Statutory Interpretation
34The starting point must be the words of the legislation.
35In Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355 at 384 McHugh, Gummow, Kirby and Hayne JJ said: -
"[T]he duty of a court is to give the words of a statutory provision the meaning that the legislature is taken to have intended them to have. Ordinarily, that meaning (the legal meaning) will correspond with the grammatical meaning of the provision. But not always. The context of the words, the consequences of a literal or grammatical construction, the purpose of the statute, or the canons of construction may require the words of a legislative provision to be read in a way that does not correspond with the literal or grammatical meaning."
36In Certain Lloyd's Underwriters Subscribing to Contract No IH00AAQS v Cross; Certain Lloyd's Underwriters Subscribing to Contract No IH00AAQS v Thelander [2012] HCA 56 at [23] - [32] French CJ and Hayne J restated "some basic principles" of statutory construction, and after referring to Project Blue Sky stated (at [26]): -
"The purpose of legislation must be derived from what the legislation says, and not from any assumption about the desired or desirable reach or operation of the relevant provisions."
37Their Honours cited Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue (2009) 239 CLR 27 at [47] per Hayne, Heydon, Crennan and Kiefel JJ: -
"This Court has stated on many occasions that the task of statutory construction must begin with a consideration of the text itself. Historical considerations and extrinsic materials cannot be relied on to displace the clear meaning of the text. The language which has actually been employed in the text of legislation is the surest guide to legislative intention. The meaning of the text may require consideration of the context, which includes the general purpose and policy of a provision, in particular the mischief it is seeking to remedy." (citations omitted)
38Section 13(1) of the Act provides that a person who claims to be entitled to a progress payment must serve a payment claim.
39Section 13 is in the following terms: -
"13 Payment claims
(1) A person referred to in section 8 (1) who is or who claims to be entitled to a progress payment (the "claimant") may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.
(2) A payment claim:
(a) must identify the construction work (or related goods and services) to which the progress payment relates, and
(b) must indicate the amount of the progress payment that the claimant claims to be due (the "claimed amount"), and
(c) must state that it is made under this Act.
(3) The claimed amount may include any amount:
(a) that the respondent is liable to pay the claimant under section 27 (2A), or
(b) that is held under the construction contract by the respondent and that the claimant claims is due for release.
(4) A payment claim may be served only within:
(a) the period determined by or in accordance with the terms of the construction contract, or
(b) the period of 12 months after the construction work to which the claim relates was last carried out (or the related goods and services to which the claim relates were last supplied),
whichever is the later.
(5) A claimant cannot serve more than one payment claim in respect of each reference date under the construction contract.
(6) However, subsection (5) does not prevent the claimant from including in a payment claim an amount that has been the subject of a previous claim. "
40Sections 14 and 15 of the Act are in the following terms: -
"14 Payment schedules
(1) A person on whom a payment claim is served (the "respondent") may reply to the claim by providing a payment schedule to the claimant.
(2) A payment schedule:
(a) must identify the payment claim to which it relates, and
(b) must indicate the amount of the payment (if any) that the respondent proposes to make (the "scheduled amount").
(3) If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent's reasons for withholding payment.
(4) If:
(a) a claimant serves a payment claim on a respondent, and
(b) the respondent does not provide a payment schedule to the claimant:
(i) within the time required by the relevant construction contract, or
(ii) within 10 business days after the payment claim is served,
whichever time expires earlier,
the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates.
15 Consequences of not paying claimant where no payment schedule
(1) This section applies if the respondent:
(a) becomes liable to pay the claimed amount to the claimant under section 14 (4) as a consequence of having failed to provide a payment schedule to the claimant within the time allowed by that section, and
(b) fails to pay the whole or any part of the claimed amount on or before the due date for the progress payment to which the payment claim relates.
(2) In those circumstances, the claimant:
(a) may:
(i) recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or
(ii) make an adjudication application under section 17 (1) (b) in relation to the payment claim, and
(b) may serve notice on the respondent of the claimant's intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.
(3) A notice referred to in subsection (2) (b) must state that it is made under this Act.
(4) If the claimant commences proceedings under subsection (2) (a) (i) to recover the unpaid portion of the claimed amount from the respondent as a debt:
(a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1), and
(b) the respondent is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract."
41As Leighton did not serve a payment schedule in response to the First Payment Claim, by reason of s 14(4) it became "liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates".
42The "claimed amount" was the amount in the First Payment Claim (see s 13(2)(a)). There is no dispute that this amount was not paid by the "due date".
43SAS thereby obtained an accrued right that it could enforce in one of the two ways specified in s 15(2); by either moving for judgment, or making an adjudication application. SAS, eventually, took the first option.
44The question is, is there anything in the words of the Act to compel the conclusion that the right that accrued to SAS ceased to exist once it served the Second Payment Claim?
45Leighton's submissions focussed on the "distinction" between a "payment claim" (defined in s 3), on the one hand, and a "claim" (said to be an "undefined term") on the other.
46Mr Rudge SC, who appeared for Leighton, submitted that s 14 gives to a party served with a "payment claim" an opportunity to "reply to the claim" and that if a claimant: -
"[C]hooses to include in a payment claim an amount for the same work that has been the subject of a previous claim (ie a repeat claim), then section 14(1) gives the respondent an opportunity 'to reply to the claim' ie the 'claim' is the repeat claim" (emphasis in original)...
and
...if a claimant elects under s13(6) to include the repeat claim in a subsequent payment claim, then any section 14(4) liability in respect of the repeat claim and any consequent right the claimant had under section 15(1) must have expired because the respondent has a statutory entitlement and opportunity to reply to the repeat claim in a payment schedule under section 14(1)" (emphasis added).
47Insofar as this submission relies on a "distinction" between "payment claim" and "claim", I do not accept it. "Payment claim" is defined in s 3 of the Act to mean "a claim referred to in s 13". That makes clear, in my view, that the reference to "claim" in s 14(1) is a reference to the "claim" made in the "payment claim" to which s 14(1) refers.
48Further, as Mr Simpkins SC, who appeared for SAS, submitted, where a previously claimed amount is included in a subsequent payment claim, there is an opportunity, provided by s 14, to respond to the "claim" made in that "payment claim" by service of a payment schedule. I do not see why it follows from the inclusion by a claimant of a "repeat claim" in a subsequent payment claim that the claimant's accrued rights in respect of an earlier payment claim "must have expired".
49Leighton was not otherwise able to point to, and I cannot see, any words in the Act that removed from SAS the right that accrued to it once Leighton failed to serve a payment schedule in response to the First Payment Claim.
50Leighton pointed to the fact that a claimant may include in a subsequent payment claim a claim made in an earlier payment claim, and submitted that a "continuation of a liability under section 14(4)" in respect of claims that are repeated in a subsequent payment claim "would render superfluous the opportunity to reply to the repeated claims in the subsequent payment claim provided by operation of section 14(1)".
51I do not accept this submission. Leighton's "opportunity" (which it took by serving a payment schedule) to respond to the Second Payment Claim had the effect that it did not "become liable" under s 14(4) in respect of the Second Payment Claim on the due date of that claim. But it does not follow that Leighton ceased to be liable in respect of the First Payment Claim. Nor does it follow that Leighton's "opportunity" to respond to the Second Payment Claim was rendered "superfluous".
52Leighton also submitted that if, as permitted by the Act, claims are repeated, "there is a further opportunity to answer them" and that provision of that further opportunity "cannot co-exist with a pre-existing liability for the same claims that is based on a previous failure to answer them".
53I do not accept this submission. If a claim made in one payment claim is repeated in one made subsequently, the same "opportunity" to answer arises on each occasion. The question is, what is the consequence of not answering the first? Both opportunities can "co-exist" unless there is wording in the statute that removes the first, once the second arises. I see no such wording.
54Leighton further submitted that the construction for which SAS contended is one which would permit "a claimant to approbate and reprobate, in that it would permit a claimant who had repeated claims in a subsequent payment claim that is answered with a payment schedule to go back to an earlier unanswered claim and seek judgment for the full amount of the claim". The submission continued: -
"The respondent to a payment claim that contains claims for repeated amounts from an earlier unanswered payment claim should not be left in a position where there is doubt as to whether the claimant will proceed on the subsequent payment claim or will instead seek to go back to the earlier payment claim and enforce it. This would impermissibly afford the claimant with a technical advantage that could not have been intended by the legislature."
55In my opinion, this submission begs the question of what the Act means. As SAS submits, there can be no objection that a subsequent payment claim includes a component, or perhaps the whole, of an earlier payment claim; the Act permits this: s 13(6). Whether or not a respondent to a payment claim "should not be left in a position where there is doubt" as to what action the claimant will take in relation to an earlier payment claim is not a question I find useful in determining what the Act means.
56Leighton drew attention to the comments of McDougall J in Urban Traders Pty Ltd v Paul Michael Pty Ltd [2009] NSWSC 1072 at [94]: -
"In the present case, there has been no adjudication of the claim raised by payment claim 19. It is not a case where the builder is seeking to have another adjudicator do what a previous adjudicator failed to do to its satisfaction. It is not a case where the builder is seeking to use the processes of the Act repetitiously, in an attempt to get a better outcome. On the contrary, if the builder's contention - that no payment schedule was provided in response to payment claim 19 - is correct, it has obtained the best outcome that it can get, in respect of the particular payment claim. That is because, by operation of s 14(4), the proprietors are liable for the amount claimed. The builder cannot do better than that in any adjudication. By repeating the claim in a subsequent payment claim, the builder gave the proprietors another opportunity to provide a payment schedule. In that payment schedule, the proprietors were entitled to answer not only the fresh aspects of the claim, but also those aspects that (as permitted by s 13(6)) had been included in the earlier payment claim." (emphasis as provided by Leighton)
57In my opinion, his Honour's remarks cast no light on the question before me. His Honour was doing no more than recognising that repetition of a claim in a subsequent claim gives the respondent an "opportunity" to serve a payment schedule in respect of all of the matters in the subsequent payment claim. I do not read his Honour's observations to address in any way the statutory consequence of the failure of a respondent to serve a payment schedule in respect of an earlier payment claim.
58Leighton also referred to the observations of McDougall J in Cardinal Project Services Pty Ltd v Hanave Pty Ltd [2010] NSWSC 1367 at [37] - [38] as follows: -
"Of course, that does not mean that the claimant is entirely without remedy. Except where the outer time limit fixed by s 13(4)(b) of the Act has expired, the claimant retains the right to serve a fresh payment claim. That claim may include amounts that were the subject of previous claims (s 13(6)). In the circumstances under consideration, there could be no estoppel or abuse of process, on the principles discussed in cases such as Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69 and Watpac Constructions v Austin Corp [2010] NSWSC 168.
It is correct to say that, if a fresh payment claim were served, the respondent would have a fresh, and unqualified, opportunity to raise further "defences" in its payment schedule. That, no doubt, is an inconvenience from the claimant's perspective. But the Act's object, to secure cash flow, does not to my mind require that plain words should be given a strained construction so as to enable the claimant to retain some perceived tactical advantage." (emphasis as provided by Leighton)
59Again, I do not find that his Honour's observations assist me in resolving the question before me. The question before his Honour was whether a respondent to a payment schedule could make a second adjudication application which had as its subject the same payment claim raised in a previous adjudication that had been declared void, by consent, by the Court. His Honour was not considering a situation where an earlier payment claim had not been responded to.
60I see nothing in the Act which had the effect of extinguishing SAS's accrued rights under s 14(4) following upon Leighton's failure to serve a payment schedule in response to the First Payment Claim. I see no basis in the words of the statute to conclude that service by SAS on Leighton of the Second Payment Claim had the effect that its accrued rights under s 14(4) "expired or became unenforceable".
61I therefore reject Leighton's submission that, as a matter of statutory interpretation, SAS is not entitled to move for judgment on the basis of the First Payment Claim.