Giles JA cited Krivoshev v Royal Society for the Prevention of Cruelty to Animals NSW Inc [2005] NSWCA 76 where his Honour (with the concurrence of Hodgson JA and Young CJ in Eq) said at [123]:
"Delay is of course undesirable, and is contrary to the public interest in the prompt resolution of disputes. But delay, however undesirable, does not itself mean that on appeal a different result is substituted or a new trial ordered - there would be no sense in causing further delay by a new trial. What must be considered is the effect of the passage of time on the quality of the decision-making, including the perception of an effect."
31 In NAIS at 403, [171], Callinan and Heydon JJ set out arguments by the first respondent in that case to the effect that the Refugee Review Tribunal had not committed jurisdictional error or breached the rules of natural justice in hearing and deciding the matter before it. Their Honours said at 430, [172]:
"The answer to these arguments is that unfairness can spring not only from a denial of an opportunity to present a case, but from denial of an opportunity to consider it. Failure by the tribunal to consider a case can arise not only from obstruction by the tribunal of its presentation but also from self-disablement by the tribunal from giving consideration to that presentation by permitting bias to affect its mind: either way the case is prevented from having a fair impact on the tribunal's mind. Another way in which the tribunal can disable itself from giving consideration to the presentation of a case arises where it permits so much time to pass that it can no longer assess the evidence offered. That is what happened here. The first respondent contended that the appellants could not succeed in the absence of findings that 'delay by the Tribunal actually resulted in a material failure to analyse the oral evidence of the Appellants'. That finding ought to be made because it can be inferred from the delay that, in the absence of contrary evidence, the tribunal had deprived itself of its capacity to do so, and there is no contrary evidence."
32 NAIS concerned the application of the principles of jurisdictional error when setting aside administrative decisions made after a period of delay (see at 373, [13] per Gummow J). Whether everything said by the members of the High Court in NAIS is applicable to delay by a judge in curial proceedings remains to be decided.
33 Gleeson CJ's reference to Monie v Commonwealth and his Honour's reference to the ground of appellate intervention being the error in the decision and not the delay itself gives a different emphasis to that propounded by Callinan and Heydon JJ. Nevertheless, the following remarks by the Chief Justice at 373, [10] are not dissimilar to the observations of Callinan and Heydon JJ:
"In a case of failure to give a hearing when a hearing is required, the person complaining of denial of procedural fairness does not have to demonstrate that, if heard, he or she would have been believed. The loss of an opportunity is what makes the case of unfairness. The appellants in this case do not have to demonstrate that the tribunal's assessment of them probably would have been more favourable if made reasonably promptly. What they have to demonstrate is that the procedure was flawed; and flawed in a manner that was likely to affect the tribunal's capacity to make a proper assessment of their sincerity and reliability. The procedures required by the Act were designed to give the appellants a reasonable opportunity to state their claims and to have those claims competently evaluated. If the tribunal, by its unreasonable delay, created a real and substantial risk that its own capacity for competent evaluation was diminished, it is not fair that the appellants should bear that risk. The delay on the part of the tribunal in the present case was so extreme that, in the absence of any countervailing considerations advanced in the reasons of the tribunal, it should be inferred that there was a real and substantial risk that the tribunal's capacity to assess the appellants was impaired. That being so, the appellants did not have a fair hearing of their claims by the tribunal."
34 Whatever the position may be in this regard, however, I do not regard the delay on the part of the arbitrators as being so extreme as to give rise to the inference that there was a risk that their capacity to assess the evidence and issues before them was impaired. I come to this conclusion not only by reason of the length and complexity of the case before the arbitrators and the length of the actual delay, but by reference to the award. The award was more than 200 pages long. It set out the issues, the reasoning of the arbitrators and their findings in rational, detailed and clear terms. It gives every indication that the arbitrators gave due and proper attention in an appropriate way to the matters that required their adjudication.
35 Rein AJ dealt fully with the issue of delay. His Honour raised the question whether delay in the delivery of reasons could give rise to a "question of law arising out of an award" within the meaning of s 38(2) of the Commercial Arbitration Act (particularly bearing in mind the power under s 42 to set aside an Award on the ground of misconduct on the part of an arbitrator). His Honour did not resolve this question but held against Sea Containers on the basis that, even if delay did amount to a question of law within s 38, he was not persuaded that the delay "has or may have been productive of unfairness". In coming to this conclusion, his Honour said:
"My first impression when I read the Interim Award was that it was a detailed and fair consideration of the issues. In my view, the Interim Award is expressed in clear terms and presents the competing arguments in what appears to be a comprehensive way.
I regard it as of significance that Issues (1), (3), (4), (5), (6) and (7)(b) and (c) are all issues of construction of the various agreements and do not involve issues of credibility of witnesses. Issue (2), whilst not a construction point, does not appear to be based on any adverse finding of any witness's credit but rather is based on inferences to be drawn from undisputed facts. This case is therefore quite different to NAIS (even putting aside the fact that it was concerned with a tribunal acting under a statute).
It is true that the Interim Award does not embark upon detailed analysis of much of the evidence that was before it but I agree with the submissions made by ICT and which I have set out above in [72] that the absence of such analysis is explicable in terms of the Board's findings. It has not been demonstrated that any factual finding of the Board ignores or wrongly rejects specific evidence that was before it, or that its summary of the general problems with SCL's evidence of defects (para 15.1-15.12 TB 581-585), which underpins its approach on that aspect of the case, was based on a misperception of the evidence which it had received. There does follow an examination of each of the categories of claimed defects which in the context appears comprehensive.
Having had the benefit of Mr Street's submissions, I am not persuaded that the long delay in delivery of the Interim Award has or may have been productive of unfairness to SCL because the Board's perception of testimony had been dulled or diminished, or that the failure to advert to the specifics of oral evidence points to any unfairness. The Board's conclusions are in my view expressed with clarity and do not instil disquiet as to the likelihood that time has eroded perception or pressed the Board into an easy path."
36 In my view Rein AJ did not err in the conclusion to which he came. Thus, it is unnecessary to consider whether delay gives rise to a "question of law arising out of an award" within the meaning of s 38(2).
37 I now turn to the ground that relates to the construction of the guarantee clause in each of the Building Contracts (the design ground).
38 The relevant guarantee clause is cl 8.01 in the 025 and 026 Building Contracts and cl 11.01 in the 027 and 028 Building Contracts. The wording of the guarantee clauses in each contract is the same. Clause 8 reads as follows:
"8. GUARANTEE
8.01 If within twelve (12) months from entering service of the Vessel, or fifteen (15) months after delivery whichever is the earlier, this period being referred to as the guarantee period, the Buyer shall notify the Builder that any part of the Vessel manufactured by the Buyer [Builder] has become defective on account of inferior or faulty materials or workmanship but not through fair wear and tear, inadequate maintenance or incorrect operation, or if such defect is discovered prior to delivery as a result of experience with a similar Vessel purchased by the Buyer from the Builder, the Builder hereby undertakes to remedy the defective part without charge, or to pay the costs involved or to arrange for it's representatives to carry out such work. All expenses of transportation of replacement parts shall be paid by the Builder.
8.02 In respect of parts and components fitted during the building of the Vessel under the Contract but not manufactured by the Builder (excluding items supplied by the Buyer) the Builder will provide or arrange with supplier to provide similar guarantee terms to those provided in Clause 8.01 and will pass to the Buyer the benefits of any warranty or guarantee given by the manufacturer.
8.03 Except for the guarantees which are expressly provided in this Contract and the undertakings contained in this Clause 8 all conditions, warranties and guarantees whether statutory, expressed, implied or constructive or arising by reason of any description used are hereby excluded and every form of liability for consequential loss or damage is expressly excluded.
8.04 Any claim made upon the Builder for the enforcement of Clause 8 shall be made by notice to the Builder effective on receipt within the guarantee period or within the period of the relevant manufacturer's guarantee as the case may be."
39 Sea Containers' written submissions correctly summarised the decision of the majority of the Board of Arbitrators in relation to the guarantee clauses as follows:
"(a) under the terms of each of those contracts, ICT was responsible for deficiencies in design up until the point of delivery of the vessels;
(b) ICT's liability following delivery of each vessel was governed solely by the guarantee clause within that vessel's building contract;
(c) ICT's liability under the guarantee clause was limited to defects arising from 'inferior or faulty materials or workmanship';
(d) the guarantee clause and in particular the word 'workmanship' as used in the phrase 'inferior or faulty materials or workmanship' within that clause did not embrace defects or deficiencies in the design of the vessel; and
(e) accordingly, post delivery of the vessels, ICT did not have any ongoing responsibility under the guarantee clause for defects arising from the design of the vessels and was not thereby liable for the cost of repair work that was necessary due to deficiencies in the design of the vessels."
40 Mr Dubler dissented from the majority on the basis that the phrase "inferior or faulty materials or workmanship" in cl 8.01 was, in his opinion, sufficiently wide to encompass design errors where the relevant design formed part of the work that ICT contracted to perform. This, in essence, was the argument advanced by Sea Containers.
41 Sea Containers relied on A/B Gotaverken v Westminster Corporation of Monrovia [1971] 2 Lloyd's Rep 505. Donaldson J, in the course of his reasons, considered whether "workmanship" incorporated "design" in a particular clause of a contract. His Lordship said at 512:
"The contract, as varied, required Gotaverken to supply watertight hatch covers. This required good workmanship both in the design and the execution, and, if there were design errors, I see no reason why these should not be characterised and attract liability as bad workmanship. The alternative view would be that Gotaverken escaped all liability …, which seems an improbable result for the parties to have intended."
42 The Board distinguished the contract in the Westminister Corporation case from the building contracts it was required to construe in the present case. The Board had regard to dictionary meanings of the word "workmanship" (which emphasised the execution of work, rather than design) and a passage from a textbook on shipbuilding which asserted:
"Shipbuilding makes a traditional distinction between defective execution of the specification and plans, through bad workmanship or faulty materials, on the one hand, and defective or faulty design in the preparation of the specifications and plans, on the other hand …" (Shipbuilding Contracts, ed Clarke, 2nd ed (1992)).
43 Rein AJ held:
"The construction taken by the majority of the Board was entirely open to them and is one that does not appear, without the need for extensive analysis, to be obviously wrong."
44 Mr Fagan SC, who together with Mr Hyde appeared for ICT, drew attention to provisions in the Building Contracts that provided for extensive sea trials (at which Sea Containers representatives were entitled to be present) prior to the delivery of the vessels. He submitted that, under the contracts, this process and the provisions for the acceptance of delivery were the agreed mechanism whereby Sea Containers would be protected against design defects for which ICT was responsible. He argued that the intention of cl 8 was to limit the potential liability of ICT after delivery solely to defects of workmanship and materials.
45 On this argument, the design defects were to be dealt with by the sea trial and delivery procedures and after the tests had been passed and delivery had been agreed, there would be no claim for design. This, indeed, was the view to which the majority came. They considered that ICT was responsible for deficiencies in design only up to the point of delivery.
46 A later amendment to Building Contracts 026 and 027 incorporated the following provision:
"Without derogation to the Builder's duties and the Buyer's rights pursuant to cl 8 hereof and subject to any unfinished works and the remedy of any inherent vice or defects in design not reasonably discoverable on acceptance following trials but which have become apparent on inspection before delivery, or for any other damage or claims arising on the delivery voyage or for any minor defects (if any) which shall [be] listed in a Schedule to the Protocol the Buyer shall not be entitled to make or maintain any complaint in relation to or seek any compensation for, the performance of the vessel after the execution of the Protocol."
47 Mr Fagan submitted that this amendment continued to limit liability for design to those defects that became apparent before delivery. On that basis, he submitted, the amendment effected no change to ICT's liability for design as had been provided under the unamended guarantee provisions.
48 The design ground concerns only the "one-off" wording in the four building contracts, the subject of this case. The determination of the question raised by it could not therefore "add, substantially to the certainty of commercial law" as required by s 38(5)(b)(ii) of the Commercial Arbitration Act. Thus, for leave to be granted under s 38, the Court would have to decide that there was a manifest error of law on the face of the award (within s 38(5)(b)(i)).
49 In Promenade Investments Pty Limited v State of New South Wales (1991) 26 NSWLR 203 Sheller JA (with whom Meagher JA agreed) said at 222:
"A manifest error of law on the face of the award may be an error which would be apparent to the judge upon a mere perusal of the reasoned award itself without the benefit of adversarial argument."
50 His Honour's views in this regard were based substantially on the following statement by Lord Diplock in Pioneer Shipping Limited v BTP Tioxide Limited (The Nema) (1982) AC 724 at 742:
"Where, as in the instant case, a question of law involved is the construction of a 'one-off' clause the application of which to the particular facts of the case is an issue in the arbitration, leave should not normally be given unless it is apparent to the judge upon a mere perusal of the reasoned award itself without the benefit of adversarial argument, that the meaning ascribed to the clause by the arbitrator is obviously wrong."
51 Lord Diplock went on to say that, even in cases where questions of construction of contracts with standard terms are concerned, leave should not be given "unless the judge considered that a strong prima facie case had been made out that the arbitrator had been wrong in his construction".
52 In the present case, the error contended for by Sea Containers is by no means apparent upon a mere perusal of the award itself. Indeed, in my opinion, there is a great deal to be said in favour of the argument advanced by ICT in this regard (which the majority of the arbitrators upheld). I am not persuaded that Rein AJ was wrong in the conclusion to which he came in regard to the design ground.
53 The last primary ground is that described as the "IMO Issue".
54 The relevant clause (cl 1.03 of the 025 and 026 Building Contracts) provides:
"The Vessel shall be built to Det Norske Veritas Class + 1A1 Light Craft (CAT) + MV R280 Passenger Ship EO Car Ferry B (PET) and Bahamas Register of Shipping Short International Voyage Passenger Vessel categorised as a Dynamically Supported Craft in accordance with IMO Code of Safety Resolution A.373 (X) 14th November, 1977 in compliance with the By-Laws, requirements and recommendations of the Survey Authorities …"
55 Sea Containers contended that cl 1.03 required the vessel concerned to be constructed in accordance with the IMO Code. The Board found that the words "categorised as a Dynamically Supported Craft in accordance with IMO Code of Safety Resolution A.373 (X) 14th November, 1997" were words of description and did not impose a contractual obligation to build in accordance with the IMO Code. Rein AJ held that the Board's construction of the clause was correct.
56 The Building Contracts provided that the vessel concerned was to be built in accordance with an identified specification. A typical specification (I shall refer to the specification attached to 025 Building Contract) provided:
" 1.2.2 Classification and Survey
The vessel will be built under Survey by Det Norske Veritas and Classed + 1A1 light craft (cat), + MV, R280, passenger ship, EO, car ferry.
The vessel may be categorised as a dynamically supported craft in accordance with IMO Code of Safety, Resolution A.373 (X) 14th November 1977 in so far as it is applied by the National Authorities. It is recognised that this Code applies to vessels up to 450 passenger capacity."
57 In essence, the Board's conclusion was that cl 1.0.3 defined the class to which the vessel was to be built, and the reference to the IMO Code was merely part of the classification description.
58 The reference to Det Norske Veritas and the Bahamas Register of Shipping supports this construction as these are bodies that are concerned with the classification of vessels. The Det Norske Veritas Rules themselves provide that they are "aimed at conformance with the intentions of the IMO Code of Safety for Dynamically Supported Craft - Resolution A.373(X) 1978." They "apply to High Speed Light Craft having a defined restricted service". The restricted service is specified by reference to a restricted maximum distance of sailing from nearest harbour or safe anchorage and a limited vertical acceleration of the craft resulting from a restricted sea state to speed relationship. The Det Norske Veritas Rules define acceptance criteria for the design, construction and testing of High Speed Light Craft of various lengths and speeds and apply the IMO Code only to a limited extent. Different rules apply depending on the particular classification. These matters support the Board's construction of the relevant clause.
59 There is a further consideration, in regard to this issue, to which Mr Fagan referred. Clause 4.03 of the relevant Building Contracts provides:
"After delivery of the Vessel, all responsibility and/or liability of whatsoever nature on the part of the Builder in respect of such Vessel shall cease excepting only that laid down in cl 8."