Second ground - no evidence of fill on the site?
70 Her Honour found that there was unconsolidated fill on the site underneath the footings of the eastern wall of the premises. This was common ground. Mr Dawson says that the fill in this location was obvious "as soon as we started digging." The report of Douglas Partners was significantly more cautious about whether the fill in this location would have been apparent. However, neither the builder nor Mr McHugh, both of whom must have observed the trenches, gave evidence.
71 The appellants submit that the finding by her Honour, that "there is no evidence establishing knowledge or imputed knowledge on the Second Defendant's part of the presence of fill anywhere on the site", is not correct. In my opinion, having regard to the evidence of Mr Dawson, that submission should be accepted.
72 The Council approved plans for the dwelling were not tendered at the trial. However, there was in evidence the "Guide to Slab Reinforcement - Detail for Simple Domestic Construction" published by the Council. Under the Guide, when a building site is comprised of non-compacted fill up to 900mm in depth, a slab of 100mm thickness is required with piers at 2.00m centres. For a site with non-compacted fill between 900mm and 1200mm in depth, a slab of 125mm thickness is required. Over 1200mm in depth, a structural engineer's detail is necessary. Provision is also made for the dimensions of footings and columns on sites containing compacted fill.
73 The evidence at the trial included the Council's file relating to this building. It includes a document entitled "Record of Inspection Details." That document has two sections, "Footings Inspection" and "Slab on Ground Construction."
74 In the section relating to "Footings Inspection", notes are made against a standard check-list of items and the document has been initialled. A tick has been placed against the items "Size of footings", "Reinforcement of footings" and "Bearing value foundations." Because only the garage section and the eastern wall of the main house were constructed on footings, this part of the document must relate to the garage section.
75 In the section headed "Slab on Ground Construction", the note in relation to "Structural Engineer's Design" is "NIL." With respect to "Foundation height/approved plans" the note is "higher at front within code", together with the note "OK with engineer." This is consistent with a note relevant to the slab which reads as follows:
"NOTE: alteration to approved plan - height of floor 1200mm above ground at front. Plan indicates 300mm. Builder advises council engineer visited site and requested no cutting of site to restrict ground water disturbance.
- could not ask for amended plan."
76 It would seem, and this is consistent with the final built form of the structure, that in order to avoid cutting into the ground at the rear of the house, which because of the slope would have been necessary to keep the level of the floor at a maximum of 300mm above ground level, the Council had required the slab to be raised to a maximum height above ground of 1200mm at the front of the site. However, "slab on ground construction" denotes that the structure is to be erected without piers or strip footings. The slab is constructed on the ground and the building supported off it.
77 In order to construct the house with a raised slab it was necessary to provide a means of support. This could have been provided either by piers, at appropriate spacings and themselves founded on suitable material, or the slab could have been constructed on properly consolidated fill. The file note does not suggest that either method was utilised.
78 What is clear is that where unconsolidated fill in excess of 900mm is present, the Council's slab reinforcement guidelines impose requirements for a thicker slab and, if the height above natural ground is greater than 1200mm, structural engineer's details are required. If the fill exceeds 900mm, additional brickwork is required when forming the columns.
79 The compelling inferences available from the Council officer's note are that the garage section of the house has been constructed on footings which support the walls of that part of the building whilst the remainder of the house has been constructed on a slab which was for the most part originally intended to be placed on natural ground. The latter would not have required piers and there would have been no need for an engineer to have certified the design. However, once the Council's engineer had intervened to require the slab to be raised to avoid excavation, different considerations arose. Instead of the slab being "on ground", it would now have to be constructed on appropriately consolidated fill or on piers. The fact that the building inspector notes that the Council could not ask for amended plans, together with the fact that the inspector notes that "cut and fill" is nil, indicates that, although the slab was raised, its design was not changed.
80 The relevant Australian Standard 2870.1-1998 "Residential Slabs and Footings. Part 1: Construction" was also in evidence. In that document, "Section 2. Site Classification" provides guidance with respect to proper practices when considering the suitability of a site for the construction of a building. Sites with soft soil or uncontrolled fill are indicated as being appropriately classified as "Class P", sites for which engineering advice is required before the construction of the foundation.
81 As I have already indicated, there was evidence before her Honour as to the nature of the foundation material in some parts of the site. Four test pits were dug and reviewed by Douglas Partners, who are consulting geotechnical engineers. Two of the pits were adjacent to the eastern wall of the garage, one was at the north-west corner of the main house, and the fourth was well away from the house to the south and in the path of the old watercourse.
82 Douglas Partners expressed these conclusions about the site having regard to the evidence available from the pits:
"The principal results of the investigation are summarised as follows:
s test pits excavated in the vicinity of the garage have indicated a subsurface profile comprising filling to depths of 0.7 - 1.0 m overlying stiff residual clays,
s the moisture content of the filling was initially wet decreasing to moist with increasing depth,
s field testing indicated that the filling is of a lower strength than the residual soils,
s the footing supporting the garage (east) wall was measured to be 200 mm thick and founding in the filling whilst the footing supporting the front wall of the dwelling was 300 mm thick,
s prior to the development of the site, it is considered that a classification of M (moderately reactive) would be appropriate,
s the placement of uncontrolled clay filling to depths in excess of 0.4 m would result in a P classification,
s surveying of a selected brick course around the dwelling indicated a difference in level of 25 mm (within the limits of an M site) with the front wall being higher than the rear wall and the front wall peaking at about the front door. Regular monitoring of a brick course would be required in order to establish the existence of any settlement/displacement trends.
s it is considered that the damage to the dwelling is most likely due to the shrink/swell behaviour of the site soils with changes in soil moisture content, with the damage to the garage area exacerbated by the footing founding in uncontrolled filling,
s based on the results of the investigation, the site soils are naturally variable in colour and as such, any obvious distinction between the filling and natural soils based on colour may have been difficult to observe. A variation in texture and strength however, may have been a little more obvious, with the natural soils having a smooth excavation surface whilst the filling would have been slightly more irregular. Any delineation in texture however, would still be slight and possibly not that obvious."
83 The test holes were also observed by Mr Dawson, a building consultant, who gave evidence. He concluded that the holes beside the garage "clearly revealed non-compacted fill and water in the land." In his oral evidence he said:
"There were holes dug on the alongside [sic] the garage, and it was quite obvious as soon as we started digging that there was fill under the foundations from the garage. It was pretty obvious from the other holes dug at the front of the building and at the rear of the building that it wasn't the same texture as near the garage, but it was clay, and I think once a builder is aware that there is some fill on site, he should have called in some expert straightaway."
84 The footing for the garage wall was a shallow footing, described as just below ground level. Mr Dawson's evidence makes plain that the foundation material for at least that part of the house was quite inadequate, thereby confirming at least one mechanism for the failure of the structure.
85 In these circumstances, the fact that neither the Council nor the builder called evidence as to the process of construction of the foundations and the slab assumes considerable significance. The allegation being that the building, both main house and garage, had been constructed on inappropriate fill, with an inadequate slab and either no piers or inadequate piers, could no doubt have been addressed by the builder himself or the relevant officer of the Council. Such evidence not being called, it should be inferred that the evidence would not have assisted either respondent (Jones v Dunkel (1959) 101 CLR 298). Notwithstanding the fact that a submission to this effect was made, the trial judge does not advert to it.
86 It is true that there was evidence which her Honour could accept that at least some of the foundations for the house at a point furthest to the north-west may be in reactive clay. However, given the presence of fill on the eastern side, it could not be concluded that the whole of the main part of the house was on reactive clay. Given the slope of the land and the raising of the floor level at the instigation of the engineer, unless contradicted, the inevitable inference is that a substantial part of the main house must be on fill, the characteristics of which are presently unknown.
87 With respect to the piers, her Honour admitted into evidence a letter from the Council dated 1 September 1998 and signed by the Administrative Officer in which it is said:
"Piers were not used on this dwelling therefore there is no information relevant to your request."
88 The letter indicates that if further information is required contact should be made with Steve McHugh, who was the Council building inspector. However, her Honour noted that she would limit the use of that sentence saying "that statement, being hearsay, is not admissible as to proof of the truth of the assertion."
89 Whatever may be the effect of her Honour's ruling, it is plain that, as the question of whether piers were present was in issue, the statement must at the very least be understood as an admission made by the Council affirming the assertion that there were no piers (see Lustre Hosiery Ltd v York (1935) 54 CLR 134 and s 81 of the Evidence Act 1995). Furthermore, to my mind the admission would have considerable probative force being based upon Mr McHugh's knowledge of the plans and method of construction. Mr McHugh was the Council inspector who inspected the footings, and, although apparently available, was not called to give evidence. Of course, the admission was not joined in by the builder.
90 I am satisfied that her Honour's finding in relation to the lack of evidence of the presence of fill under the house slab cannot be sustained. Consideration of the whole of the evidence at the trial points to a conclusion that the house is built on fill and without piers.