(a) is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract, or
(iii) to challenge the adjudicator's determination, and
(b) is required to pay into the court as security the unpaid portion of the adjudicated amount pending the final determination of those proceedings.
18 It was submitted by Shell that s 25(4)(b) requires that the adjudicated amount be paid into Court and that it must remain in Court until the proceedings are finally determined. Thus it was submitted the order I made was without jurisdiction
19 Firstly, I do not agree with that construction of s 25(4)(b) of the Act. I am of the view that the legislature would not have intended to fetter a judge's discretion generally in relation to security in the hands of the Court. It also seems to me, in particular, that the legislature would not have intended to fetter a judge's discretion to order that such part of the amount paid into Court that was not in issue could be paid out, if the dictates of justice required such order. If such was intended it would have to be by very clear provisions indeed. There are no such provisions.
20 I am not satisfied that I should grant the relief sought. The Motions are dismissed.
21 Mayr seeks costs of the Motions on an indemnity basis. It is submitted this application should never have been brought having regard to what occurred on 8 March 2006, the subject of the judgment that I have just delivered.
22 On this occasion I do not intend to exercise my discretion to grant indemnity costs. It appears, and I accept from Mr Christie, that his client was concerned to ensure that its position was protected in the Court of Appeal. It appears that Tobias JA's observations set a hare running that was pursued in an application that was unsuccessful: Goldsmith v Sandilands (2002) 76 ALJR 1024. This is not a case that was hopeless from the outset. It was a case that ultimately failed, but there was at least a question as to whether the non-opposition of the orders I made on Wednesday 8 March amounted to what I regard as the end of the matter. Ultimately, the basis upon which I decided the matter was that I took the view that the legislature could not have intended s 25(4) (b) to fetter the discretion of a Supreme Court judge in dealing with security paid into the Court.
23 In all those circumstances I am not minded to award indemnity costs. However, I am of the view that the costs should be payable forthwith as agreed or assessed.
24 I order that Shell Refining (Australia) Pty Limited pay A J Mayr Engineering Pty Limited costs of the motions forthwith as agreed or assessed.
**********