercise of any authority or discretion or the exercise, giving or making of any other matter or thing of any nature hereunder by the State will not, except where this document expressly provides to the contrary or where such approval, direction, appointment, exercise of authority or discretion expressly deals with matters contained in or relating to this document, relieve the company from its obligations under this document. 46.7 Consent or approval of the State In any case where pursuant to this document the doing or executing of any act, matter or thing by the company is dependent upon the approval or consent of the State such approval or consent may be given or withheld by the State in its absolute uncontrolled discretion unless otherwise provided in this document."
"2.3 Environmental requirements The parties acknowledge that each party, and any other person or body, in carrying out its duties, performing any functions or exercising any powers in relation to the Reserve and/or the Site under the Project documents or any applicable Laws, must have regard to the following requirements: (a) the need to care for, protect, manage and maintain the Reserve; (b) the need to protect: (i) the Reserved Land Values; (ii) the Flora and Fauna Values; (c) the need to minimise adverse impacts on the Environment; (d) the need to have land use and protection measures carried out in accordance with any Current Management Plan and to give effect to any Current Management Plan in the areas affected by it."
"Flora and Fauna Values means those values from time to time promoted by the board or required in order to conserve, manage, protect and foster, in the case of fauna, any animal life which is indigenous to Victoria whether vertebrate or invertebrate and in any stage of biological development (including fish and any other living thing generally classified as fauna but not including humans) and, in the case of flora, any plant life which is indigenous to Victoria whether vascular or non-vascular and in any stage of biological development, including any other living thing generally classified as flora, and those values promoted or required to further the objectives of the Flora and Fauna Guarantee Act 1988."
"2.4 Interpretation of intent This document is intended by the parties to be, and must be, interpreted in a way which is consistent with: (a) the objects of the Acts which affect any land in the Reserve and the duties imposed upon those charged with the obligation to implement and enforce the Acts which, in each particular case, regulate the use of land in the Reserve; (b) the enforcement of any regulation applicable to any land in the Reserve and it is not the intent of this document to waive, vary or estop any regulation made pursuant to any Act which affects the use of any land in the Reserve in the particular case from being enforced."
I interpolate that, as will become apparent, the actions upon which the State seeks to rely (other than actions which it maintains were authorised by the relevant agreements) included actions with respect to the regulation of Ventnor Road which is adjacent to but outside the Reserve.
"2.5 Conflicts between Environment Requirements and Interpretation It is recognised by the parties that there may be some: (a) disagreement on the Reserved Land Values and the Flora and Fauna Values; (b) disagreement in determining aspects of the Environmental Requirements; and (c) conflicts between any or all of the Environment Requirements and any or all of the interpretative requirements set out in clause 2.4. Where such a disagreement or conflict arises that disagreement or conflict is to be resolved by giving effect to the best balance of the Environmental Requirements and interpretative requirements considered to be most important and appropriate by the Board; provided that no party will be required to act in breach of any Act or regulation. 2.6 Objectives of parties The parties' primary objective in entering into this document is to enable the Board to care for, protect, manage and maintain the Reserve in the most efficient and effective manner possible having regard to the rights and obligations of the parties contained in the Development and Concession Agreement. In their attempts to achieve this primary objective, the parties' further objectives in entering into this document are to: (a) ensure that the Reserve is at all times managed in accordance with: (i) any of the Acts which are applicable; (ii) the Environmental Requirements; (iii) all relevant laws; and (iv) this document; (b) confirm that the Board is responsible for determining the policy necessary to care for, protect, manage and maintain the Reserve; ..."
"The Executive cannot by representation or promise disable itself from, or hinder itself in, performing a statutory duty or exercising a statutory discretion to be performed or exercised in the public interest, by binding itself not to perform the duty or exercise the discretion in a particular way in advance of the actual performance of the duty or exercise of the power: ... No doubt the principle gains some of its force from the circumstance that the discretion has a legislative foundation and it is not readily to be supposed that the legislature intended that a proper exercise of the discretion in the public interest was to be frustrated, hindered or circumvented by executive action. Nonetheless there is no reason why the same principle should not apply to common law powers and functions of the Crown or the Executive when they involve the making of decisions in the public interest." (citations omitted)
"I put to one side cases where the discretion is properly exercised in advance at the time the contract is made. What I am about to say relates only to contracts where the discretion must be exercised in the future in the light of the public interest at that time or whatever other factors may be made relevant by the nature of the power, its purpose or any applicable statute. In such a case a provision of the contract will be void if it purports to prevent the due exercise of the discretion at the time required by law. Goldsbrough's Case and The Amphitrite were both cases of that kind. See also Ayr Harbour Trustees v. Oswald (1883) 8 App.Cas. 623 at 634, 638 and 640 and South Australia v. The Commonwealth [1962] HCA 10; (1962) 108 C.L.R. 130 at 141. Unless a contract has that meaning on its true construction, the relevant provision will not be void. Instead it will be read subject to the repository's right not to perform the contract in the future if performance would be inconsistent with a proper exercise of the discretion. In other words there is a contract, but the repository of the discretion reserves the right not to perform it if performance is inconsistent with his or her common law or statutory duty when the time for performance arrives."[16]
"(a) use its best efforts to do all things necessary or desirable to give full effect to this document and all other State Documents; and (b) refrain from doing anything that might hinder performance of this document and all other State Documents."
"In determining whether the best efforts clauses in any of the documents have been breached, it is therefore necessary to identify an obligation which has not been given full effect or the performance of which has been hindered as a result of a failure to exercise best efforts by the party said to be in breach."
"The collective objectives of the company and the State referred to in clause 2."
"The company has agreed, in accordance with this document, to develop, manage, operate and maintain the Facilities and provide Amenities (both as defined in this document) in accordance with the objectives of the parties and the requirements of the State as expressed in this document."
"2. Objectives of the parties The company has agreed, in entering into this document, to design, construct, operate and maintain the Facilities and to provide the Amenities towards satisfaction of the following objectives of the State: (a) realising the potential for use and enjoyment of the site whilst protecting and enhancing the area's natural value; (b) providing for an international standard facility with the aim of further enhancing Phillip Island's reputation as a destination for eco tourism for both local and international visitors; (c) enhancing the public use, understanding and enjoyment of the area to the extent that it is consistent with the protection of the area's natural values; (d) providing additional facilities aimed at attracting tourists and lengthening the stay of visitors on Phillip Island; (e) enhancing the attraction of the area by considerably improving the current design and siting of facilities; (f) enhancing the opportunity for public education and viewing the seals to the extent that it is consistent with the protection of the area's natural values and enhancing the Penguin Parade activities; (g) promoting a better understanding of the environment by improved provision of interpretation and education facilities, and the following objectives of the Company: (h) to maximise visitor numbers; (i) to maximise gross revenue."
(a) it refers in terms to objectives of first the State and second the company; and
(b) (as already noted) it is defined as comprising joint objectives by clause 2.
"The company may (without prejudice to any other rights provided for and conferred on the company pursuant to this document with respect to that default) without further notice exercise all or any of the following remedies: (f) where the State has been given the opportunity to and failed to demonstrate that a reasonable person would consider that the State is willing and able to achieve the Objectives (i) accept the repudiation or other circumstance and terminate or bring this document to an end by notice to the State. (ii) exercise or enforce its rights under or terminate any other State document;"
"Perhaps, however, express mention should be made of the trial judge's finding that under the law of New York and of Connecticut `every contract imposes upon each party a duty of good faith and fair dealing in its performance and its enforcement': Restatement of the Law: Contracts (2nd), s.205. This, he found, meant no more than that neither party to an agreement may do anything to impede performance of the agreement or to injure the right of the other party to receive the proposed benefit and was, in substance, an expression of the same principle enunciated by this court in Secured Income Real Estate (Australia) Ltd v St. Martin's Investments Pty Ltd, quoting the words of Griffiths CJ in Butt v M'Donald: `But it is a general rule applicable to every contract that each party agrees, by implication, to do all such things as are necessary on his part to enable the other party to have the benefit of the contract'."
"The best endeavours clause is the kind of clause which in any event would be implied. The much-cited general proposition stated by Lord Blackburn in Mackay v Dick (1881) 6 App Cas 251, at p.263, is in point: `I think I may safely say, as a general rule, that where in a written contract it appears that both parties have agreed that something shall be done, which cannot effectually be done unless both concur in doing it, the construction of the contract is that each agrees to do all that is necessary to be done on his part for the carrying out of that thing, though there may be no express words to that effect'. ... Even more pertinent are the words of Cockburn CJ in Stirling v Maitland [1864] EngR 752; (1864) 5 B & S 840, at p.852 cited by Lord Atkin in Southern Foundries (1926) Ltd v Shirlaw [1940] App Cas 701 at p.717: `... If a party enters into an arrangement which can only take effect by the continuance of an existing state of circumstances ... I look on the law to be that ... there is an implied engagement on his part that he shall do nothing of his own motion to put an end to that state of circumstances, under which alone the arrangement can be operative'. Lord Atkin said: `That proposition in my opinion is well established law. Personally I should not so much base the law on an implied term, as on the positive rule of the law of contract that conduct of either promissor or promissee which can be said to amount to himself "of his own motion" bringing about the impossibility of performance is in itself a breach'."
(a) The clause in sub-para.(a) requires best efforts to do all things necessary or desirable to give full effect to the DCA and the State documents. The requirement to do all that is desirable might be thought to go beyond what the law would otherwise imply.
(b) Likewise, sub-para.(b) requires each party to refrain from doing anything that might hinder performance of the DCA and other State documents. Usually an implied term would not extend to matters which "might" hinder performance.
"It is easy to imply a duty to co-operate in the doing of acts which are necessary to the performance by the parties or by one of the parties of fundamental obligations under the contract. It is not quite so easy to make the implication when the acts in question are necessary to entitle the other contracting party to a benefit under the contract but are not essential to the performance of that party's obligations and are not fundamental to the contract. Then the question arises whether the contract imposes a duty to co-operate on the first party or whether it leaves him at liberty to decide for himself whether the acts shall be done, even if the consequence of his decision is to disentitle the other party to a benefit. In such a case, the correct interpretation of the contract depends, as it seems to me, not so much on the application of the general rule of construction as on the intention of the parties as manifested by the contract itself."[21]
"A best efforts clause is not an uncommon feature of a distributorship agreement. However, it is unusual to include in the clause a provision that the promisor will use his best efforts for the common benefit of both parties. It is a clause ordinarily inserted in a contract between parties at arm's length, designed to give protection to one party by imposing an obligation on the other to promote the sales of the first party's products. The extent of the obligation thereby imposed is governed by what is reasonable in the circumstances: Transfield Pty Ltd v Arlo International Ltd [1980] HCA 15; (1980) 144 CLR 83 at pp.100-101, 107. In Transfield a tender by a licensee based on its use of its own product instead of the product of its licensor was held not to be a breach of a best efforts clause. However, in other cases sale of competing products has been regarded as a breach: see, e.g. Randall v Peerless Motor Car Co (1912) 99 NE 221; Paige v Faure (1920) 127 NE 898. To say that the promise was to be performed to or for the common benefit of both parties is to overlook the qualification of reasonableness usually associated with a best efforts promise. The qualification itself is aimed at situations in which there would be a conflict between the obligation to use best efforts and the independent business interests of the distributor and has the object of resolving those conflicts by the standard of reasonableness."[23]
(a) extended to doing all things reasonably necessary or desirable to enable the company to have the benefit of the contracts; but
(b) were subject to the detailed terms of the contracts as to the respective obligations of the parties; and
(c) were potentially subject to the right of the State to independently exercise statutory powers bona fide for public purposes extraneous to the contract.
"842. Thirdly, the State contends that the Claimant's reliance upon the best endeavours clause (clause 46.11 DCA) asserts an entitlement, in terms of performance on the part of the State, which goes well beyond the intentions of the parties. The State contends that clause 46.11 is to be construed in light of other clauses in DCA, including clause 31, in which the Claimant acknowledges that `no risks or responsibilities in relation to' the operation and management of the Centre and the Facilities are to be accepted by the State (except, where expressly assumed by it) and clause 1.6 in which the parties acknowledge that nothing in DCA or other Agreements is to be construed as constituting the relationship of principal and agent, partnership or joint venture As the cases state, it is fundamental, in an action on contract, that the alleged wrongdoer is not to be held liable for failing to do something which he has not promised. The best endeavours clause should be read subject to the Objectives of the parties. I agree with these latter submissions. Indeed, the Claimant founds its own case against the State upon them. I do not accept, however, that clause 31 or 1.6 inhibit the operation and effect of clause 46.11 so that the Claimant cannot rely upon it as it has done in this case. Insofar as the State relies upon clause 31, it cannot excuse the State from its own conduct, including a failure to act or not to act under the best endeavours clause which I found it [sic] to be a fundamental obligation imposed upon each party. To accede to the State's reliance upon this submission amounts to exempting the State from using its best endeavours on every occasion the Claimant requires it to do or not to do something in order to enable the Claimant to operate and manage the Centre. I am satisfied that the parties never intended clause 31 to have this effect or operate in this manner. As for clause 1.6 of DCA, it is not a logical extension of a finding against the State that, by reason of it breaching the best endeavours clause, the relationship of principal and agent, partnership or joint venture somehow emerges between the parties."
(a) he misconstrued the interpretation of the definition of "Dusk" and consequently erred in his findings as to the powers of the Penguin Parade Manager;
(b) he failed to properly acknowledge the powers of the local council to regulate traffic on Ventnor Road pursuant to the Local Government Act 1989 and of the State to regulate such traffic pursuant to planning permit condition and under the Transport Act 1983;
(c) he misconstrued the obligations of the State with respect to co-operative arrangements such as those with respect to joint ticketing and a new management plan; and
(d) he misconstrued the obligations of the State with respect to variations requested by the company to the contractual documents.
Dusk
"`Dusk' means on any day 90 minutes after sunset or the time for closure of the facilities most recently notified to the company by the manager of the Penguin Parade, whichever is earliest."
"`Sunset' means the time as set out by the Astronomical Society and publicised in the Age or other publication selected by the State."
The proper application of this definition gives rise to questions which pervade the Arbitrator's Reasons and are critical to the Arbitrator's decision with respect to claims 1 (vacation times), 3 (early road closure), 4 (emergency management and maintenance), and 5 (quiet enjoyment of the site); and bear on claims 12, 15 and 16 (requests to amend DCA and other agreements).
* that its apparent purpose is to fix a specific point in time;
* the period of time which is defined by the ordinary meaning of "dusk" will vary in duration throughout the year depending on the azimuth and angle of the sun and weather conditions;
* dusk as ordinarily understood does not extend to 90 minutes after sunset in mid winter and it follows the point in time contemplated is not necessarily within "dusk" as that term is ordinarily understood.
"The definition contained in the contract is unambiguous. `Dusk' is to be decided by reference to the definition of sunset published by the Astronomical Society or by the determination of the Penguin Parade Manager notified to the company, in either case the decision being made by a party outside the DCA. When the Penguin Parade Manager has notified more than one time, the most recent is to apply ..."
"46.12 Entire document The Project documents contain the entire agreement of the parties with respect to the transactions contemplated by them. There are no understandings, agreements, warranties or representations, express or implied, with respect to the transactions contemplated by the Project documents except for those referred to in them."
* The contract documents are detailed and on their face comprehensive. As Mason J said in Codelfa Construction Pty Ltd v. State Rail Authority of New South Wales[25] at 346_:_
"The more detailed and comprehensive the contract the less ground there is for supposing that the parties have failed to address their minds to the question at issue."
* The application of the principles stated in BP Refinery (Westernport) Pty Ltd v Shire of Hastings[26] leads to the conclusion:
"It is not the case that a term may be implied if it removes uncertainty from or makes more effective the bargain the parties have made. An implied term is an acknowledgment of the presumed intention of the parties and it is not supplied to add what some may perceive as a desirable improvement to the bargain."[27]
* The State's objectives set out in the DCA include:
"(a) realising the potential for use and enjoyment of the Site while protecting and enhancing the area's natural value; ..."
This suggests that the stipulation of times governing operational matters might well be deliberately delegated to the Manager of the Penguin Parade as a person having operational responsibility for protecting and enhancing part of the area's natural values.
* The tripartite agreement constituted by the COMA which gives to a State agency (PINP) a specific delegated role in the management of the relationship between the Penguin Parade and the Seal Rocks facility, might be thought entirely consistent with the power apparently delegated to the Penguin Parade Manager by the definition of "Dusk".
* The natural and environmental values specifically recognised in the COMA suggest that that such considerations might lead to the delegation to the Manager of the Penguin Parade of the function apparently referred to in the definition. These values being matters in respect of which I have already observed the Arbitrator misdirected himself.
(a) by reference to opportunity - requiring exceptional circumstances on the day in question; and
(b) by prescription of such exceptional circumstances as those warranting closure to protect human lives or the natural values of the area.
(a) was it open to the Arbitrator to have regard to other than the plain meaning of the definition and in particular to have regard to the matrix of fact surrounding the making of the agreements for the purpose of ascertaining the true meaning of the definition?
(b) if yes, were the findings made by the Arbitrator as to the presumed intention of the parties open to him?
(c) if yes, can the terms implied by the Arbitrator rest upon or be regarded as supportable by such findings?
The Matrix of Fact
"The basis on which the courts act in implying a term was expressed by MacKinnon LJ in Shirlaw v Southern Foundries (1926) Ltd. in terms that have been universally accepted: `Prima facie that which in any contract is left to be implied and need not be expressed is something so obvious that it goes without saying ...' The conditions necessary to ground the implication of a term were summarized by the majority in BP Refinery (Westernport) Pty Ltd v Hastings Shire Council: `(1) it must be reasonable and equitable; (2) it must be necessary to give business efficacy to the contract, so that no term will be implied if the contract is effective without it; (3) it must be so obvious that "it goes without saying"; (4) it must be capable of clear expression; (5) it must not contradict any express term of the contract'."[28]
(a) that the definition is to be interpreted "purposively" (the State contending contrary to the view held by the Penguin Parade Manager himself that any time notified must be after sunset); and
(b) the presumed intention of the parties was to be ascertained in part by an examination of the relevant matrix of fact underlying the making of the agreement.
"In the present case the New South Wales Court of Appeal placed much emphasis on the speeches of Lord Wilberforce in Prenn v. Simmonds, and in Reardon Smith line v. Hansen-Tangen. Their Honours, though acknowledging that his Lordship's remarks were directed not to the implication of a term but to the application of the parol evidence rule, for in each of the two cases the issue was one of orthodox construction of a contract, thought that the remarks had significance for the implication of a term in a contract. With this I agree. But there is a question whether these two cases and other authorities support the Court of Appeal's view that it is legitimate to take into account the common beliefs of the parties as developed and manifested during their antecedent negotiations."[29]
"The true rule is that evidence of surrounding circumstances is admissible to assist in the interpretation of the contract if the language is ambiguous or susceptible of more than one meaning. But it is not admissible to contradict the language of the contract when it has a plain meaning. Generally speaking facts existing when the contract was made will not be receivable as part of the surrounding circumstances as an aid to construction, unless they were known to both parties, although, as we have seen, if the facts are notorious knowledge of them will be presumed. It is here that a difficulty arises with respect to the evidence of prior negotiations. Obviously the prior negotiations will tend to establish objective background facts which were known to both parties and the subject matter of the contract. To the extent to which they have this tendency they are admissible. But in so far as they consist of statements and actions of the parties which are reflective of their actual intentions and expectations they are not receivable. The point is that such statements and actions reveal the terms of the contract which the parties intended or hoped to make. They are superseded by, and merged in, the contract itself. The object of the parol evidence rule is to exclude them, the prior oral agreement of the parties being inadmissible in aid of construction, though admissible in an action for rectification. Consequently when the issue is which of two or more possible meanings is to be given to a contractual provision we look, not to the actual intentions, aspirations or expectations of the parties before or at the time of the contract, except in so far as they are expressed in the contract, but to the objective framework of facts within which the contract came into existence, and to the parties' presumed intention in this setting. We do not take into account the actual intentions of the parties and for the very good reason that an investigation of those matters would not only be time consuming but it would also be unrewarding as it would tend to give too much weight to these factors at the expense of the actual language of the written contract."[30]
"Except in the most exceptional circumstances, it would be contrary to all principle to allow a party, after a case has been decided against him, to raise a new argument which, whether deliberately or by inadvertence, he failed to put during the hearing when he had an opportunity to do so."[32]
"In some cases when a question of law is raised for the first time in an ultimate court of appeal, as for example upon the construction of a document, or upon facts either admitted or proved beyond controversy, it is expedient in the interests of justice that the question should be argued and decided (Connecticut Fire Insurance Co v Kavanagh; Suttor v Gundowda Pty Ltd; Green v Sommerville)."
"The implication of the term found by the Court of Appeal rests on findings made by the Arbitrator based on circumstances surrounding the making of the contract, including evidence of the discussions between the parties which preceded entry into the contract. Thus the Arbitrator found that there was a common understanding (described as a `belief' by the Court of Appeal) that the works would be carried out on a three shift continuous basis six days per week and without restriction as to Sundays. He also found that the Authority had represented to Codelfa, and that it had accepted, that no injunction would be granted in relation to noise or other nuisance. He further found that the works could not be carried out in accordance with methods and programmes agreed between the parties unless Codelfa worked three shifts a day for six days a week. The first question is whether, in the light of the principles as I have explained them, it was legitimate to look to this material on the issue of implication of a term. I think it was. ... As it was, the relevant discussions reflect neither the preliminary consensus that merged into the written contract, nor statements made during the course of negotiations indicative of the unilateral intentions of each party. Instead the evidence revealed a matter which was in the common contemplation of the parties yet was not a contractual provision actually agreed upon for the simple reason that it was a matter of common assumption."[35] (emphasis added)
"This is not a case in which an obvious provision was overlooked by the parties and omitted from the contract. Rather it was a case in which the parties made a common assumption which masked the need to explore what provision should be made to cover the event which occurred. In ordinary circumstances negotiation about that matter might have yielded any one of a number of alternative provisions, each being regarded as a reasonable solution."[36]
(a) the contract was not a negotiated contract but one put forward by one party in a form the other accepted; and
(b) the assumption in issue related not to the resolution of circumstances arising directly under the contract (as here) but generated by the action of a third party having no necessary role under the contract.
"118. At the time the parties entered DCA and other Agreements, they were fully aware of the circumstances that there would be penguins on Ventnor Road after dark. Evidence was given at the hearing that they could be present on Ventnor Road any time after sunset. Despite being `a wild animal' it is more likely than not they would be present on Ventnor Road 30 minutes after sunset. On any view of the evidence this phenomena was known to at least 1 officer of the State. If this was so why would the parties vest the Penguin Parade Manager with a discretionary power to close the Centre and the Facilities when penguins were likely to be present on the road? Why did the parties simply not provide that the Claimant could only operate its business when penguins would not be present on it? In my opinion the parties expected the Claimant to operate and manage its business in the presence of penguins and to co-exist with them. They expected and required the Claimant to conduct its business accordingly. 119. In effect the State is contending that, if the Penguin Parade Manager considers the welfare of penguins may be endangered by the Claimant carrying on its business at the Facilities, he is empowered by the definition to notify the Claimant to close the Centre and vacate the Facilities. He is not required to consider what courses may be open to the Claimant to avoid endangering the penguins whilst carrying on its business. It does not matter what are the consequences of the closure upon the business. The State says, in effect, that it was never intended by the parties that the Claimant should carry on business in the presence of penguins, particularly those appearing on Ventnor Road. 120. I do not accept these submissions and the outcomes of them. Indeed, I consider this interpretation and what may follow from it could relieve the Claimant, wherever the expression `dusk' appears in DCA, from its obligations under it. It would be easy for the Claimant, when faced with an allegation of non-performance, to argue that it was relieved from performing its obligation because the Penguin Parade Manager should have intervened and exercised his discretion, as penguins may have been present at the relevant time of performance. Such an outcome is not one which the parties, I am satisfied, ever intended when they made the Agreements."
"No transcript or other account of Mr Biles' viva voce evidence was put before the Court. Clearly, however, the Tribunal accepted Mr Biles' evidence as critical to its decision for the next paragraph of its reasons reads: `The Tribunal accepts that `serviced apartments' is a new concept of providing accommodation for visitors. The Tribunal also accepts that such accommodation is temporary accommodation but it is not usually provided for persons travelling by car. In view of those findings the Tribunal finds that the proposed use is of `serviced apartments' and not as a `motel'. In the absence of a full account of the evidence which Mr Biles gave to the Tribunal, it seems to me to be impossible to sustain the appellant's contention that the Tribunal made a finding which was not reasonably open on the evidence."[39]
"132. At the time of making DCA and other Agreements the parties intended, in my opinion, that the Penguin Parade Manager should only exercise the power conferred on him by the definition `dusk' to notify the Claimant to close the Centre and vacate the Facilities when he perceived and determined that circumstances were present which warranted the Claimant ceasing its business operations. Given the effect upon the business of a notification, in my opinion, the parties intended that the Penguin Parade Manager should only exercise his power in special circumstances. It would be open to him to exercise this power, at any time, whilst the Claimant was operating its business. The circumstances, however, must be `exceptional'. They would be circumstances which the parties considered, more likely than not, to be unusual and which would rarely occur. They would not be circumstances which already would be known to the parties as foreseeable and regular occurrences or already dealt with by DCA or other Agreements. The Agreements expressly refer to and recognise `wildlife' in the area. The parties vested the Penguin Parade Manager with this power because, as the principal officer of the most dominant Governmental operation on Summerland Peninsula, he was in the best position to assemble information and determine whether or not circumstances were present which were exceptional, warranted closing down the Claimant's business and taking necessary measures and precautions to overcome or relieve the situation that had emerged. COMA speaks of measures to be considered and introduced to deal with these types of circumstances. The power was not to be exercised capriciously or unfairly. On any view, it was not intended by the parties that this power should be exercised so as to conflict with the rights conferred upon or which were to enure for the benefit of the parties under DCA and other Agreements or, more importantly, to displace or interfere with an obligation imposed upon a party so as to result in the parties failing to satisfy their Objectives, unless exceptional circumstances were present, which warranted the intervention of the Penguin Parade Manager."
"Under the objective theory of the contract, evidence of actual intention is admissible in the limited circumstance where it is evidence of a `shared subjectiveness'; that is to say of matters in common contemplation or of common assumption. Such matters of mutual subjective intention are themselves part of the objective framework of facts within which the contract came into existence, and are thus receivable as part of the surrounding factual circumstances ..."[40]
"134. The State strongly contends that, if its interpretation of `dusk' is rejected, the welfare of penguins, particularly those that gather on Ventnor Road, after sunset, will be endangered. By the Claimant being able to carry on its business up to 90 minutes after sunset, motor vehicles, including the shuttle bus, will be able to drive through them. I consider this submission to be contrary to the evidence. At the time when the parties executed the Agreements, they were aware that penguins would be present on the Site, on Ventnor Road and adjoining the Site, but expected the Claimant to conduct its business in their midst."
"143. Accordingly, I consider the expression `dusk' wherever it appears means `up to 90 minutes after sunset' unless exceptional circumstances emerge during the course of the day, as determined by the Penguin Parade Manager, which would warrant the Claimant's business being closed earlier in order to protect human lives (see for example, although not strictly on point, the Penguin Parade Manager in a letter dated 18 January 2000 to the Claimant [see para 194] in which he warns of the dangers of persons walking down the western section of Ventnor Road after dark) or the natural values of the area. It follows, therefore, I reject the interpretation contended for by the State. I wish to stress that in arriving at this finding I have carefully considered and taken into account all the provisions of DCA and, insofar as they may affect them, the provisions of the other Agreements as well (although they must be read subject to the operation and effect of DCA)."
"147. I do not consider that the matrix of circumstances in which DCA and other Agreements were made, as constituted by what was discussed at the meeting on 18 August 1996, enables me to presume what was in the contemplation of the parties as to the true meaning of the definition of `dusk' which should move me to attribute to it an interpretation different from that which I find. I am satisfied that in light of this matrix of circumstances it was not the intention of the parties to empower the Penguin Parade Manager to determine the business hours of the Claimant. I am satisfied that it was not their intention that the Penguin Parade Manager should be able to exercise the power so as to result in the parties not fulfilling their Objectives or creating difficulties for the Claimant in managing and operating the Centre and in using its best endeavours to satisfy the Operating Requirements in Schedule 7 and to comply with the Amenities Performance Criteria in Schedule 8."
"150. Apart from the catalyst, at the meeting, that prompted the discussion, namely, the subject of the Claimant's business operating hours, I find the matrix of circumstances, which resulted in the insertion of the definition of `dusk' in DCA, does not assist me, in presuming, what was in the contemplation of the parties. The catalyst that prompted the discussion, in my opinion, presumes that the parties intended the definition of `dusk' should serve the purpose of introducing some certainty for the Claimant as to the times within which, it must do or not do something, which leads me to conclude that the parties did intend the expression `dusk', wherever it appears in DCA, should have the meaning and effect which I attribute to it."
(a) I_t must be reasonable and equitable_ - it cannot be said the terms are manifestly unreasonable or inequitable having regard to the Arbitrator's findings.
(b) It must be necessary to give business efficacy to the contract - the Arbitrator has found in substance that the terms are necessary to give business efficacy to the contracts and it cannot be concluded that this finding was not open to him.
(c) It must be so obvious it goes without saying - the Arbitrator has elaborated his findings in such a way that it is open to conclude that the terms implied by him are so obvious that they go without saying.
(d) It must capable of clear expression - although the Arbitrator's formulation might be criticised (e.g. "as determined" presumably means "as determined and notified") nevertheless the critical limitations formulated by him are clearly expressed.
(e) It must not contradict any express term of the contract - there is no direct inconsistency between the implied terms and the express terms of the contract. The effect of the implied terms is to better define the operation of the Penguin Parade Manager's discretion.
"This approach to the meaning and effect of s.38 was informed by the deliberate legislative intention of confining curial intervention in arbitrations earlier mentioned, and it follows (and has been held) that if an arbitrator's construction of a contract is reasonably open, it cannot be said that his error is evident or obvious or that there are powerful reasons for considering that he was in error."[42]
"by permitting (the Penguin Parade Manager) to assume absolute discretion as to when to close the facilities, alternatively by acquiescing in an assumption of absolute power by (the Penguin Parade Manager) as to when to close the facilities (wrongfully and contrary to the terms of the Agreement and the intention of the Agreement);"
"The State has never resiled from its support of the vacation times notified by the Penguin Parade Manager, irrespective of the impact they may have upon the Claimant's business operations."
(a) the alleged declaration of road closure times by the Shire of Bass;
(b) the imposition of closure times upon the use of the Seal Rocks site by the Department of Natural Resources and Environment ("DNRE") from May 2001 pursuant to the planning permit relating to the Seal Rocks Development; and
(c) the imposition from late October 2001 of road closure times on Ventnor Road by the Roads Corporation at the direction of the Minister for Transport pursuant to the provisions of the Transport Act 1983.
(a) Ventnor Road does not form part of the reserve administered by the PINP, but runs into and through that reserve to the Seal Rocks area demised to the company;
(b) the Arbitrator found that the Penguin Parade Manager initially acted on a misunderstanding of the provisions of the COMA and believed that as his letter of 5 February 1999 demonstrates[43], the provisions of Schedule 7 of the DCA imposed on the company an obligation of:
"Ensuring that Ventnor Road is closed at dusk (at a point immediately west of Manndeville Road) to allow penguins undisturbed access to their nests." Whereas in fact the DCA requires that the company: "(c) use the company's best endeavours to ensure Ventnor Road is closed at dusk (at a point immediately west of Manndeville Road)."
(c) the mistaken belief of the Penguin Parade Manager was the subject of dispute and clarification at a meeting on 25 March 1999[44]:
"After the meeting, by letter dated 7 April 1999, the Penguin Parade Manager sought from the Bass Coast Shire Council its `agreement' to the ongoing closure of Ventnor Road at night and requested from it an authorisation for PINP to act as agent of the Shire Council to effect the road closures ... The Penguin Parade Manager was obviously concerned by the source of his power to close Ventnor Road as much of what had been discussed at the meeting concerning (sic) the power conferred upon him by the definition of `dusk'."[45]
"That Council confirms that the Phillip Island Nature Park is authorised to continue to act as Council's delegate to implement the nightly closure of roads on the Summerland Estate as previously authorised by the former Shire of Phillip Island and VicRoads."
"The Shire of Bass Coast did not address the request, as it had been proposed by the Penguin Parade Manager (`the Park [PINP] seeks formal agreement of the Council to the ongoing closure of the road at night and its authorisation to act as agent of the Council to effect such closure')."
"307. A careful analysis of the resolution passed by the Shire Council however does not produce the conclusion that the Council has conferred power or authority upon PINP or the Penguin Parade Manager to do anything. It simply authorises `the continuation of a state of affairs' that never existed and, if they once did exist, were revoked and came to an end by `the declassification' of Ventnor Road almost 5 years earlier, on 12 October 1995."
"Other than in emergency circumstances or for matters associated with emergency maintenance purposes, the permitted use must cease on each day no later than 90 minutes after sunset [being the time as set by the Astronomical Society and published in `The Age' newspaper or such other publication selected by Minister for Conservation and Land Management] or at any other time after sunset which may be specified by DNRE; ..."
"160. DNRE has not disclosed its reasons for exercising the power conferred by Condition 9(b) of the planning permit. I assume, however, that, as the times specified by DNRE coincide with the vacation times notified by the Penguin Parade Manager, it exercised this power as `an extra measure' to protect penguins that may be on Ventnor Road. In my opinion, DNRE cannot exercise the power conferred by this Condition 9(b), unless it has `a town planning' reason for doing so. I accept that the boundaries of `town planning' are extensive and somewhat difficult to define, but, in this case, `the factors' constituting `town planning' reasons must arise from the use of the Site by the Claimant, as permitted by the planning permit, unless `the factors' are something which were not in the contemplation of the responsible authority at the time, when it determined to grant the permit, and certainly some thing (`the factor') that was not the inevitable result of the use permitted by the permit. In this instance the use permitted by the planning permit was always going to involve a motor vehicle, of one kind or another, travelling along Ventnor Road in order to carry patrons to and from it. Penguins and other wildlife were always going to be present. Indeed, the enterprise was put in place to enable visitors to enjoy watching the wildlife. Their protection and the measures to protect them are to be found elsewhere, if it exists at all. It is not to be found in town planning. In my opinion Condition 9(b) does not empower DNRE to specify closure times for the Claimant's business for the purpose of protecting penguins on Ventnor Road."
(a) The test of validity of a planning permit condition was stated by Harris J in 271 William Street Pty Ltd v City of Melbourne[47]; applying the decision of the High Court in Allen Commercial Constructions Pty Ltd v The Council of the Municipality of North Sydney[48]. Planning permit conditions will be valid if they are:
"... conditions which are reasonably capable of being regarded as related to the purpose for which the function of the authority being exercised as ascertained from a consideration of the scheme and the Act under which it is made. This purpose may be conveniently described, in accordance with the expression used by Lord Jenkins in Fawcett Properties Ltd v Buckingham County Council, 1961 AC 636 at p.684, as being `the implementation of planning policy', provided that it is borne in mind that it is from the Act and from any relevant provisions of the Ordinance, and not from some preconceived general notion of what constitutes planning, that the scope of planning policy is to be ascertained."[49]
As to the applicability of this test under the Planning and Environment Act 1987 see Crichton v Moorabbin City Council[50]. The Arbitrator has not applied this test in purporting to determine whether the requirements made under condition 9(b) were valid.
(b) The purposes of the Planning and Environment Act 1987 quite clearly extend to environmental objectives such as the protection of native wildlife including penguins. The objectives of planning in Victoria include:
"4(1)(b) To provide for the protection of natural and man made resources and the maintenance of ecological processes and genetic diversity;"
The objectives of the planning framework established by the Act include:
"4(2)(d) To ensure that the effects on the environment are considered and provide for explicit consideration of social and economic effects when decisions are made about the use and development of land;"
(c) The Arbitrator does not refer to or purport to have considered the provisions of the relevant planning scheme;
(d) The requirements of a condition of a planning permit are enforceable not only by the responsible authority but also by third parties pursuant to the provisions of the Planning and Environment Act. The requirements of such a condition must be presumed valid unless set aside on appeal to the Victorian Civil and Administrative Tribunal or by order of the Court.
(e) It does not follow that because a requirement made under a condition is invalid that a permit holder can necessarily avoid it and take the benefit of the permit. A right of appeal against conditions on permits is given by s.80 of the Planning and Environment Act and a further specific right of review with respect to requirements imposed pursuant to a condition is given by s.149. Provision is also made for amendment of a permit under s.87. A fundamental reason for these provisions is that a permit holder cannot both take the benefit of a permit and reject the burden of a condition unless the requirement under the condition is severable. The relevant principle was stated by Stephen J in Spurling v Development Underwriting[51] adopting the principles stated by the House of Lords in Kent County Council v Kingsway Investment[52]. In that case Lord Reid said at p.90:
"Suppose that a planning authority purports to impose a condition which has nothing whatever to do with planning considerations but is only calculated to achieve some ulterior object thought to be in the public interest. Clearly, in my view, the condition should be severed and the permission should stand. But suppose on the other hand, that a condition, though invalid because ultra vires or unreasonable, limits the manner in which the land can be developed, then the condition would not be severable, for if it were simply struck out the result would be that the owner could do things on his land for which he never in fact obtained permission, and that would be contrary to the intention of the statute."
It follows that if the Arbitrator were correct in regarding the limitation of hours for environmental purposes relating to protection of penguins as being ultra vires (a conclusion which I reject) the question of severability would remain to be determined (in the absence of resolution of the underlying merits of the situation pursuant to statutory process).
"865. In relation to premature vacation times the State adopted the stance that the business should be closed down so as not to endanger the welfare of penguins on Ventnor Road despite there being much evidence of persons driving on Ventnor Road when they were on the road and apparently doing so without harming them, although reports were received in evidence, to which I alluded, of several penguin fatalities on the road over about 4 years. The State never afforded a chance to the Claimant to convey patrons in and out of the Centre when penguins were on the road. It simply accepted that whatever the Claimant proposed to do and despite what was in DCA and other Agreements, it should not be afforded an opportunity even to conduct a shuttle bus, which is what the parties originally agreed should be the means used to convey patrons to and from the Centre. I am unpersuaded that the presence of penguins on the road could not have been overcome."
"717. I have found that the Claimant has established a number of breaches it has alleged against the State. In short, a private business cannot operate profitably if it is denied the opportunity to trade during the busiest period of the day, if its patrons cannot make their way to its doors on peak days because of traffic congestion, particularly if it is located in an isolated area and patrons require a motor car to access it, if barriers are erected across the road to it or if it relies on patrons holding tickets to be admitted to it and its ticket seller shows little enthusiasm for selling tickets. Also, it cannot operate profitably if it incurs financial obligations without being afforded the opportunity to challenge them or is dependent upon Government officials for permission to enhance its enterprise in order to improve its profitability. All these things happened to the Claimant as a result of the breaches which I have found against the State. 718. On numerous occasions before and after it opened for business, the Claimant informed the State of the difficulties it was experiencing and, in most instances, how they could be overcome. I do not rehearse these complaints save to refer to what the Claimant conveyed to Project Monitor, the Premier of Victoria in 1998 and 2000, Ministers, the Executive Director and Senior Public Service Officers. Apart from resolving the problem of the traffic congestion, all these difficulties in my opinion could have been overcome by the State, with little effort, either doing or refraining from doing some thing. Regrettably, as the Project Monitor observes in one of his reports, the actions required to resolve these difficulties had become `bargaining points'. The State did not appear to understand how the difficulties were affecting the Claimant's business. I only set apart the resolution of the traffic congestion, as requiring more effort on the part of State, because it required a little bit of thinking and analysis, as well as some positive action on the part of the State. On the other hand, the State has an abundance of expertise in VicRoads combined with an input from the Penguin Parade Manager to assist the Claimant as to how to best resolve this problem which was so apparent on peak days (80-100-120 days of the year). 719. Had the State used its best endeavours many of the difficulties, being encountered by the Claimant, would have been overcome, allowing the Claimant to enjoy its rights and to receive the benefit of and discharge its obligations under the Agreements, to satisfy the Operating Requirements and to comply with the Amenities Performance Criteria. These difficulties have precluded the Claimant from generating the returns of revenue, forecast and expected by the parties which were so necessary to making it profitable and financially viable and enabling it to pay the concession fees and rental premium, as well as the contribution fees. 720. The matters and events which constitute the breaches of these clauses also amount to breaches of other clauses in DCA, the Lease and COMA. I refer to the findings made by me. I do not repeat them, apart from observing that I cannot think of a more classical breach of quiet enjoyment of a lease, for the demise of business premises, than for a lessor to require his lessee to close the business, being conducted on the premises, at times, when the parties expect the lessee to generate sales and for which the lessee had leased the premises in the first place. 721. All these things combine to move me to conclude that, by it beaching these clauses, as I have found them in sections 2, 4, 6, 7, 9, 10, 12, 13, and, insofar as I found that the State should have consented to the proposals submitted by the Claimant to it on 14 July 1999, 15 of the Reasons, the State has deprived the Claimant substantially of the rights and benefits of the Agreements. The State deprived the Claimant of the opportunity to establish and operate a profitable enterprise. Accordingly, I find that the State did repudiate its obligations under DCA and other Agreements and that all the breaches, apart from denial of access for emergency maintenance purposes and breach of confidentiality requirements, go to the root of the contract. In other words the State breached fundamental obligations of the Agreements. I find that these breaches also breached material obligations of the Lease and COMA." [54]
Breaches of Best Efforts Clauses with Respect to Co-operative Arrangements
"Whether a party has `used his best endeavours' to achieve a stated objective, must be determined objectively in the light of what in fact is required to be done, in the circumstances as they exist, to achieve the stated objective. In such a case: `... he is required to do all that he reasonably can in the circumstances to achieve the contractual object, but no more'."
(a) Claim 8 implementation of traffic management scheme;
(b) Claim 9 appointment of fifth person to OCC;
(c) Claim 11 joint ticketing/new management plan.
"Whatever may appear in the Crown Land (Reserves) Act in my opinion the State and PINP both in fact and law are one and the same thing."
In addition to the matters exemplifying the relationship between the State and PINP set out in paragraph 458 the Arbitrator subsequently set out detailed reasons at paragraph 636 for finding that the State in effect controlled PINP. The Arbitrator's characterisation of the relationship between the State and PINP does not in my view demonstrate a manifest error of law. In substance, the Arbitrator has found as a fact that in the circumstances which occurred the State did exercise control over PINP but did not use its best efforts with respect to the exercise of such control in accordance with its obligations under the contract documents.
Breaches of the Best Efforts Clauses with Respect to Variation of the
"41.1 Variations and amendment (a) Neither party will at any time after the execution of this document make any modification, variation or amendment or give a waiver of a material nature to any one or more of the Project Documents to which it is a party (collectively referred to as an `amendment' in this clause), without first obtaining the consent of the other in writing, which consent will not be unreasonably withheld or delayed. (b) No modification, variation or amendment of this document will be of any force unless such modification, variation or amendment is in writing and executed by each party."
[3] [1999] FCA 1; (1998-99) 160 ALR 543 at 552
[4] [1998] 1 VR 83 at 89-91
[5] (1991) 26 NSWLR 203 at 226
[6] Unreported Victorian Supreme Court decision, 10 February 1995.
[7] [2002] VSCA 113, at [31]
[9] Unreported New South Wales Court of Appeal decision, 26 May 1994.
[10] Secretary Department of Premier v. Hulls [1999] VSCA 117; [1999] 3 VR 331 at 335
[11] Promenade Investments Pty Ltd v New South Wales, Sheller JA at 226
[12] cf Royal Botanic Gardens v South Sydney City Council [2002] HCA 5; 186 ALR 289 per Gleeson J at para.12
[14] (1990) 170 CLR 1 at 17-18
[24] As to the concept of this notion as applied to an administrative decision-maker: see Minister for Aboriginal Affairs v. Peko Wallsend Pty Ltd [1986] HCA 40; (1986) 162 CLR 24 per Mason J at 40-42
[27] Poseidon Ltd & Anor v Adelaide Petroleum NL & Ors [1991] FCA 663; (1991) 105 ALR 25 per Lee J at 44
[28] [1982] HCA 24; (1982) 149 CLR 337 at 346-347
[31] Coulton v Holcombe [1986] HCA 33; (1986) 162 CLR 1 at 7
[32] (1985) 59 ALJR 481 at 483
[34] [1982] HCA 33; (1982) 150 CLR 310 at 319
[36] At 355-6, see also Aickin J at 374 and Brennan J at 404
[39] Crockett J reached a similar conclusion at p.366 and Southwell J at p.372
[40] (1994) 36 NSWLR 290 at 309
[41] Supreme Court of New South Wales (Commercial Division 50224 of 1997, 26 March 1998). The case is reported omitting the relevant passage in (1998) 44 NSWLR 312 at 338.
[42] See also Re Tiki Village International (1994) 2 Qd R 674; Natoli v Walker (New South Wales Court of Appeal 40351 of 1993, 26 May 1994); and Leighton Contractors v South Australian Superannuation Fund Investment Trust (1995) 12 BCL 38.
[47] [1975] VicRp 15; [1975] VR 156 at 162
[54] See also paras.860-869 of the Reasons
[55] (1991) 6 WAR 85; see also Hawkins v Pender Bros. [1990] 1 Qd R 135
State of Victoria
Seal Rocks Victoria
(1980) 144 CLR 83
(1990) 170 CLR 321
(1991) 26 NSWLR 203
(1990) 170 CLR 1
(1984) 156 CLR 41
(1979) 144 CLR 596
(1986) 162 CLR 24
(1982) 149 CLR 337
(1977) 16 ALR 363
(1991) 105 ALR 25
(1986) 162 CLR 1
(1985) 59 ALJR 481
(1982) 150 CLR 310
(1994) 36 NSWLR 290
(1998) 44 NSWLR 312
(1994) 2 Qd R 674
(1970) 123 CLR 490
(1991) 6 WAR 85