Rectification
143 The defendant's case on the subject of the rectification of the Project Management Agreement was pleaded in pars 27A to 27J of the Defence to the fourth amended statement of claim, as follows:-
""27A In further and alternate answer to the whole of paragraphs 1 to 23.2, the defendant says that clause 5.4 of the agreement did not reflect the common intention of the parties to the agreement at the time of the agreement to the extent that the clause purported to provide that, if Building Consent was not to be granted by 28 February 1996, either party to the agreement may terminate the agreement.
27B The common intent of the parties to the agreement at the time of the agreement was that there was no requirement that the Building Consent be obtained by 28 February 1996 or at any specified time except as provided by clause 5.1.2 of the agreement (the "common intent").
27C At all material times, the agreement was liable to be rectified so as to reflect the common intent by deleting the words "and Building Consent" from clause 5.4 of the agreement.
27D By 28 February 1996, Development Consent had been obtained in respect of the project the subject of the agreement and, not later than 6 weeks thereafter, Building Consent was lodged in respect of the project in accordance with clause 5.1.2 of the agreement.
27E If, either on 21 days notice of termination or forthwith, the plaintiff had purported to terminate the agreement by reason of any failure to obtain Building Consent by 28 February 1996 or, alternatively, within 21days of any notice of termination, Oceanview would have contested the validity of the purported termination of the agreement by the plaintiff.
27F The contest by Oceanview as to the validity of the purported termination by the plaintiff would have included an application by Oceanview to the Court for an order rectifying the agreement so as to reflect the common intent by deleting the words "and Building Consent" from clause 5.4 of the agreement and for an order specifically enforcing the agreement as rectified and for further and consequential orders, including costs.
27G The Court would have made orders so rectifying and so enforcing the agreement.
27H Upon rectification of the agreement, even if the plaintiff could have validly terminated prior to that time (which is denied), the plaintiff would no longer have been entitled to validly terminate the agreement with effect as and from the date of the agreement by reason of any alleged failure to obtain Building Consent by 28 February 1996.
27I Any purported termination of the agreement by the plaintiff by reason of the failure by any party to obtain Building Consent by 28 February 1996 would have been found by the Court to have been wrongful and the plaintiff would have been compelled to specifically perform its obligations under the agreement.
27J In the premises, any breach of retainer and duty of care as alleged by the plaintiff against the defendant (which is denied) could not have caused and did not cause any loss or damage to the plaintiff.""
144 These allegations in pars 27A to 27J of the Defence were disputed by the plaintiff.
145 The defendant did not in the Defence made a claim that the Project Management Agreement be rectified. He would have had no standing to make such a claim, because he was not a party to the Project Management Agreement, the parties to which were the plaintiff and Dramwren (or Ocean View).
146 However, the defendant alleged in the Defence that cl 5.4 of the Project Management Agreement, insofar as it conferred a right to terminate the agreement if Building Consent was not granted by 28 February 1996, did not reflect the common intention of the parties to the Project Management Agreement at the time the Project Management Agreement was entered into and that, if the plaintiff had purported to terminate the Agreement on the ground that Building Consent had not been granted by 28 February 1996, Ocean View would have been entitled to apply to have the Agreement rectified by deleting the words "and Building Consent" from cl 5.4, that Ocean View would in fact have brought proceedings for rectification and that those proceedings would have been successful and upon a court making an order for rectification of the Project Management Agreement the purported termination of the agreement by the plaintiff would have been invalidated.
147 If the allegations made by the defendant in the Defence were established, they would be relevant to the issues of whether the defendant had been negligent and whether, if the defendant had been negligent, his negligence had caused the plaintiff any loss or damage.
148 In support of his case on rectification the defendant relied on arguments based on the history of the drafting of the Project Management Agreement, on an argument that there was no rational explanation for the inclusion of the words "and Building Consent" in cl 5.4 and on an argument that cl 5.4, if the words "and Building Consent" were included in it, would be in conflict with cl 5.1.2 of the Project Management Agreement.
149 As I stated earlier in this judgment, the task of drafting the Project Management Agreement was primarily allocated to the defendant and between early September 1995 and mid November 1995 the defendant prepared at least nine drafts of the Project Management Agreement. These drafts were submitted to Mr Newhouse as solicitor for Ocean View, which was controlled by Mr Robin Wise. From a certain point of time drafts were also submitted to Blake Dawson Waldron solicitors acting for the Hong Kong Bank.
150 The summary in the defendant's written submissions of the tortuous history of the drafting of the Project Management Agreement covers many pages of the written submissions. In my opinion, this summary is an accurate summary of the history of the drafting of the Agreement but I do not propose to repeat all of it in this judgment. I will refer only to certain parts of the history of the drafting of the Agreement which are central to the defendant's submissions.
151 On 25 September 1995 the defendant prepared a sixth draft of the Project Management Agreement. This was the first draft of the Project Management Agreement to be sent to the Hong Kong Bank or its solicitors. At this stage the clause in the agreement which ultimately became clause 5 was numbered as clause 6 and the clause which ultimately became cl 5.4 read:-
""6.4 In the event that Council refuses to grant Development Consent or has not granted Development Consent by 31 December 1995 either party may by notice in writing to the other terminate this agreement and neither party shall have any right or action or claim for damages or specific performance against the other.""
152 Blake Dawson Waldron prepared a Memorandum of Comments on the draft, which was dated 11 October 1995. The comments included the following (item 4):-
""4. Add the word "Building Application" to the heading in clause 6. In addition, add a further clause to clause 6 specifically requiring the Project Manager to prepare the building application and to seek and obtain a Building Application Approval from Council. The Building Application should be provided to the Bank for its review and consent, prior to it being lodged with Council.""
153 Up until this point there had not been any provision in any draft of the Project Management Agreement about the obtaining of Building Consent.
154 The Memorandum of Comments was communicated to the defendant and the defendant replied in a letter of 13 October 1995. In this letter the defendant, adopting the same numbering system as Blake Dawson Waldron had in the Memorandum, said inter alia:-
""4. Agreed subject to the Bank's consent not being unreasonably withheld and a five working day turn around time so as not to delay the project.""
155 In the letter of 13 October 1995 the defendant said in reply to another comment made by Blake Dawson Waldron in their Memorandum of 13 October 1995:-
""The parties are agreeable to a right to terminate the Agreement to be available in the event that Development Approval is not obtained prior to 28 February 1996 or that Building Approval is not obtained prior to 30 April 1996.""
156 Blake Dawson Waldron responded to the defendant's reply in a letter of 17 October 1995. In this letter Blake Dawson Waldron said inter alia:-
""6.
…………
Development Approval and Building Approval must be obtained by 31 December 1995. The failure to obtain these approvals by that date must give the owner a right to terminate. The Bank will not agree to any extension beyond 31 December 1995.""
157 I accept that this passage in Blake Dawson Waldron's letter of 17 October 1995, although it related to a different clause in the Project Management Agreement, was the "genesis" of a requirement made by Blake Dawson Waldron in their later letter of 31 October 1995, with regard to the clause which became cl 5.4.
158 On 31 October 1995 Blake Dawson Waldron wrote a long letter to the defendant, enclosing copies of the draft Project Management Agreement and draft Tripartite Deed, incorporating amendments made in handwriting which were required by the Hong Kong Bank.
159 In their covering letter Blake Dawson Waldron said inter alia:-
"Project Management Agreement"
1. We have added reference to the Building Consent and Application in a number of the provisions of clause 6.
2. We note the provisions for a mortgage to be given to the Project Manager have been deleted. However, the priority provisions in the Tripartite Deed have been retained: see clause 4. Should the priority provisions be deleted? Will the Project Manager lodge a caveat? If so, the Bank will want to review the terms of the caveat prior to signing documents.
160 In the letter of 31 October 1995 Blake Dawson Waldron referred to other parts of the Project Management Agreement.
161 Clauses 6.1, 6.2,.6.3, 6.4 and 6.7 as they appeared in the latest draft prepared by the defendant and before the amendments made by Blake Dawson Waldron, were in the following terms:-
""6.1 The Project Manager will on behalf of the Owner but at the Project Manager's own expense:-
6.1.1 prepare the Development Application, draft Strata Plan and Building Application, and
6.1.2 submit the Development Application, draft Strata Plan and Building Application to the Council.
6.2 Forthwith upon receipt by the Project Manager of Development Consent or any written refusal from the Council in relation to the Development Application the Project Manager will submit a copy thereof to the Owner.
6.3 The Project Manager will use its best endeavours and do all things reasonably necessary to obtain Development Consent with due expedition and diligence.
6.4 In the event that Council refuses to grant Development Consent or has not granted Development Consent by 31st December 1995 either party may by notice in writing to the other terminate this Agreement and neither party shall have any right or action or claim for damages or specific performance against the other.
6.5 In the event of the Council granting the Development Consent but imposing additional conditions over and above the conditions contained in the current Development Consent which would (other than arising from the plans and specifications forming part of the Project Manager's Development Application and the application of the conditions of the Development Consent thereto);-
(a) entail the Project Manager having to expend more than $100,000 in meeting such additional requirements of Council (except in the event that the Owner elects within seven days of being notified in writing by the Project Manager of the amount in excess of $100,000 to allow the amount in excess of $100,000 as a deduction from the Settlement Sum by notice in writing to the Project Manager) ; or
(b) have the effect of reducing the sale prices which may be reasonably anticipated by the Project Manager for the lots by an aggregate of 10%
then for the purposes of this Agreement the Development Consent shall be deemed to be a refusal and either party may by notice in writing to the other rescind this Agreement PROVIDED THAT the owner shall not be entitled to rescind this Agreement pursuant to this clause in the event that the Project Manager elects to proceed with the Development Consent as approved and notifies the Owner in writing of such decision within the seven day period stipulated in sub-clause (a).
6.6 Prior to lodgement of the Building Application with Council the Project Manager shall submit a copy to the Mortgagee for its consent.
6.7 In the event that the Project Manager has not obtained the Development Consent approval by 29th February 1996 (and in this regard time shall be of the essence) the Owner shall have the right to terminate this Agreement without any claim against it by the Project Manager for any costs, charges or expenses incurred by the Project Manager whatsoever.""
162 The amendments made by Blake Dawson Waldron in handwriting, on the instructions of their client the Hong Kong Bank, consisted of adding the words "and Building Consent" after the words "Development Consent" in cl 6.2 and the words "or Building Application" after the words "Development Application" in cl 6.2; the words "and Building Consent" after the words "Development Consent" where they appear (twice) in cl 6.4; and the words "and Building Consent" after the words "Development Consent" in cl 6.7.
163 The making of these amendments by Blake Dawson Waldron was the first occasion that any suggestion had been made by anyone that clauses 6.4 and 6.7 of the Project Management Agreement should have included in them a reference to a need to obtain Building Consent by a particular date.
164 The defendant replied to Blake Dawson Waldron's letter of 31 October 1995 in a letter dated 2 November 1995. I accept a submission made by counsel for the defendant that I should find that this letter was written by the defendant after discussions between him, Robert Phillips, Robin Wise and George Newhouse and that the letter stated the common position of all of those persons. In this letter the defendant said in part:-
""Project Management Agreement
1. The reference to Building Consent etc in clauses 6.2 and 6.3 added by you is acceptable but not in 6.4. The "deal" has never been that the BA would have to be obtained within such a restricted time frame.
Paragraph 2 is acceptable. Please note, however, that in paragraph 6.4 the date is to now to become 28th February 1996.""
165 In the first paragraph the defendant, consistently with his objection to the inclusion of the reference to Building Consent in cl 6.4, should also have objected to the inclusion of the reference to Building Consent in cl 6.7.
166 A number of documents were admitted into evidence recording work done by solicitors in Blake Dawson Waldron and communications between Blake Dawson Waldron and the Hong Kong Bank, regarding the defendant's letter of 2 November 1995.
167 A diary note of a discussion between Mr Mason and Mr Stoupas of Blake Dawson Waldron on 7 November 1995 included the following:-
""Bank has given away the reqt the BC be obtained by any date at all. Have to rely on DA and BA being lodged by 31/12/95 and that Project Manager will use its "best endeavours" to obtain that consent.
→ difficult for HKBA to rely on - they could easily allege that plans/consents etc were held up by Council.
→ they might also have a problem with clause 6.7 which has 28/2/96 as being the date by which BC must be obtained in it. Haven't mentioned it in their fax. We presumed that they'll look after that.
→ DWM drafted a new clause 3.4 for the Tripartite Deed.""
168 It is clear the in this diary note "BC" is an abbreviation for Building Consent, "DA" is an abbreviation for Development Application and "BA" is an abbreviation for Building Application.
169 On 7 November 1995 Blake Dawson Waldron wrote a letter to the defendant, which included the following:-
""Project Management Agreement
1. First paragraph: Agreed, subject to the words "on or before 31 December 1995" being inserted into clause 6.1.2 after the word "Council.
Second paragraph: Noted and agreed.""
170 On 9 November 1995 the defendant wrote a letter to Blake Dawson Waldron, in which he referred to Blake Dawson Waldron's letter of 7 November 1995 and said:-
""Project Management Agreement
1. We agree to insertion of the 31st December 1995 as regards the development application (which has already been lodged with your client's consent) but not the building application and Strata Plan.""
171 There were further communications concerning whether a date should be fixed for the lodging of the building application.
172 A file note made by Mr Stoupas on 10 November 1995 recorded:-
""T/T Peter Varnay (240pm)
He's happy for the PM to lodge the BA & SP with Council asap but not more than six weeks after Council approves the DA.""
173 The file note recorded a conversation with Mr Peter Varnay of the Hong Kong Bank "asap" is an abbreviation for "as soon as possible".
174 On 10 November 1995 Blake Dawson Waldron wrote a letter to the defendant, in which they referred to the defendant's letter of 9 November 1995 and said:-
""Project Management Agreement
1. Agreed, subject the inclusion of an undertaking by the Project Manager to lodge the Building Application and Strata Plan with the Waverley City Council as soon as practicable, but not later than six weeks after the Council's approval of the Development Application.""
175 The defendant responded to the letter from Blake Dawson Waldron of 10 November 1995 in a letter dated the same day. In this letter the defendant said in part:-
""Project Management Agreement
1. Agreed except with regards to Strata Plan. The Strata Plan cannot be finalised until the building is almost completed as each lot must be physically measured by the surveyor before he is able to complete such details as the area of each unit and garage/car space etc. The Strata Plan must be in registrable form before it is lodged for approval with the Council.""
176 This letter was sent on the instructions of Robert Phillips and a copy of the letter was sent to Mr Newhouse.
177 It was submitted by counsel for the defendant that the position which had been reached by this stage on 10 November 1995 was that the Hong Kong Bank and its solicitors Blake Dawson Waldron, who were the only persons who had sought to have the words "and Building Consent" included in the clause which became cl 5.4 of the Project Management Agreement, had agreed that the words should not be included, that no date should be specified in the Project Management Agreement as being the date by which building consent should be obtained, that no date should be specified in the Project Management Agreement as being the date by which an application for building consent should be lodged with the Council and that the only requirement in the Agreement as to when an application for building consent should be lodged or Building Consent should be obtained would be in the clause which became cl 5.1.2 in the Project Management Agreement under which an application for building consent was to be lodged as soon as practicable and not later than six weeks after the Council had approved the development application.
178 However, further things happened after the defendant's letter of 10 November 1995.
179 On 10 November 1995 the conduct of the matter on behalf of the plaintiff was transferred by the defendant to his employee Margaret Rowley.
180 On 10 November 1995 Margaret Rowley sent a letter to Mr Newhouse, which read in part:-
""Herewith up to date amended documents with the latest amendments marked up.
Also herewith letter just received from Blake's. We will amend the Agreement as required in their item 1.""
181 It is clear that the letter which had just been received from Blake Dawson Waldron was the letter of 10 November 1995 from Blake Dawson Waldron. The draft Project Management Agreement enclosed with the letter of 10 November 1995 which Ms Rowley sent to Mr Newhouse included the words "and Building Consent" in cl 5.4.
182 Also on 10 November 1995 Margaret Rowley sent a letter to Blake Dawson Waldron, which said in part:-
""Please find enclosed Project Management Agreement and Tripartite Deed, amended as agreed, and marked up for your assistance.
Would you please let us know if these documents are now in form satisfactory to the Bank so that we may engross them and have them executed.""
183 The draft Project Management Agreement enclosed, which Margaret Rowley said in her letter had been amended as agreed, included the words "and Building Consent" in cl 5.4.
184 On 13 November 1995 Blake Dawson Waldron wrote a letter to the defendant in which they said in part:-
""We refer to your facsimile dated 10 November 1995 and attached marked up pages of the Project Management Agreement and the Tripartite Deed showing our further amendments to those documents.
Subject to the amendments shown in the attached pages being made and the inclusion of minimum prices for the sale of lots in the Third Schedule, the Project Management Agreement is in a form acceptable to the Bank. Please provide us with a final draft of the Project Management Agreement once these amendments have been made.""
185 Only certain pages of the draft Project Management Agreement were enclosed with Blake Dawson Waldron's letter of 13 November 1995. One page which was enclosed included part, but not all, of cl 5.4, including the words "and Building Consent" after the words "Development Consent". The same page included cl 5.1.2, which, as it stood in the typed draft, required the Project Manager to submit the Development Application, the draft Strata Plan and the Building Application to the Council. A further amendment required by Blake Dawson Waldron was handwritten and consisted of adding to cl 5.1.2 the words "which Building Application must be lodged with the Council as soon as practicable but not later than six weeks after Council's approval of the Development Application".
186 On 14 November 1995 Margaret Rowley sent a letter to Robert Phillips in which she said in part:-
""Enclosed please find fax which appears to have come from Blake's yesterday afternoon but which, unfortunately, had been put to the side of the fax and buried under some other papers.
Some amendments are just typos, others, I believe, are as agreed and not picked up by me.""
187 With this letter of 14 November 1995 were enclosed a copy of Blake Dawson Waldron's letter of 13 November 1995 and its enclosures.
188 On 14 November 1995 Margaret Rowley wrote to Blake Dawson Waldron saying that the documents (which included the Project Management Agreement) would be amended in accordance with Blake Dawson Waldron's recommendations, that is in accordance with the requirements made by Blake Dawson Waldron in their letter of 13 November 1995.
189 On 15 November 1995 the plaintiff executed the Project Management Agreement. Clause 5.4 of the Agreement as executed included the words "and Building Consent" in cl 5.4. The Project Management Agreement was executed in escrow and was delivered and exchanged on 18 December 1995.
190 Counsel for the defendant submitted that the words "and Building Consent" should not have been included in the drafts forwarded between 10 November and 14 November 1995 and should not have been included in the document which was executed by the plaintiff on 15 November 1995. Counsel submitted that the words "and Building Consent" had been included in cl 5.4 in those drafts and in the document which was executed, by mistake. It was submitted that the mistake had occurred, because the conduct of the matter on behalf of the plaintiff had been transferred by the defendant to his employee Margaret Rowley, who had not participated in the negotiating of the terms of the Agreement, and Margaret Rowley, either negligently or because of a failure in communication between the defendant and her, had sent out drafts of the Project Management Agreement, which were based on the amended drafts enclosed with Blake Dawson Waldron's letter of 31 October 1995 and which did not take into account the events which had occurred between 2 November and 10 November and, in particular, the consensus which had been reached by 10 November 1995 that the words should not be included in cl 5.4.
191 Counsel for the defendant submitted that, after Blake Dawson Waldron had abandoned its requirement that the words "and Building Consent" be included in cl 5.4, there could be no reason why the plaintiff or its solicitors, acting rationally, would have intentionally reintroduced such a requirement. A requirement that building consent be obtained at the same time as Development Consent made no sense, as the Hong Kong Bank and its solicitors had eventually conceded. Particularly in a project of this size, an application for building consent would not be lodged until after development consent had been granted, so that the application for building consent could take into account the conditions subject to which development consent had been granted. At the time the Project Management Agreement was entered into it was known by the parties to the Agreement that development consent could not be granted before the meeting of the Council to be held near the end of February 1996.
192 On 13 November 1995 Blake Dawson Waldron had required as an addition to cl 5.1.2 that the application for building Consent be lodged with the Council as soon as practicable but not later than six weeks after Council's approval of the development application. Such a requirement would be quite inconsistent with a right being conferred on each party to terminate the Project Management Agreement, if building consent was not granted by 28 February 1996.
193 Counsel for the plaintiff submitted that I should find that the words "and Building Consent" had been deliberately included in the drafts of the Project Management Agreement sent on 10 November 1995 to Blake Dawson Waldron and to Mr Newhouse as solicitor for the other party to the Agreement. Counsel pointed out that the words "and Building Consent" were underlined in these drafts.
194 It was suggested by counsel for the plaintiff that the words "and Building Consent" had been included in the drafts, because the defendant had become frustrated with his own lack of progress in his negotiations with the Bank's solicitors and had decided to shift the burden of dealing with the Bank and its solicitors to Robin Wise and his solicitor.
195 Counsel for the plaintiff referred to part of the defendant's affidavit of 13 August 2003 (par 49) in which the defendant had said that the words "and Building Consent" had been "left in" the newly marked up versions of the Project Management Agreement prepared on 10 November 1995. It was submitted by counsel for the plaintiff that the words had not been "left in"; they had not been included in the draft of 22 October or 25 October 1995 on which Blake Dawson Waldron had made their handwritten amendments.
196 It was submitted by counsel for the plaintiff that it was unlikely that the words "and Building Consent" had been included by mistake. The words could have been included by mistake, only if all, or at least most, of the defendant, his employee Margaret Rowley, the solicitors at Blake Dawson Waldron handling the matter for the Bank and Mr Newhouse had failed to notice the alleged mistake. Of these persons the defendant himself had given evidence at the trial but he had not called as witnesses Margaret Rowley, any solicitor from Blake Dawson Waldron or any representative of the Hong Kong Bank and it should be inferred that, if any of these persons had been called to give evidence, their evidence would not have assisted the defendant.
197 It was submitted by counsel for the plaintiff that the subsequent conduct of the defendant and of Robin Wise was inconsistent with either of them believing that the inclusion of the words "and Building Consent" in cl 5.4 was due to a mistake. The defendant had asserted that there was a right under cl 5.4 to terminate the Project Management Agreement, if Building Consent was not obtained by 28 February 1996, in the letter of 10 April 1996 to Mrs Phillips, his conversation with Mrs Phillips about his "great" or "brilliant" idea, his letter of advice to Mrs Phillips of 22 April 1996, the 21 day notice given to Ocean View on 22 April 1996 and his written instructions to Mr Hilton of 1 May 1996. As far as Ocean View and Robin Wise were concerned, after the notice of 22 April 1996 had been served, Ocean View had not contested the validity of the notice on the grounds that it was not a term of the true agreement between the parties that Building Consent should be obtained by 28 February 1996; and after the defendant's letter of 8 May 1996 had been received by Ocean View, Ocean View did not in its detailed response of 16 May 1996 take any point that it was not a term of the Project Management Agreement that building consent be obtained by 28 February 1996.
198 Counsel for the plaintiff relied on some passages in the evidence of Robert Phillips. Robert Phillips had not made an affidavit for either party. He was spoken to by the solicitors for the defendant. However, he declined to make an affidavit. He was understandably reluctant to appear to be giving evidence against his mother. The defendant's solicitors prepared two short statements in indirect speech of the evidence it was anticipated he would give, if he was called. At a late stage in the trial he was called as a witness by counsel for the defendant and he was then orally examined in chief by counsel for the defendant and cross-examined by counsel for the plaintiff.
199 Passages in Robert Phillips' evidence referred to in argument were:-
- Evidence at transcript 1023 (lines 33-42)