© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[1998] VSC 102
Supreme Court of Victoria
1998-10-15
Balmford, J.
Original judgment source is linked above.
37(e) A variation shall be valued at the rates included in the Priced Bill of Quantities or Schedule of Rates or in a Schedule of Prices to the extent that those rates are applicable and in the case no Bill or Schedule rate or price is applicable then the rate or price shall be determined by agreement PROVIDED that where a rate or price has been agreed with the concurrence of the Sub-Contractor or failing agreement as determined otherwise than by agreement as between the Contractor and the Superintendent then the same rate or price shall be the basis of valuation as between the Contractor and the Sub-Contractor.
37(f) Where a variation has been valued otherwise than by agreement for the purposes of the Head Contract then in no case shall this clause be construed so as to allow a greater value of the variation taking into consideration the relevant value that in one way or another shall be established as between the Contractor and the Superintendent.
A variation shall be valued in accordance with the rates or prices included in any Schedule included in the Contract if and in so far as the Superintendent determines that those rates or prices are applicable to the variation. Where the Superintendent determines that the rates or prices do not apply to a variation, the rate or price payable for the variation shall be determined by agreement between the Contractor and the Superintendent, but if the Contractor and the Superintendent fail to agree on the rate or price the Superintendent shall determine such rate or price as the Superintendent considers reasonable or the Superintendent may direct that the variation shall be carried out as Daywork.
if, as between the Contractor (John Holland) and the Superintendent (Mr Liddle),
(a) a rate or price has been agreed with the concurrence of the Sub-Contractor (Select); or
(b) a rate or price has been determined otherwise than by agreement; then
that rate or price shall be the basis of valuation as between the Contractor (John Holland) and the Sub-Constractor (Select).
the person appointed to the position named or described in the Second Schedule as the Superintendent or in his absence such other person acting in that position or such other person for the time being or from time to time during the currency of the Head Contract appointed by [VicRoads]
and in the head contract in similar terms; that is, as a specified individual.
To make an order, direction, decision, or determination by a court or tribunal, or other authority vested with the power to so make a determination in relation to some matter.
8. Holland has indicated that its total costs for the additional tip works are in the order of $4.9M, however VicRoads has assessed the total value of the additional works to be $4,217,744.81 . . .
9. Holland is currently in dispute with [Select] . . .
10. Despite this, Holland has advised that it will accept VicRoads' assessment in settlement of all its claims associated with the tip.
(i) a binding agreement was reached between the parties to the effect that the rates and prices to be paid for the variation of the sub-contract between them in relation to the tip relocation works, were the rates and prices set out in the 29 April memorandum;
(ii) if that agreement was conditional on the approval of VicRoads, John Holland waived the benefit of that condition; and
(iii) sub-clauses 37(e) and (f) of the sub-contract have no application to this matter.
Select Plant Hire Pty Ltd
John Holland Construction & Engineering Pty Ltd [1998] VSC 102
City of Heidelberg v. McPherson [1964] VicRp 102; [1964] VR 783