© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2024] NSWCA 314
Court of Appeal (NSW)
2024-09-02
Payne JA, McHugh JA, Stevenson J
Original judgment source is linked above.
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] Ms Nerida Robinson and Mr Mark Bowmer (Owners) purchased a vacant block of land in Kiama in September 2017. The Owners approached Construction & Design Australia Pty Ltd (Builder) to construct a residential dwelling and other amenities on the land. The Owners and the Builder met on 24 July, 3 August, 30 August and 16 November 2018 to discuss the design brief. On 19 February 2019, the parties entered into an HIA NSW Residential Building Contract for Works on a Cost-Plus Basis and construction commenced shortly thereafter. Several months into construction, a dispute between the parties arose as to the Owners' budget and ability to finance the build. Construction ceased on or around 12 September 2019. The parties subsequently engaged in an exchange of written correspondence (including an email from Mr Bowmer to the Builder on 16 September 2019, an email and accompanying letter from the Builder to the Owners on 18 September 2019, and an email by Ms Robinson on 20 September 2019, to which the Builder responded with mark-ups). The contract was terminated in February 2020. In their cross-claim, the Owners alleged that the Builder had engaged in misleading or deceptive conduct contrary to s 18 of the Australian Consumer Law by making various representations as to the cost of building. The Owners also sought damages on a no transaction basis. A key issue was the conflict as to what was said in the above meetings. The parties agreed below in MFI-4 that the emails exchanged after construction had ceased (together with other specified documents) were to "be treated as evidence of the contents of the documents but not the truth of the matters alleged in the documents". The primary judge ultimately found that none of the pleaded representations was made. Further, the primary judge found that, whilst it was strictly unnecessary to consider what loss flowed from the alleged misleading or deceptive conduct, the appropriate measure of the countervailing benefit to the Owners was the value of the building works performed, and as such, there was no loss (applying Mills v Walsh [2022] NSWCA 255). On appeal, the issues were whether: The primary judge erred by using some of the documents contrary to the parties' agreement in MFI-4 when determining whether the alleged representations had in fact been made. The primary judge erred in finding that the Owners suffered no loss for the purposes of the misleading or deceptive conduct claim. The Court (Griffiths AJA, Payne and McHugh JJA agreeing) dismissed the appeal, holding: As to issue (i): The primary judge used some of the emails specified in MFI-4 to corroborate or confirm the truth of other evidence concerning whether or not the alleged representations were in fact made, but not as evidence of the truth of the matters set out in those emails: [48], [51], [58], [63] (Griffiths AJA); [1] (Payne JA); [2] (McHugh JA). As to issue (ii): Given the rejection of ground 1, ground 2 did not need to be determined and, in view of their complexity, the issues raised should await a case in which their resolution is essential: [66]-[67] (Griffiths AJA); [1] (Payne JA); [2] (McHugh JA).
JUDGMENT
The primary judgment summarised
Assessing damages for the alleged misleading or deceptive conduct
The parties' submissions summarised 1. (a) Ground 1
(b) Ground 2
(c) Notice of Contention
(a) Ground 1
(i) 16 September 2019 email
(ii) 18 September 2019 email and attached letter
(iii) 20 September 2019 email
24 July 2018 meeting
3 August 2018 meeting
30 August 2018 meeting
16 November 2018 meeting
(b) Ground 2
(c) Notice of contention
Conclusion
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 20 December 2024
Robinson
Construction & Design Australia Pty Ltd
(2004) 218 CLR 592
(1992) 39 FCR 31
(1990) 171 CLR 207
(2020) 282 FCR 530