183 For essentially the same reasons, I refuse leave to amend in respect of the fourth further particular of breach: namely, that set out in para (e) of the particulars to para 31 in the draft third further amended summons."
194 The matters in the trial judge's [168(3)] and [168(4)] were that Jeffery & Katauskas had suggested to Rickard Partners that the design be checked, and that it had been retained on a Level 2 Certification basis with the incidents earlier described.
195 No submissions were made by Rickard Constructions in support of error in the refusal of leave to add to the particulars. The application to amend the particulars was made late in the hearing, and it was refused at least in part because Jeffery & Katauskas had not had the opportunity to deal with the matters alleged in particulars (d) and (e). The trial judge was in the best position to assess the requirements of justice between the parties, and Rickard Constructions has not attempted to show that his exercise of discretion miscarried.
196 The submissions put by Rickard Constructions in this Court to which regard can be had should therefore be restricted. However, I propose to consider the submissions without restriction; they do not, in my opinion, make out breach of duty by Jeffery & Katauskas.
197 It is appropriate now to say more of the letter of 3 May 1999. There was heavy rain in the latter part of April 1999. On 29 April 1999 Mr Treweek met Mr Potts at the site, at the request of Mr Potts. Sub-base had been laid, and had been affected by the rain. Laying of basecourse had not begun; basecourse was first laid a week or so later.
198 Mr Potts said to Mr Treweek, "We have got problems here. Can you comment on what you see as being an issue", and Mr Treweek "commented on issues where he [Mr Potts] pointed". They walked around part of the site, which had a great deal of water ponding between the two buildings, apparently discharging from the stormwater outlets from their roofs, and around some drainage pits. Mr Treweek said to Mr Potts, "You are wasting your time trying to place basecourse over saturated sub-base", and recommended that Jeffery & Katauskas view proof-rolling of the sub-base.
199 There was then discussion at a meeting at the offices of Jeffery & Katauskas, following which Mr Treweek wrote the letter of 3 May 1999 addressed to Mr Potts at Rickard Constructions.
200 The letter of 3 May 1999 began -
"Further to our Thursday 29 April 1999 meeting at our offices we confirm the following points from those discussions."
201 The letter dealt with backfilling around stormwater pits and manholes and installation of underground services, and then -
" 3. Proof Rolling
Currently in most areas the site has been constructed to finished subbase levels. Due to recent prolonged inclement weather the exposed surface materials have become saturated.
J&K recommend that after all surface water has dried off and prior to the commencement of additional fill placement that the area be heavily proof-rolled to delineate potential soft zones before placement of the basecourse layer.
A 10 tonne (or larger) self-propelled vibrating smooth drum roller should traffic the entire site six times with a J&K senior representative observing the final roller pass. Any soft areas identified requiring rectification should be addressed at that time.
Should Rickard Construction require expediency in their approach to enable work to recommence immediately, the saturated surface materials will need to be stripped. J&K cannot currently ascertain the depth of saturation without completing a site visit but would assume the depth to be about 75mm to 100mm. At the completion of stripping, proof-rolling would be required unless J&K were confident the stripped surface was unyielding under construction traffic loads. Regardless of the approach taken all area should be rolled under J&K supervision prior to placement of the basecourse.
Any stripped surface material is likely to be too sandy to permit its reuse as the upper fill layer. A more granular fill is necessary to provide a better CBR.
4. Basecourse
Any imported material should comply with the requirements of the specification or RTA Form 3051. The provider of the material should supply to Rickard Construction ' current ' NATA endorsed test reports for the material being supplied to the project; alternatively J&K can complete an independent test and, in any case, a few audit checks would be wise.
We understand that the thickness of base is 150mm. In our opinion this material should be placed and compacted in two layers. This will reduce the potential of material degradation due to over-rolling and effectively improve roller efficiency, which will ultimately reduce the total time of compaction.
…
6. Density test Results
All outstanding density ratio non-conformances should be retested and comply with the specification.
7. Asphaltic Concrete
Due to the expected heavy loads which will be applied directly on the asphaltic concrete surfacing, we recommend that independent testing be completed during placement of that material. Testing should include observation, coring to confirm layer thickness, density of the compacted mix and mix analysis tests of the supplied product.
Should you require additional information please do not hesitate to contact the undersigned."
202 Save to an uncertain but limited extent to which I shortly refer, Jeffery & Katauskas was not asked to observe the proof rolling of the sub-base as referred to in para 3 of the letter of 3 May 1999. It was not asked to conduct tests of material imported for the basecourse as referred to in para 4 of the letter (the tests being for the quality of the material prior to placement, see the "audit" in the quality control document earlier described, not tests for compaction or the subsequent condition of the basecourse). It was not asked to re-test outstanding density ratio non-conformances as refererred to in para 6 of the letter. It was asked to undertake testing of the asphalt layer during placement. Rickard Constructions exercised its own judgment in the former respects.
203 Rickard Constructions submitted that Jeffery & Katauskas owed Mayne a duty to take care to avoid economic loss if the pavement failed, and was in breach of the duty of care because it failed in early May 1999 or when observing proof-rolling of the basecourse and re-working of areas to give the advice the subject of the advice case.
204 A design engineer engaged by the architect was held in Bevan v Blackhall & Struthers (No 2) Pty Ltd (1973) 2 NZLR 45 to owe a duty of care to the proprietor. Beattie J held that the facts disclosed a "duty-situation", acting on Lord Atkin's neighbour principle from Donoghue v Stevenson (1932) AC 562 (at 80-81). Developments in the law thereafter led to proximity as the guide to a duty of care, and now to the principles explained in cases such as Perre v Apand Pty Ltd (1998) 198 CLR 180 and, with particular present relevance, Woolcock Street Investments Pty Ltd v CDG Pty Ltd.
205 The evidence of Mr Jeffery was that he did not know that Mayne had any interest in the container depot until late in the construction of the pavement; that did not exclude knowledge of, for example, Mr Treweek, but Mr Jeffery had undertaken the engagement on behalf of Jeffery & Katauskas and one would expect that he would have been told of a new Proprietor.
206 Jeffery & Katauskas would nonetheless have known that there was a Proprietor, even if it did not know that Mayne had come to have that status. But it was engaged by Rickard Partners, and was engaged to provide particular and limited services: relevantly, the compaction testing as a Level 2 Certification and, in the language of the engagement conditions, advice explicitly commissioned. It charged Rickard Partners for the compaction testing it undertook, and also for particular services such as Mr Treweek's attendance leading to the letter of 3 May 1999. Its limited role had been come to with clear rejection of the greater responsibilities of Level 1 Certification.
207 This could have been ascertained by Mayne if it had enquired at the time of the Business Purchase Agreement. Whether Mayne knew that Jeffery & Katauskas, or any geotechnical engineer, was providing geotechnical services was far from clear, but beyond Mr Rickard's evidence that Mayne attended site meetings there was no evidence that it showed any interest in such matters. To repeat from earlier in these reasons, Mayne Nickless received Rickard Constructions' promise to construct the pavement in a workmanlike manner and in accordance with sound engineering practice and principles. If it had supervision in mind, Rickard Partners was in that role.
208 By analogy with the observations on Bryan v Maloney (1995) 182 CLR 609 in Woolcock Street Investments Pty Ltd v CDG Pty Ltd at [28], relevant to any duty of care owed by Jeffery & Katauskas to others was the contract defining the task it undertook. The observations of Gleeson CJ and Gummow, Hayne and Heydon JJ included that at the least the contract between the builder or engineer and the original owner defined the task which the builder or engineer undertook, and -
"There would be evident difficulty in holding that the respondents owed the appellant a duty of care to avoid economic loss to a subsequent owner if performance of that duty would have required the respondents to do more or different work than the contract with the original owner required or permitted".
209 I do not think it should be held, in the circumstances I have indicated, that Jeffery & Katauskas owed to Mayne a generalised duty of care to avoid economic loss from failure of the pavement; again, at most there could be a duty to take care in the provision of the services in the task it undertook. There was foreseeability of loss to the Proprietor if the particular services were negligently provided. But that was not enough. Mayne Nickless acquired the container depot and the contract of 23 April 1998 relying, so far as it relied at all, on proper performance by Rickard Constructions of a contract which required Rickard Constructions to have testing in accordance with the quality control document, and which did not provide for supervision by anyone. There was no evidence of reliance by Mayne. Nor, for similar reasons to those earlier given, was Mayne in a position of vulnerability. It came into the picture as purchaser from Container Park in a major commercial transaction in which it could protect itself against defective construction of the pavement, whether the delinquency be by engineer, materials supplier or tradesman. In my opinion, Jeffery & Katauskas did not owe even the more limited duty of care to Mayne.
210 But if Jeffery & Katauskas did owe a duty of care, it was not established that it failed to exercise reasonable care and skill in the provision of its services. As I have noted, it was no part of the proceedings that Jeffery & Katauskas made mistakes in carrying out the compaction testing required of it.
211 I return to the letter of 3 May 1999. The trial judge accepted (at his [186]) that Mr Treweek "was asked to formalise an advice on certain points, and that is what he did in the 3 May letter". Mr Treweek's evidence bore out the view his Honour took of the occasion. The "issue" from the "recent prolonged inclement weather" concerned the sub-base. Basecourse had not yet been laid. It can readily be accepted that Mr Treweek was asked to respond, and only responded, to the concerns Mr Potts expressed at the time, and that their minds were not on moisture content of basecourse at the time the asphalt wearing layer was laid or on testing immediately prior to that time. Mr Treweek did tell Mr Potts that he was wasting his time trying to place basecourse over saturated sub-base, but that was an observation upon the sub-base and did not tell Mr Potts anything new; Mr Treweek said specifically in his evidence -
"Q. In the context when you understood about the significance of moisture on this site, it was important for you to make it plain that base course of this type might be prone to failure through the build up of pore pressure if the moisture was not controlled so that it was, in fact, within acceptable limits before sealing?
A. It wasn't an issue for me to comment on because it wasn't raised as being a potential issue, and I didn't say anything in relation to that."
212 The trial judge accepted Mr Treweek's evidence. There was no occasion for Mr Treweek to go further.
213 The Court was not taken to evidence of engineering practice to support that he should have gone further. Its counsel did obtain evidence from Mr Thom -
"Q. Would you go to the letter of 3 May, page 6135. Assume on 29 April, you had an understanding that water might flow on the base course which you would understand was particularly susceptible to moisture following compaction even to the extent of morning dew and you had written about the base course, would you have mentioned that?
OBJECTION (MR DEMPSEY); QUESTION ALLOWED.
A. Yes, but it is a matter of risk, contractors risk. If they let the pavement get wet then they have got to the do [sic] extra work to dry it out.
Q. Would you have advised the contractor that it's running a risk?
A. Yes.
Q. Look at page 6137, you will see that advice has been given about the imported material complying with the RTA specification?
A. Yes.
Q. If you had been giving any advice about the base course and was aware of its sensitivity to moisture would you have also made some mention of that fact?
OBJECTION (MR DEMPSEY).
HIS HONOUR: What factor, Mr Corsaro?
CORSARO: Q. That it was sensitive to moisture.
A. Yes."
214 The assumption did not meet the situation, and in any event Rickard Constructions knew it was running a risk in laying the asphalt wearing layer over wet or soft basecourse (see Mr Rickard's evidence of taking a commercial decision). It also knew that, like all materials, the basecourse was sensitive to moisture. Presumably the questions were directed to particular sensitivity ("the morning dew"). Accepting that Mr Thom would have "made some mention" of the fact that the basecourse was sensitive to moisture does not make out the advice case, and in my view fell well short of evidence that Jeffery & Katauskas failed to exercise reasonable care and skill in not giving the advice the subject of the advice case.
215 There was also evidence from Mr Leventhal -
"Q. If you had gone to the site and had been asked to look at the site and you were aware that it was a site which had moisture problems because of lack of drainage or other condition?
A. So we're talking challenges with surface drainage?
Q. Yes. If you went to the site and you saw that this was a site that had problems because of poor drainage let's say, and you were asked to advise on how the basecourse should be placed assuming that you knew it was going to be placed in two levels, you would have advised wouldn't you some sort of procedure that would have ensured testing and dry back for the first layer before placement of the second layer, correct?
A. Yes, that would be a reasonable approach.
Q. And then testing and dry back for the top layer immediately before the laying of the asphalt, correct?
A. Yes.
Q. And would you have told the contractor that in the event that it wetted up, that it should be recompacted and retested and allowed to dry back again?
A. There's an intermediate step which would have been moisture condition, and then compact."
216 Mr Treweek was not asked to advise on how the basecourse should be placed beyond the separate levels; and Rickard Constructions knew that wet material should be dried back: that was why it undertook the tyning and aerating or replacement of basecourse. When the material was disturbed it did not need to be told it should be retested for compaction, although it failed to do so. This evidence did not assist the advice case.
217 I go then to advice at other times. I can see no basis for advice other than as part of a supervisory role in relation to proof-rolling. There were occasions when Jeffery & Katauskas was recorded as observing proof-rolling; these were relied on for the submission that it should as part of a supervisory role have advised in relation to moisture content.
218 A daily site report of Jeffery & Katauskas for 18 May 1999 recorded "Proof roll pavement area west of Building 2, failed inspection required tyning and aerating". Another for 19 May 1999 recorded "Talk to Chris [Potts] re: subbase material heaving nth of Line 1, base will be removed, tyne & aerate fill material compact and reproof roll. Required by J&K". Both daily site reports were of occasions of attendance for compaction testing. The technician concerned could not recall the occasions. Jeffery & Katauskas' charges to Rickard Partners, generally only for tests at so much per test, had charges at an hourly rate for tests on 18, 19 and 20 May 1999, for nearly full days (including travel) on each occasion. There was no like mention of proof rolling in a daily site report for 20 May 1999, although there had been proof rolling on that day. These occasions were most likely proof-rolling of sub-base, not basecourse.
219 Mr Hulbert's diary for 29 July 1999 recorded proof rolling of an area prior to the tack coat spray and that "J & K checked same with CP [Mr Potts]". On 4 August 1999 it recorded Jeffery & Katauskas' attendance for tests to a particular backfill area "and for proof rolling of DGB", and on 6 August 1999 that Jeffery & Katauskas "viewed proof rolling". His diary had no entries of Jeffery & Katauskas observing proof rolling corresponding to the two Jeffery & Katauskas daily site reports.
220 A number of other entries in Mr Hulbert's diary recorded that "J&K" was on site, but Jeffery & Katauskas attended the site for, for example, asphalt testing and these could not properly be taken into account. The often cryptic records were not materially filled out by oral evidence. No invoices for Jeffery & Katauskas' charges for attendance at the site on any of these occasions were in evidence.
221 It can not be concluded from these few records that Jeffery & Katauskas undertook a supervisory role in relation to the condition of the basecourse immediately before the asphalt wearing layer was laid. As I have said, the May 1999 occasions were probably sub-base rather than basecourse. There were numerous references, in Mr Hulbert's diary and elsewhere, to proof rolling without any involvement of Jeffery & Katauskas. The occasions in the records mentioned above were exceptions, readily enough explicable because the technician on site for other purposes happened to observe proof rolling and, it must be accepted, on one occasion said that the material had to be re-worked. The preponderance by far, on the evidence, was that Rickard Constructions proof rolled and decided whether or not to proceed to sealing and laying asphalt without reliance on Jeffery & Katauskas.
222 Indeed, this appears specifically from other evidence. Mr Rickard gave evidence of seeing proof rolling, after the letter of 3 May 1999, in company with Mr Potts; he said to Mr Potts "That's good", and Mr Potts said "We're getting it right now". In a note attached to a Jeffery & Katauskas field density worksheet for 2 June 1999 the technician recorded "left site still rolling & trimming DGB20 areas Lance [Woodworth] and Chris [Potts] of Rickards said they will proof roll base themselves with loaded fork prior to tack coat, and fix soft spots". Rickard Constructions exercised its own judgment as to proof-rolling and the suitability of the basecourse for sealing and laying asphalt.
223 Jeffery & Katauskas was not expected to and did not oversee the suitability of the basecourse for laying the asphalt wearing layer, notwithstanding that on a few occasions, for uncertain reasons, it observed proof rolling. It was not incumbent on it to advise in relation to the susceptibility of the basecourse material to moisture, or that testing for moisture content immediately prior to laying the asphalt wearing layer was necessary or desirable. There was no breach of duty in failing to do so.
224 In my opinion, Mayne did not have a cause of action against Jeffery & Katauskas. It is again unnecessary to consider Mayne's damages and whether there was effective assignment of a cause of action, or whether the trial judge was in error in refusing the application by Rickard Constructions to join Mayne as a plaintiff claiming in its own right.