Scharer v Giro Construction Group Pty Ltd
[2017] NSWCATAP 140
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2016-12-12
Before
Dr J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Introduction
- The essential chronology in this appeal is as follows.
- In 2007, Wayne Scharer and Judith Anderson (the Appellants/Applicants) entered into a contract, via an agent, together with others (the co-principals), for the Respondent to construct balconies on a strata building owned by the Applicants and the co-principals. The construction work took place.
- In 2014, the Applicants commenced proceedings in the Tribunal below in matter HB 14/495581, alleging breaches of s 18B of the Home Building Act in relation to defects with the construction work.
Preliminary Hearing on Applicants' standing
- A preliminary hearing on the question of the Applicants' sufficiency of standing to bring the proceedings was heard by the Tribunal below on 16 November 2015 with the Tribunal ruling (by decision dated 7 January 2016 but not delivered to the parties until 10 February 2016) that the Applicants lacked standing to commence the proceedings in the absence of the other co-principals, and directing that the Applicants join as parties the other co-principals within 14 days, failing which the proceedings were to stand dismissed and a timetable for costs applications fixed.