NSWNSWDC
Repfix Industries Pty Ltd v FBD Group Pty Ltd
[2020] NSWDC 594
District Court of NSW|2020-10-07
View original sourceAt a glance
Source factsCourt
District Court of NSW
Decision date
2020-10-07
Source
Original judgment source is linked above.
Judgment (4 paragraphs)
[1]
BACKGROUND
- I delivered reasons for judgment in this matter on 8 September 2020 [1] and afforded opportunity for the parties to try to resolve amongst themselves dispositive orders, including costs. The parties remain divided on the question of costs. I will return to the other dispositive orders at the conclusion of my determination of the dispute about costs.
- To recapitulate, and stating the matter broadly, the plaintiff brought a claim for its unpaid costs of supplying carpentry and joinery services to the defendant across three different sites. That claim was defended partly on the basis that even if the claim was established, it was extinguished or reduced in its value on the basis that the works on two of the sites were defective and that the defendant/cross-claimant was entitled to rectification costs.
- Both claims substantially failed. The plaintiff was unable to establish agreement to terms for payment that it contended for. The cross-claimant failed to establish any intention to carry out the renovation works even in respect of works which did not comply with the specifications and plans, and this took its case out of the general run of cases in which the principles of Bellgrove v Eldridge (1954) 90 CLR 613 applied. The Court did, however, acknowledge an entitlement in the cross-claimant to receive nominal damages for proof of defective works at two of the sites.
- With this background, the plaintiff says that on the question of costs, the practical result was that both parties' claims substantially failed with the consequence that the parties should bear their own costs. That characterisation, it says, accords with the reality that the hearing time was essentially equally divided between the admission of evidence for the two respective claims.
- The defendant/cross-claimant maintains that though it failed on obtaining an order for damages under the principle in Bellgrove v Eldridge, its 'success' in obtaining an order for nominal damages, underpinned by findings that the works were indeed defective in relation to two of the sites, meant that it should not have to pay the plaintiff/cross-defendant's costs on the cross-claim since it could not be said that the plaintiff/cross-defendant was successful. Accordingly, there should be no costs order in relation to the cross-claim. In effect, neither party could be said to have been successful in relation to the cross-claim.