Respondent's submissions
1.
1. The building is a two-storey brick and concrete commercial building which contains 29 commercial lots and car spaces.
2. There are 13 commercial lots situated on the top floor of the building. One of the top floor lots is lot 24, the applicant's lot.
3. The owners corporation is aware of water leaks to the top floor lots including the applicant's lot.
4. The owners corporation has engaged roofing experts to identify the cause of those leaks and retained plumbers and other building contractors to carry out extensive remedial works to the roof of the main building to fix those leaks and to repair water damage to the lots (remedial works).
5. Remedial works have been carried out in August 2020, October 2022, February 2021, March 2021, April 2021, December 2021, February 2022. The remedial works were largely successful and stopped or severely reduced roof leaks into all the top floor lots including the applicant's lot.
6. Whilst the remedial works reduced the leakage of water from the main building's roof into lot 24 they did not eliminate those roof leaks into lot 24.
7. The key difference between lot 24 and other top floor lots is that there is a number of air conditioning units for various lots in the main building that sit on a wooden platform above lot 24. It appears that the air conditioning contractors have from time to time caused damage to the roof when they have walked on the roof to service, maintain and repair those air condition units and that damage has resulted in further roof leaks affecting lot 24.
8. The owners corporation has carried out the additional works to be done on the roof to prevent water leaking into lot 24 and to make good water damage caused to lot 24 caused by those leaks (rectification works).
(a) October 2021; DBS replaced broken tiles above lot 24 (invoice attached Exhibit R;10)
(b) October 2021 DBS again repaired broken roof tiles caused by air conditioning contractors walking on roof (invoice Exhibit R:11)
(c) February 2022 DBS installed sealant over several cracked roof tiles and fixed the flashing and inspected the whole roof and found no damaged roof tiles (DBS invoice Exhibit R:95)
(d) February 2022 DBS sealed leaking air conditioning pipes above lot 24 (DBS invoice Exhibit R;12)
(e) April 2022 ASP engaged to clean the ceiling lot 24, remove mould and paint the gyprock (Exhibit R;13)
1. A building consultant was engaged by the owners corporation in May 2022. Mr Taylor of BWRA inspected the building on 3 August 2022 and provided a draft report on 28 September 2022. The final report was issued to the owners corporation on 4 October 2022. IN his report, Mr Taylor set out scope of work for the rectification of the defects.
2. The strata committee reviewed the report and resolved that the recommendations made by Mr Taylor to relocate the air conditioning units on the roof to allow other repairs to be undertaken.
3. On 27 October 2022 the strata manager sent an email to the building contractor, Carlton, requesting that the air conditioning units be relocated in accordance with Mr Taylor's recommendations.
4. On 1 February 2023 the applicant wrote to the strata manager to complain about another water leak. Later that day, the strata manager sent a work order to a plumber requesting that the contractor attend and repair the roof leak. On 9 February 2023 the plumber reported that the roof leak had been repaired.
5. Between October 2022 and February 2023 correspondence was exchanged between the strata manager, the builder Carlton and the structural engineer GHA Engineer , which advised against relocating the air conditioning units due to concerns about the structural integrity of the wall.
6. Due to the structural engineers recommendations, the owners corporation has not been able to implement Mr Taylor's recommendations to relocate the air conditioning units. Further, the repairs to the roof recommended by Mr Taylor cannot be carried out until the air conditioning units have been moved.
7. The owners corporation is liaising with the builder, the engineer and Mr Taylor to find a way forward to resolve the issue and remedy the defects in the roof.
8. The owners corporation concedes water damage to the applicant's lot however, the damage is confined to a handful of water stained ceiling tiles, some isolated wet spots on rather old looked carpet and some bubbling paint and mould on the plasterboard ceiling in the bathroom
9. The owners corporation disputes that the damage is major or significant or that it renders lot 24 unfit for occupation.
10. Between 9 -13 April 2022 after torrential rainfall in Sydney members of the strata committee inspected the lot and observed no leaks from the roof or any mould or bad smells in the lot.
11. The owners corporation disputes that the applicant's tenants vacated due to the water ingress issues.