© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2007] NSWIRComm 276
Industrial Relations Commission (NSW)
2007-12-10
Kavanagh J
Original judgment source is linked above.
CITATION: Rodney Dale Morrison v Roche Mining Pty Ltd [2007] NSWIRComm 276
Prosecutor: PARTIES: Rodney Dale Morrison Defendant: Roche Mining Pty Ltd
CATCHWORDS: Charge under s8(1) of the Occupational Health and Safety Act 2000 - defendant company employer of miners - miners working with control of the site under another company - manual roof bolting task - knowledge of soft roof condition - inability to identify applicable existing safe work procedure - untrained employee - knowledge that proper practice for the task not followed - contribution of third party to risk - general and specific deterrence - foreseeable risk - roof fall - fatality - penalty imposed
LEGISLATION CITED: Occupational Health and Safety Act 2000
Capral Aluminium Limited v WorkCover Authority of NSW (2000) 99 IR 29 Department of Mineral Resources of New South Wales) Chief Inspector Bruce Robert McKensey v Kembla Coal & Coke Pty Ltd (1999) 92 IR 8 Inspector Robert Johnston v Hire N' Higher Scaffolding Pty Ltd; Inspector Robert Johnston v Lipman Pty Ltd [2006] NSWIRComm 10 CASES CITED: Lawrenson Diecasting Pty Ltd v WorkCover Authority of New South Wales (Inspector Ch'ng) (1999) 90 IR 464 Markarian v R (2005) 215 ALR 213 R v Thomson; R v Houlton (2000) 49 NSWLR 383 WorkCover Authority of New South Wales (Inspector Belley) v Hughston & Sons Pty Ltd (2002) 121 IR 1 WorkCover Authority of NSW v McDonald's Australia Ltd and anor [1999] 95 IR 383
Prosecutor: Mr M.P. Cahill of counsel Solicitors: Ms M. Rizzo Crown Solicitor's Office LEGAL REPRESENTATIVES:
Defendant: Mr B.D. Hodgkinson SC with Mr M. Shume of counsel Solicitors: Mr G. McCann Sparke Helmore
Prosecution under s8(1) of the Occupational Health and Safety Act 2000
1 This prosecution is brought by Rodney Morrison, the Director, Mine and Forest Safety Performance, Department of Primary Industries against Roche Mining Pty Ltd (the defendant) by way of an Amended Application for Order issued pursuant to s8(1) of the Occupational Health and Safety Act 2000 (the Act). 2 It is alleged in Matter No. IRC2365 of 2006, the defendant company contravened s8(1) of the Act in that it failed to: ensure the health, safety and welfare at work of all its employees and in particular, James Arpine Tautari Adams, Jim Adams and Hamish Lister contrary to section 8(1) of the Occupational Health and Safety Act 2000.
In particular, the defendant: a) failed to provide and maintain a safe system of work in relation to the conduct of the pillar split at the 1-2 cut through in the Kayuga Seam at the Dartbrook Mine ("the pillar split") generally, and more particularly with respect to manual erection of roof support in that it failed to ensure that: i) the Road Header was withdrawn a sufficient distance so as to create a work area of sufficient size in front of the Road Header to allow the roof support to be installed whilst working at all times under supported roof; ii) temporary roof support was erected prior to the commencement of the roof and/or rib drilling process; iii) each roof bolt hole was drilled and bolted, consecutively, across the heading. b) The defendant failed to provide adequate instructions to James Arpine Tautari Adams, Jim Adams, Hamish Lister and Wayne Wallace in relation to the pillar split and in particular regarding the need to ensure that: i) the Road Header was withdrawn a sufficient distance so as to create a work area of sufficient size in front of the Road Header to allow the roof support to be installed whilst working at all times under supported roof; ii) temporary roof support was erected prior to the commencement of the roof and/or rib drilling process; and iii) each roof bolt hole was drilled and bolted, consecutively, across the heading. c) The defendant failed to ensure that an adequate risk assessment was performed with respect to the design and performance of the pillar split prior to the commencement of that work. 3 The defendant pleaded guilty to the charge. 4 Mr M.P. Cahill of counsel appeared for the prosecutor and tendered in evidence an Amended Application for Order, an Agreed Statement of Facts and documents titled: Standard Work Procedure - marked "Draft A"; a Standard Work Practice 9.17 - prepared by Mr M. Coffey, former Occupational Safety and Environment Officer for Roche Pty Ltd and Standard Work Practice 9.18 - prepared by Mr B. Wright of J.R. Wright Consulting Pty Ltd. 5 The defendant was represented by Mr B.D. Hodgkinson SC with Mr M.L. Shume of counsel. The defendant relied upon the Agreed Statement of Facts and the affidavit (with annexures) of Frank Xavier Fulham sworn 20 September 2007. 6 Relevantly, the Agreed Statement of Facts states: 3. The defendant, was an employer. 4. At all material times, the defendant employed workers to work at the Dartbrook Mine near Muswellbrook in the State of New South Wales. 5. At all material times, Dartbrook Mine was both a place of work and a coal mine within the meaning of the Coal Mines Regulation Act (NSW) 1982.
Management, Control and Operation of the Dartbrook Mine 6. At all material times there was a Joint V enture comprising Marubeni Thermal Coal Pty Ltd, Anglo Coal (Dartbrook) Pty Ltd and SsangYong Resources Pty Ltd ("the Joint Venture"). 7. At all material times the Joint Venture held Coal Mining and Coal Exploration Leases, including the Coal Mining and Coal Exploration Leases comprising the colliery known as the "Dartbrook Mine" near Muswellbrook in the State of New South Wales (the "Joint Venture Area"). 8. At all material times Anglo Coal (Dartbrook Management) Pty Limited was a wholly owned subsidiary of Anglo Coal Holdings Australia Limited (ABN 52 079 017 940). 9. At all material times Anglo Coal (Dartbrook Management) Pty Limited ABN 62 007 377 577 ("AC(DM)") was contracted by the Joint Venture to manage, control and operate coal exploration, coal mining and related activities within the Joint Venture area, including management, control and operation of the Dartbrook Mine. 10. In about December 2003 the workings in the Kayuga Seam within the Joint Venture, formerly known as the "Kayuga Mine", were integrated with the workings in the Wynn Seam within the Joint Venture, formerly known as the "Dartbrook Mine". The integrated workings became known as the "Dartbrook Mine". 11. As and from 7 May 2004 AC(DM) assumed statutory control of all parts of the integrated workings. 12. At all material times, Anglo Coal Australia Pty Ltd (ABN 930 760 59679), a wholly owned subsidiary of Anglo Coal Holdings Australia Limited (ABN 520 79 0170 940) employed Daniel Clifford ("Clifford"). 13. At all material times Clifford was appointed as the Mine Manager of the Dartbrook Mine pursuant to section 36(2) of the Coal Mines Regulation Act 1982 (NSW). 14. At all material times Clifford, as mine manager, had full charge and control of all persons employed at the Dartbrook Mine and all operations at the Dartbrook Mine. As mine manager, Clifford's duties and functions included the requirement to enforce the observance by all persons employed at the Dartbrook Mine of the Coal Mines Regulation Act 1982 (NSW), together with any regulations, rules and any schemes and any directions or conditions of exemptions or approvals given under the relevant legislation. 15. Further, at all material times Clifford's duties, as mine manager, included ensuring that the roof and sides or working places and roadways in the mine were adequately supported where necessary for safety. [See: s 37(2)(c)(ii) of the Coal Mines Regulation Act 1982 (NSW).] 16. Further, at all material times Clifford's duties as mine manager included ensuring that officials at the mine were in possession of such information and plans as were necessary to enable those officials to ensure that all operations at the mine for which they were responsible were carried out in a safe manner. [See: s 37(2) (d) of the Coal Mines Regulation Act 1982 (NSW).]
The role of the defendant at the Dartbrook Mine 17. At all material times the defendant was contracted to perform underground mining work at the Dartbrook Mine that was associated with the development of the long wall panel in the Kayuga Seam, together with other underground mining works associated with the integration of the underground workings in the Kayuga Seam with the underground workings in the Wynn Seam. 18. At all material times the defendant employed Frank Fulham as its Project Manager with respect to works being performed underground in the Kayuga Seam. 19. At all material times the defendant employed Douglas Ashcroft ("Ashcroft") as its Production Superintendent with respect to works being performed underground in the Kayuga Seam. 20. At all material times the defendant employed Wayne Wallace. 21. At all material times, Wayne Wallace was appointed by Clifford, in his capacity as the mine manager of Dartbrook Mine, as a Deputy pursuant to section 42 of the Coal Mines Regulation Act 1982 (NSW). 22. At all material times, the defendant employed James Adams as an underground mine worker to work at the Dartbrook Mine. 23. At all material times, James Adams was a member of an underground "development" crew assigned by Ashcroft to a pillar split at the 1-2 cut-through in the Kayuga Seam. 24. At all material times, the defendant employed Jim Adams as an underground mine worker at the Dartbrook Mine. 25. At all material times, Jim Adams was also member of the abovementioned underground "development" crew assigned by Ashcroft to a pillar split at 1-2 cut-through in the Kayuga Seam. 26. At all material times, the defendant employed Hamish Lister as an underground mine worker at the Dartbrook Mine. 27. At all material times, Hamish Lister was a member of the abovementioned underground "development" crew assigned by Ashcroft to a pillar split at 1-2 cut-through in the Kayuga Seam.
Background to the Subject Incident 28. Sometime prior to 26 May 2004, as part of the development work associated with the integration of the underground workings in the Kayuga Seam with the underground workings in the Wynn Seam, a project was developed to split a pillar at the 1-2 cut-through in the Kayuga Seam. 29. The "pillar split" at the 1-2 cut-through in the Kayuga Seam commenced on Day Shift on 26 May 2004. 30. On 26 May 2004 Ashcroft assigned an underground mining crew to commence work on the Pillar Split at the 1-2 cut-through using a Mitsui 200 Road Header. 31. Thereafter, work continued on the Pillar Split at the 1-2 cut-through in the Kayuga Seam on each consecutive shift until the completion of the Night Shift on the morning of 28 May 2004. 32. On 28 May 2004 Ashcroft assigned a day shift crew to continue working on the Pillar Split with the Mitsui 200 Road Header. That day shift crew consisted of: · James Adams - Mitsui 200 Road Header Operator and Steel Handler on the "gopher"; · Jim Adams - "Cable hand" for the Mitsui 200 Road Header and roof bolter; and · Hamish Lister ('Lister") - Eimco Operator and "roustabout"; and · John Daowlis ("Daowlis") - fitter. 33. The roof in the area of the Pillar Split was of sufficient concern for a specific direction to be given at the start of shift meeting held prior to the commencement of work on 26 May 2004. The concerns about the roof in the area of the Pillar Split were such that the development crews working on the Pillar Split were warned to keep cuts to a minimum, to erect one sheet of mesh roof support at a time and to maintain support close to the production face. 34. At the commencement of the Day Shift on 28 May 2004 the roof at the Pillar Split had been bolted to within about 0.5 metres of the face. 35. Further, at the commencement of the Day Shift on 28 May 2004 the heading at the Pillar Split was filled with spoil so that the crew spent the morning up to lunch time "cleaning up the spoil" left by the Night Shift Crew. 36. After lunch on 28 May 2004 the Day Shift Crew returned to the heading at the Pillar Split. Daowlis, the fitter, went to work on the boot end. The balance of the Day Shift Crew then commenced cutting coal:- James Adams operated the Mitsui 200 Road Header; Jim Adams handled the cable; and Lister, the Eimco driver and roustabout, provided general labouring support. 37. When James Adams had cut enough coal for between about "one to two mesh", he stopped cutting coal so that the next round of roof support could be erected. 38. The Mitsui 200 Road Header being used to cut the Pillar Split was not fitted with drill rigs. 39. As there were no drill rigs attached to the Road Header, roof support had to be erected in front of the Road Header, manually. 40. As roof support was to be erected manually, the Road Header had to be reversed back in the heading from the face a sufficient distance to enable the crew to obtain access to the roof in front of the Road Header, for the purpose of manually erecting roof support, whilst remaining behind the last line of previously erected roof support (i.e. working from under supported roof). 41. After James Adams stopped cutting coal, he reversed the Road Header back in the heading, he lowered the cutting head to the floor in the centre of the heading and turned the Road Header off. After the incident, the Dartbrook Mine surveyor established that the Road Header had been reversed back in the heading so that the Road Header's pineapple cutting head was located about 0.2 metres outbye of the last line of previously installed roof bolts. 42. After James Adams had turned off the Road Header, the isolation switch was engaged and both James Adams and Jim Adams "tagged out" the machine. 43. James Adams, Jim Adams and Lister then proceeded to carry the roof bolting equipment and materials inbye of the Road Header so that the next line of roof support, consisting of mesh and roof bolts, could be erected. 44. Once the roof bolting equipment and materials were in place, inbye of the Road Header, Jim Adams started the manual roof bolter and commenced boring holes in the roof of the heading for the roof bolts. 45. The Mine Manager's Support Rules for the Kayuga Seam, said to be applicable to the Pillar Split being performed at the time of the subject incident, provided for a 4/2 bolting pattern in the roof of the heading. The last line of roof support erected in the heading consisted of mesh held in place by two roof bolts so that the next line of support required by the Rules was to consist of mesh and four roof bolts drilled in across the heading. 46. Prior to the subject incident, Jim Adams bored three roof bolt holes into the roof of the heading starting from the left side of the heading looking inbye. But, no roof bolts were inserted into any of the three roof bolt holes bored by Jim Adams into the roof of the heading prior to the subject incident. Immediately prior to the subject roof fall, Jim Adams commenced drilling a fourth hole in the roof of the heading immediately adjacent to the right hand side of the heading looking inbye. 47. Jim Adams was still in the process of drilling the fourth hole, immediately adjacent to the right hand side of the cut-through looking inbye, when the subject roof collapse occurred. 48. It is unclear when and where James Adams was last seen prior to the subject roof fall. 49. However, when interviewed, Jim Adams stated that he last saw James Adams on the left hand side of the heading (looking inbye). But, Jim Adams did not know and could not say what James Adams was doing at the time of the subject roof fall. 50. Immediately after the roof fall, Jim Adams and Lister realised that James Adams had been struck by part of the roof fall and was trapped beneath fallen stone in the vicinity of the pineapple cutting head of the Road Header, which had been lowered to the floor near the centre of the heading. 51. James Adams suffered serious injury as a consequence of the fall and died a short time later as a consequence of those injuries.
Investigation of the subject incident 52. After the event, investigations established that: · The roof fall extended from the coal face back inbye towards the last series of roof bolts; · The fall occurred, essentially, across the full width of the heading; · On the right hand side of the heading, looking inbye, the roof fall terminated at the last series of roof bolts; and · On the left had side of the heading, looking inbye, the roof fall terminated approximately 200mm in front of the last line of roof bolts. · The height of the fall was not uniform. It was thin at the edges, particularly inbye, and rose up to an estimated height of about 1 metre in a dome shape which had its acme located, approximately, in the centre of the heading (i.e. in the vicinity of the pineapple cutting head of the Road Header). 53. Further, no roof bolts had been inserted into any of the three roof bolt holes that Jim Adams had "pre-drilled" across the heading as part of the manual erection of the next line of roof support that was taking place immediately prior to and at the time of the subject roof fall. 54. Further it was established that Wallace, in his capacity as a deputy appointed for the Dartbrook Mine, was assigned statutory responsibility for the area in which the "pillar split" was being performed for the Day Shift on 28 May 2004. Also, as the deputy assigned to that area, Wallace was to supervise the development crew working on the "pillar split" during his shift. 55. Further, when questioned after the event, Wallace stated that he was present in the heading shortly before the roof fall and that he saw the location of the Road Header after James Adams had reversed the Road Header back from the face to enable the next line of roof support to be erected. 56. When questioned after the incident about the location of the Road Header in the heading whilst roof support was being erected, Wallace stated that "[he] would have liked to have seen it normally further back than that". Nonetheless, Wallace gave no direction to any member of the crew regarding the location of the Road Header immediately prior to at the time the crew commenced work on the erection of the next line of the roof support. 57. Further, when Wallace was questioned after the event, he said he had seen Jim Adams "pre-drilling his holes" on occasions prior to 28 May 2004. Wallace was aware that Jim Adams' "system" was to "pre-drill his holes" when erecting roof support, (i.e. Jim Adams drilled a series of holes in the roof before inserting roof bolts into the holes, rather than inserting a roof bolt as he completed drilling each hole.) Wallace did not provide Jim Adams, or any other member of his crew, with directions regarding the "system" adopted by Jim Adams with respect to the "pre-drilling" of holes for roof bolts prior to or on the day of the subject incident. The transcript of Wallace's interview on 11 June 2004 records the following series of questions and answers: Q67 For the purposes of the interview can you tell me, so that it makes sense on the interview rather than looking at the --- A. All right. What I observed was Jimmy was predrilling his holes. On the occasions I went in there I watched them predrilling their holes. I was only there with them for the two days and I never observed them once pushing it to the roof. I am not sure whether they pushed it up with a bolter or lifted it by hand. Then I was there when I was installing their bolts. But I never observed them once how they actually pushed it to the roof. Q68. You said that you saw them predrilling their holes. Does that mean they had drilled a number of holes in preparation for rock bolting? A. I observed him drilling his four holes. He had a system where he drilled his four holes. They then lifted, pushed the mesh to the roof, inserted their bolts and then he drilled and installed the front two bolts. Q69. So if I am quite clear on this; four holes would be drilled before any rock bolts were placed in those holes? A. That's what he done when I observed him. Q70. Was that a normal practice? A. No. Q71. Did you ever discuss with them that practice? A. No. When Mr Wallace was interviewed on 15 October 2004, the following exchange was recorded: Q22. I refer you to question 71 of your record of interview on 11.6.04 where you were asked "did you ever discuss with them that practice" and you answered "no" why didn't you discuss their drilling practice if it was not a normal practice? A. I said at the time it was a system they were used to. I think I also said somewhere else that at no stage did I see them out under unsupported roof.
While the company is no longer working in underground coal mining, it is still operating as a mining company. The company works with heavy equipment above ground and in the mining industry. It employs miners in such a capacity that an element of specific deterrence is factored into penalty. 25 General deterrence is also an element for consideration. The circumstances of this case reveal the need for constant vigilance and the rigorous implementation of safe work practices in even the most basic mining tasks. The mining industry is once more reminded of the inherently dangerous nature of its work and the need for proportionate rigor in the manner in which it carries out every aspect of its mining operations. Even in a circumstance where a basic skill is required in the performance of the task, rigorous application of safe working procedures must be ensured. Training is therefore an essential element of a safe work system. 26 A significant number of documents were placed before the court through an affidavit of Francis Xavier Fulham, the General Manager Operations of Downer EDI Mining Pty Limited. Downer EDI Mining Pty Limited is but another name of Roche Mining Pty Limited and at the time of the incident Mr Fulham held the position of Project Manager for Roche Mining Pty Limited at Kayuga. He opined as to the significant expenditure by the company in its redesign of a safe work method. In the changeover and absorption of the Kayuga seam into the Dartbrook Mine, existing safe systems of work designed by Roche but absorbed into the Dartbrook operation needed revising and co-ordination. Hence, the company produced three standard safe work methods allegedly related to roof bolting on the one seam. 27 There now exists a comprehensive safe work method system for Roche employees. I am satisfied attention has been given to ensure existing work practices have been upgraded. The court is now assured that appropriate regard has been had to the serious deficiency exposed in the existing systems and all employees have been retrained. The system itself has been refined. 28 Some challenge was raised by the prosecutor to the expression of remorse by the company. The prosecutor submitted there was no evidence of either remorse or contrition and drew a distinction between an expression of regret about the occurrence of the subject incident and the tragic outcome of the incident. However, I reject this submission. I find there has been expressed the appropriate remorse and contrition following the occurrence of the said incident. Responsibility has been accepted. I am satisfied the corporation attended to the needs of the family after the employee was fatally injured. 29 It is common ground that the defendant co-operated in the Department's investigation of the incident. The defendant has a good safety record in a dangerous industry and there are no recorded convictions. The defendant is therefore entitled to the leniency of the court appropriately given to a first offender (s 21A(3)(e) of the Crimes (Sentencing Procedure) Act 1999). 30 The evidence of Mr Fulham persuades the court the company is also a good corporate citizen. In penalty there is recognition given to its good industrial character and its fine corporative citizenship. 31 The court has knowledge that there is a prosecution against a third party, Anglo Coal (Dartbrook Management) Pty Ltd. The prosecutor relies on the application of the principles of parity. It submits that due to a prior conviction, Anglo Coal (Dartbrook Management) will face a maximum penalty of $825,000 and is not entitled to any leniency. A defendant in person, the Mine Manager and employee of Anglo Coal Australia Pty Ltd, a company associated with Anglo Coal (Dartbrook Management), has also been charged with a breach of the Act. The applicability of the principles relevant to the breaches of the Act brought against Anglo Coal (Dartbrook Management) and the individual defendant require consideration at a later date. It is difficult to apply consider any principle of parity at this stage when no evidence is before me as to the particulars of the charges brought against Anglo Coal (Dartbrook Management) who had assumed management of the mine and ultimate control over the worksite. Such a submission as to parity will be more applicable when the latter pleas are heard. However, as already determined the contribution to the risk by that third party is relevant to, and has been addressed in, the determination as to the objective seriousness of the offence. 32 I accept the defendant co-operated with the investigation. 33 The defendant relies upon the authority of R v Thomson; R v Houlton (2000) 49 NSWLR 383 to submit it is eligible to receive a deduction for the utilitarian value of the plea. Such discount is offered in recognition of the practical conditions to the administration of justice (see WorkCover Authority of New South Wales (Inspector Belley) v Hughston & Sons Pty Ltd (2002) 121 IR 1, per Walton J, Vice President at [73]-[75]). The range of discount for an early plea of guilty is in the 10-25 percent range. The upper end of that range is usually reserved for cases where the plea was entered at the earliest reasonable opportunity. The plea was entered after an amended charge was filed. The court had set aside 14 days for the hearing. The Amended Application for Order and the plea were filed, and the days vacated, three and a half weeks before the hearing. In such a circumstance, there was some frustration of the valuable use of court's time. Accordingly, I allow in the circumstances a 20 per cent deduction for the utilitarian value of the plea. 34 Nonetheless, the plea has value in the circumstance and the defendant has accepted its responsibility, which has been accompanied by the appropriate expression of regret and contrition. The plea of guilty reflects this. A penalty must be fixed which reflects the matter was a serious breach of the Act but not a worst case. The defendant is further credited for its co-operation with the prosecutor in the particular circumstances of this prosecution. 35 I find the defendant guilty. 36 The defendant is fined in the sum of $180,000.
Orders Accordingly the Court makes the following orders: 1. In Matter No IRC2365 of 2006, I find the defendant guilty of the offence as charged. 2. The defendant is fined in the sum of $180,000 with a moiety to the Department of Primary Industries. 3. As there has been no agreement between the parties as to the quantification of the costs, I will hear the parties on this issue in the event no agreement can be reached. Leave to re-list at short notice.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Rodney Dale Morrison
Roche Mining Pty Ltd
(2000) 99 IR 29
(1999) 92 IR 8
(1999) 90 IR 464
(2005) 215 ALR 213
(2000) 49 NSWLR 383
(2002) 121 IR 1
(2001) 109 IR 316
(2000) 49 NSWLR 6010