Severstal Export GmbH v Bhushan Steel Ltd
[2013] NSWCA 102
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2013-02-01
Before
Bathurst CJ, Beazley P, Barrett JA, Sackar J
Catchwords
- PROCEDURE - freezing order pursuant to Uniform Civil Procedure Rules 2005 r 25.14 - foreign proceedings - construction of rule.
Source
Original judgment source is linked above.
Catchwords
Judgment (12 paragraphs)
Judgment 1BATHURST CJ: This is an appeal from orders made by a judge of the Equity Division of the Court ("the primary judge") restraining the appellant from removing from Australia cheques delivered by Jones Day to Mallesons Stephen Jaques on 13 October 2011 in the sum of $2,670,016.65 or the proceeds thereof. The order was made pursuant to the powers conferred on the Court by r 25 of the Uniform Civil Procedure Rules 2005 ("UCPR").
Background 2The appellant is a company incorporated in Switzerland carrying on business as an exporter of steel products. The financial records tendered before the primary judge indicate that it is a company of some substance. Its balance sheet for the year ended 30 December 2010 discloses current assets of CHF502,143,582 compared to current liabilities of CHF98,670,057. Its turnover for the year was around CHF2.5 billion whilst its profit before tax was CHF39,316,258. 3The respondent is a company incorporated in India and is the third largest manufacturer of secondary steel products in that country. Its shares are listed on the Bombay Stock Exchange and the National Stock Exchange of India. It has a market capitalisation of around $US2 billion. Bhushan Steel (Australia) Pty Ltd, a wholly owned subsidiary of the respondent, owned 78.6 percent of issued shares in a then Australian Securities Exchange listed coal and mineral exploration company, Bowen Energy Limited. 4Between 17 August 2004 and 9 March 2005, the appellant and the respondent entered into separate contracts by which the appellant agreed to supply hot rolled steel coils to the respondent. The contracts which are particularly relevant for the purpose of the present proceedings are contracts dated 16 December 2004, 3 February 2005 and 18 February 2005 respectively numbered 50002, 50487 and 50625 ("the third, fourth and fifth contracts") and the contract dated 9 March 2005, numbered 50754 ("the sixth contract"). 5The contracts relevantly were in common form. They obliged the appellant to deliver hot rolled steel coils of a particular standard (subject to certain tolerances). Payment was to be made through an irrevocable letter of credit in favour of the appellant open through a Swiss Bank, BNP Paribas (Suisse) SA. Payment was to be made within two days after the bank had confirmed receipt of the documents in full compliance with the credit terms. The contracts did not contain a choice of law clause. 6Steel was delivered and paid for under the third, fourth and fifth contracts. However, prior to the steel the subject of the sixth contract being delivered, the respondent sought to renegotiate the payment terms. The appellant declined to do so and the respondent refused to accept the steel. As a consequence, the appellant terminated the sixth contract on 29 June 2005 and sold the steel appropriated to the contract at a loss. The appellant also incurred additional storage fees in respect of the hot rolled steel coils. 7On or about 1 September 2005 the appellant commenced proceedings in Germany to recover its loss. The Local Court of Düsseldorf declined to hear the matter on the basis that it did not have jurisdiction. The Higher Regional Court affirmed the decision. 8On 26 October 2005 the respondent wrote to the appellant alleging that the steel supplied under the third, fourth and fifth contracts was defective and did not meet the required specifications. The appellant denied any liability for breach of contract. 9On 9 June 2006 the appellant brought proceedings in Geneva claiming damages for breach of the sixth contract. The appellant was successful in its claim both in the Geneva District Court, judgment being delivered on 18 June 2009, and on appeal, judgment being delivered on 15 January 2010. Judgment was delivered in the amount of $US1,795,830 plus interest at five percent from 25 October 2005, $US129,104.25 plus interest at five percent from 31 October 2005 and legal costs of CHF100,000. 10On 8 January 2007 the respondent commenced proceedings in the High Court of Delhi seeking damages for breach of the third, fourth and fifth contracts on the basis that the steel supplied under those contracts was defective. These proceedings have not been concluded. 11Although the question of defective steel did not directly arise in the Swiss proceedings, there was some reference to it. This appears in the following passages of the judgment of the Geneva Court of Appeal in the Swiss proceedings under the heading "Questions of Facts": "h) Between 5 and 14 February 2005, SEVERSTAL and BHUSHAN negotiated the price for a new order. SEVERSTAL made an offer to deliver 7000 to 9000 tonnes for the price of US $690 per metric tonne, whereas BHUSHAN was hoping for a price of US $670 per metric tonne. The parties eventually agreed to fix the price at US $685 per metric tonne. On 9 March 2005, SEVERSTAL posted order confirmation No. 50754 to BHUSHAN, confirming that it had sold it 7000 metric tonnes of steel coils for the price of US $685 per metric tonne - giving a total of US $4,795,000 - for direct exportation and consumption in India. The production month for the goods was April 2005 and the cut-off date for shipment was set for 15 June 2005. An irrevocable letter of credit was to be issued no later than 25 March 2005 through the bank BNP PARIBAS (SUISSE) SA, located in Geneva. A tolerance of around 10% was permitted, per item and in total, in relation to the price and the quantity. This order confirmation, like the previous ones, also specified that the time limit for making complaints was 30 days for visible defects and 60 days for hidden defects, from the date of the bill of lading. It was specified that complaints concerning the quality of the goods would not entitle the purchaser to refuse or delay payment of the invoices. This order confirmation, drafted on SEVERSTAL's letterhead, was not signed by hand by a representative of that company. Before countersigning it, BHUSHAN had changed the deadline for opening the letter of credit to 25 April 2005. i) The goods supplied under order confirmation No. 41387 were loaded - according to the bill of lading - on 28 February 2005. As for the goods supplied under order confirmations Nos. 50002, 50487 and 50625, the first consignment was loaded on 26 March 2005 and the other two on 29 May 2005. ... p) BHUSHAN informed MAHINDRA, in an e-mail dated 1 June 2005, that it had taken note that the goods specified in order confirmation No. 50754 were ready at the port. BHUSHAN had not been able to open the letter of credit on 25 April, as promised. This was because the steel price had fallen and, as a result, BHUSHAN's customers were refusing to pay the agreed price of US $685 because local steel suppliers were offering lower prices. BHUSHAN stated that it was suffering losses on its existing steel stocks and requested that the agreed price of US $685 be revised downwards. q) SEVERSTAL informed BHUSHAN, through a letter sent by its lawyer on 17 June 2005, that it had no intention of renegotiating the agreed price, and made a formal demand for BHUSHAN to open the letter of credit or pay the agreed price before 27 June 2005, so that SEVERSTAL could deliver the goods, failing which it intended to terminate the contract, resell the goods and bring an action for damages against BHUSHAN. ... u) BHUSHAN informed SEVERSTAL, in letters dated 26 October 2005, that some of the steel delivered under orders Nos. 50002, 50487 and 50625 was defective, attaching to its letters reports compiled by the SGS in India. v) In letters dated 11 November 2005, SEVERSTAL informed BHUSHAN that it was contesting its claims on the grounds that the SGS reports were concerned with cold-rolled steel coils, whereas the contracts related to hot-rolled steel coils. Furthermore, the contractual time limit for complaints regarding defects had not been respected. B. a) SEVERSTAL lodged a summons with the District Court on 9 June 2006 claiming the sum of US $1,795,830 from BHUSHAN, with interest at 5% from 25 October 2005 and also the sum of US $129,104.25 with interest at 5% from 31 August 2005. The first sum represents the difference between the price due from BHUSHAN according to the contract of 9 March 2005 and the sum obtained through the offsetting sales. The second sum corresponds to the additional storage fees that SEVERSTAL had to pay to INTERGATE AG due to BHUSHAN's failure to pay the sale price. b) On 8 January 2007, BHUSHAN brought an action against SEVERSTAL and MAHINDRA in the New Delhi High Court for the sum of US $3,390,916.710, indicating that this related to orders Nos. 50002, 50487 and 50625. c) Within these present proceedings, BHUSHAN submitted that the claim should be rejected." 12Notwithstanding this, the respondent placed no reliance on the defective steel in its defence to the Swiss proceedings. That appears from the summary of its submissions by the Geneva Court of Appeal: "BHUSHAN asserts that, according to a usage established between the parties, their intention was that they would be contractually bound only when both of them had signed the order confirmation by hand, such that the sale in issue was not valid. BHUSHAN had deferred the date for opening the letter of credit in relation to the confirmation in issue - initially scheduled for 25 March 2005 - to 25 April 2005, due to the fact that SEVERSTAL needed to find a solution to ensure that there were no defects in the goods to be supplied. According to BHUSHAN, SEVERSTAL had failed to sign the order confirmation of 9 March 2005 in order to avoid the risk that the purchaser would refuse to take delivery of the goods in the event of any defect. In any case, SEVERSTAL should have waited for the letter of credit to be opened before producing the goods, which would have enabled it to mitigate its harm. In its pleadings, BHUSHAN compiled a table apparently showing that SEVERSTAL had produced the steel under the previous orders on dates prior to the opening of the letter of credit. SEVERSTAL had demonstrated particular negligence with regard to safeguarding its own interests by producing the goods notwithstanding BHUSHAN's letter of 1 April 2005, the confirmation of the grievances contained therein SEVERSTAL's e-mail of 7 April 2005, the fact that the letter of credit had not been opened by the specified deadline (25 April) and the sharp fall in the price of steel." 13It should be noted that the parties to the proceedings agreed that Swiss law was the proper law of the contract, an agreement the Geneva Court of Appeal regarded as correct in law. This appears from the following passage of the judgment under the heading "Questions of Law": "2. The parties have argued their respective positions on the basis of Swiss law. However, in view of the international nature of the dispute, we should examine whether that law is in fact applicable. ... 2.2 In this particular case, the vendor's agent was dealing with the purchaser in India at the time that the contract in question was concluded, and there may therefore be grounds for considering whether art. 3, paragraph two of the Hague Convention of 15 June 1955 is applicable. However, the vendor maintained, in its claim to the District Court, that its habitual residence was in Switzerland at the time it received the order and that consequently - in accordance with art. 3, paragraph one of the Hague Convention of 15 June 1955 on the law applicable to the international sale of goods - Swiss law, including the United Nations Convention on Contracts for the International Sale of Goods (CISG) concluded in Vienna on 11 April 1980 was applicable. In its answer, the purchaser concurred with this solution and accepted the application of Swiss law. Subsequently, the vendor indicated, in its reply and in its final pleadings, that the parties had agreed to the application of Swiss law, as the respondent confirmed by continuing to apply it. Both parties also applied Swiss law in their proceedings with the Court of Appeal. Finally, from the start of the proceedings, they have been represented by legal counsel. It may therefore be accepted that the attitude of the litigants during the proceedings demonstrates that they were aware of the question of applicable law and had the intention to have their dispute resolved according to Swiss law. Therefore Swiss law is applicable in this case." 14The appellant unsuccessfully sought to enforce the judgment in the Netherlands and in Germany. It did not seek to enforce the judgment in India. Ultimately, the appellant sought to register its judgment in New South Wales. By Notice of Motion filed on 23 February 2011, the appellant sought orders restraining the respondent from disposing of its shares in Bhushan Steel (Australia) Pty Ltd up to a value of $2,448,712.10 ("the freezing order"). 15The judgment was registered and the freezing order was made ex parte. On 12 September 2011, Simpson J dismissed a motion to stay the execution of the Geneva Court of Appeal judgment which was registered on 3 March 2011 pursuant to the Foreign Judgments Act 1991 (Cth) and to set aside the freezing order: Severstal Export GmbH v Bhushan Steel Ltd [2011] NSWSC 1063. Her Honour noted that it was a significant point of the respondent's argument that the "Geneva proceeding" and the "Delhi proceeding" had a common substratum of fact. In rejecting that submission, she noted at par [34] that the "common substratum" lay in the identity of the parties to the Geneva litigation and the Delhi litigation and that, in each case, the issues concerned contracts for the sale of steel. She stated, "There the commonality ends". 16The conclusion reached by Simpson J reflected submissions made to her on behalf of the appellant. However, the appellant took a somewhat different approach in its defence in the Indian proceedings. This appears from the following paragraphs of its amended defence: "1A. That the aforesaid suit is not maintainable as the defendant no.1 had filed claim against the plaintiff in the Court of Geneva (Switzerland) bearing no. C/13920/2006-8 on June 9, 2006 regarding the contract between the parties which is also subject matter of this suit. The plaintiff was served with the summon of the said case on September 14, 2006 from the Geneva Court and present suit has been filed about 5 (Five) months thereafter and same was not disclosed in the present suit. The Geneva Court has passed judgment on June 18, 2009 in the aforesaid case directing the plaintiff to pay as follows:- i) USD 1,795,830 with 5% interest per year from the 25 October, 2005. ii) USD 129,104.25 with 5% interest per year from the 31 October, 2005. iii) The cost of proceedings which shall include an amount of CHF 100,000 as a participation in the legal fees of the Severstal Export GMBH i.e. the applicant / defendant no. 1. After passing of the aforesaid judgement by the Geneva Court, the present suit can be decided in terms of said judgement. The certified copy of judgement dated June 18, 2009 passed by the Geneva Court along with English Translation are placed on record alongwith Amendment Application and marked as Annexure 'A' & 'B' respectively. 2. That the aforesaid suit is not maintainable as the plaintiff has submitted to the Jurisdiction of the Court of Geneva and has also admitted that the adjudication of disputes between the parties shall be governed by the United Nations Convention on the International sales of goods of 11 April 1980 (CISG Convention). The English translated copies of Claim (Request for Payment) in the Court of Geneva (Switzerland) bearing no. C/13920/2006 on June 9, 2006 for the damage of USD 1'924'934.25 & interest Statement of Defence therein are being placed on record. 3. That the aforesaid suit is not maintainable as this Hon'ble court has no territorial jurisdiction to entertain, try and adjudicate the aforementioned suit as the answering defendant is not having any place of business or office in India. 4. That the aforesaid suit is not maintainable as the plaintiff has suppressed and concealed vital material facts from this Hon'ble Court about the claim preferred by the defendant no. 1 with regard to contract between the parties in Geneva Court. It will be relevant to mention here that the defendant no.1 has filed a case against the plaintiff in the Court of Geneva (Switzerland) bearing no. C/13920/2006 on June 9, 2006 regarding the contract between the parties which are also subject matter of this suit. The plaintiff was served with the summon of the said case in September 14, 2006 from the Geneva Court and present suit has been filed about five months thereafter and same was not disclosed in the present suit. ... 6. That the suit is not maintainable as there cannot be two parallel proceedings between the same parties and regarding contracts having same subject matter. The present suit is liable to be dismissed/rejected/stayed as it would result in multiplicity of proceedings and conflicting decisions. 7. That the suit is not maintainable as the same is barred under Indian laws as the plaintiff has itself chosen foreign law to govern the contract between the parties." 17On 3 December 2010 the judge managing the proceedings in the High Court of Delhi framed as two of the issues for the Court's determination: (i) whether the Court had territorial jurisdiction to entertain the claim, and (ii) whether the suit was barred on account of the judgment and decree of the Geneva Court. 18The respondent applied for security in the Indian proceedings for any judgment it may obtain. The appellant had refused to provide such security. 19Following the dismissal of its motion by Simpson J on 12 September 2011, the respondent's solicitors delivered cheques to the appellant's solicitors in satisfaction of the Swiss judgment on 13 October 2011. The respondent immediately sought and obtained a freezing order under UCPR r 25.14 restraining transmission of the cheques or the proceeds thereof out of Australia.