Shoal Bay Beach Constructions No. 1 Pty Ltd v Mark Hickey & the persons listed in Schedule A to the Notice of Appeal trading as Sparke Helmore
[2023] NSWCA 23
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2022-06-21
Before
Gleeson JA, Leeming JA, White JA, Adamson J
Catchwords
- (2001) 188 ALR 566 Groom v Crocker [1939] 1 KB 194 Heydon v NRMA Ltd (2000) 51 NSWLR 1
Source
Original judgment source is linked above.
Catchwords
Judgment (16 paragraphs)
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] In or around February 2014, Shoal Bay Beach No 1 Pty Ltd, a property developer engaged in the construction of a residential development in Shoal Bay ("the Developer"), retained law firm Sparke Helmore to advise and assist it in the sale of off-the-plan units in the development. The respondents/cross-appellants were partners of Sparke Helmore. Following the Developer's winding up in insolvency on 8 June 2018, the appellant/cross-respondent obtained an assignment of the Developer's right to sue Sparke Helmore for what was alleged to be professional negligence and/or breach of contract. In the course of selling the units, the Developer entered into two contracts: one for the sale of lot 52 in the development to a Mr and Mrs Forbes, executed on 6 August 2015; the other for the sale of lot 50 in the development to another Mrs Forbes, executed on 7 August 2015. As was standard in the contracts for sale used by the Developer, clause 42.2 entitled either the vendor or the purchaser to rescind the contract by written notice if certain conditions precedent to completion were not satisfied by the "Registration Date" (being, ordinarily, twelve months from the "Contract Date"). Clause 43 of the contract enabled the Developer to extend the Registration Date upon giving one month's notice to an affected purchaser, if any such extension was for a reason enumerated in the clause. On a number of occasions, Sparke Helmore had advised the Developer that, should it wish to exercise its rights under clause 43 of the contract, it would be required to give affected purchasers at least one month's written notice. Sparke Helmore provided numerous schedules setting out the Registration Dates for the contracts. Following a series of construction delays, the Developer was not in a position to complete by the Registration Date for either lot 52 or lot 50 (being, respectively, 6 August 2016 and 7 August 2016). Nor had the Developer, as required by clause 43 of the contracts, given the purchaser(s) of either lot adequate notice of any proposed extension to the Registration Date. Each purchaser subsequently rescinded the relevant contract for sale. At trial, it was contended by the appellant that that was due to negligence on the part of Sparke Helmore, such negligence consisting of a failure to alert the Developer to the impending deadlines for the exercise of its rights under clause 43 or to seek instructions before the dates for giving notices of extension arrived. The cross-respondent filed a notice of contention claiming that the primary judge should have found that Sparke Helmore had been instructed to seek instructions weekly from the Developer and separately had been instructed to negotiate an extension of time with all purchasers. The primary judge found that Sparke Helmore had been negligent, and had breached a term implied in its retainer to exercise due care and skill, in failing to alert the Developer to the imminent expiry of the period within which the Registration Dates could be extended. The primary judge awarded the appellant $258,598.40 in damages, such award having been reduced to reflect her Honour's finding that the Developer had been contributorily negligent (assessed at 30%) in the events leading to the rescission of the sale contracts. The primary judge also declined to award costs, in circumstances where the quantum of damages received fell well within the jurisdictional limits of the District Court of New South Wales. On the appellant's appeal, the issues before the Court were: (i) Whether the primary judge had erred in reducing the appellant's award of damages on the basis that the Developer had been contributorily negligent; (ii) Whether the primary judge had erred in declining to award interest on the appellant's award of damages at rates of between 11.95% and 12.95% per annum, to reflect the Developer's inability to apply the proceeds of sale from lots 52 and 50 to certain loans which it had taken out to fund the development; and (iii) Whether the primary judge had erred in declining to make an order as to the costs of the proceedings. On the respondents' cross-appeal, the issues before the Court were: (iv) Whether, as the appellant/cross-respondent contended, the primary judge's decision should be upheld on the ground that Sparke Helmore had been instructed to contact the Developer weekly to seek instructions and to negotiate an extension of time with all purchasers; (v) Whether the primary judge had erred in finding that Sparke Helmore, by failing to advise the Developer of the impending lapse of its rights under clause 43, was negligent, in circumstances where it was said that the breach alleged fell outside of the scope of the retainer and amounted merely to a failure to reiterate advice previously imparted to a client; (vi) Whether the primary judge had erred in not finding that, even if Sparke Helmore had repeated its prior advice to the Developer, it would not have prevented the relevant purchasers from rescinding their contracts; and (vii) Whether, on the assumption that Sparke Helmore had breached its duty of care and/or contractual obligations, the primary judge had erred in assessing the appellant's contributory negligence at only 30%. The Court (White JA, Gleeson and Leeming JJA agreeing), dismissing the appeal with costs and allowing the cross-appeal, held: As to issue (iv) (1) It was not open to the appellant to rely on its notice of contention on the cross-appeal as the issues raised by it had not been pleaded, the parties made forensic decisions not to call witnesses, and the course of the trial might have been different had those issues been pleaded: [2] (Gleeson JA), [7] (Leeming JA); [70]-[71] (White JA). As to issue (v) (2) The primary judge's conclusion that Sparke Helmore had breached its duty to advise and to exercise due care and skill was erroneous as the client had been repeatedly advised of the impending Registration Dates and the time limits within which the right to extend Registration Dates subsisted. While Sparke Helmore had been expressly instructed to negotiate and advise on the extension of contracts the Registration Dates of which fell in June and July 2016, the evidence did not support a finding that it was obliged to go beyond the Developer's express instructions, so as to negotiate and advise on all pending contracts for the sale of units: [1] (Gleeson JA), [3]-[5] (Leeming JA), [75]-[81] (White JA). Groom v Crocker [1939] 1 KB 194; Midland Bank Trust Co Ltd v Hett, Stubbs & Kemp (a Firm) [1979] Ch 384; Heydon v NRMA Ltd (2000) 51 NSWLR 1; [2000] NSWCA 374, discussed. (3) In any event, the repeated provision of advice to the Developer, which, through Mr Mirels, confirmed its understanding of the operation of clause 43 on its right to extend a contract's Registration Date was inconsistent with the primary judge's conclusion that Sparke Helmore ought to have reiterated its advice closer to the Registration Dates for lots 52 and 50. A solicitor is not generally obliged to repeat advice previously given to a client, or to advise on what a client already knows: [1] (Gleeson JA), [3] (Leeming JA), [84]-[90] (White JA). Yager v Fishman & Co and Teff & Teff [1944] 1 All ER 552; Fitzwood Pty Ltd, Unique Goal Pty Ltd (in liq) [2001] FCA 1628; (2001) 188 ALR 566; Capebay Holdings Pty Ltd v Sands [2002] WASC 287; Scottsdale Homes Pty Ltd v Gemkip Pty Ltd [2008] QSC 326; Nigam v Harm (No 2) [2011] WASCA 221, cited. R J Jackson QC & J L Powell (General Editors), Jackson & Powell on Professional Negligence (3rd ed, 1992, Sweet & Maxwell) par [4-106], approved. As to issue (vi) per White JA (4) The primary judge did not err in finding that, had notices attempting to extend the Registration Dates been served in time, there was no real possibility that the purchasers of lots 52 and 50 would seek to rescind their contracts on alternative bases, or to object to the validity of the notices: [92]-[94] (White JA). As to issue (i) and (vii) per White JA; Gleeson and Leeming JJA not deciding (6) On the assumption that Sparke Helmore were liable in negligence in not repeating its advice or seeking instructions, the primary judge erred in assessing the Developer's contributory negligence at 30%. Instead, the proper assessment of contributory negligence on the evidence before the Court rests at 80%: [95]-[96] (White JA). (5) Given the Court's findings as to the respondent's liability on the cross-appeal, it is unnecessary to express views on the finding of contributory negligence made by the primary judge: [2] (Gleeson JA), [7] (Leeming JA). As to issues (ii) and (iii) (7) Given the success of the cross-appeal, other grounds of appeal advanced by the appellant do not require consideration.