(i) The contract between the respondent and the first
appellant
His Honour, preferring the respondent's version,
found that the second appellant told the respondent
"at some early stage that the house could and would
be built, under his supervision, for $80,000 or
thereabouts."
His Honour added:
"The evidence established that on or around 26 May
1983 the (respondent) had entered an agreement
with the first (appellant) pursuant to which the
first (appellant) would provide designs and plans
of the (respondent's) residence which involved the
first three stages of the Agreement...
Thereupon the first (appellant), through the
second (appellant) contracted to do the following:
(a) prepare plans for the project;
(b) provide an estimate of the cost of the
project which had to accommodate the
(respondent's) budget (the estimate
eventually provided and accepted was
$80,000);
(c) prepare all documents sufficient to permit
the letting of contracts including providing
information to engineering and other
consultants or contractors, and the
co-ordination and integration of building
works on the design;
(d) advise the (respondent) regarding tenders
received and administer and supervise the
building work.
In return the (respondent) undertook to pay the
first (appellant's) fees and paid them in part.
In view of my later findings, there is no need for
me to determine what the agreed fees were. The
contract seems to have been terminated by
agreement at or about the time the second
(appellant) left the employ of the first
(appellant)."
(ii) The contract between the respondent and the second
appellant
The judge found that after the second appellant left
the employ of the first appellant in December 1983,
he entered into an agreement with the respondent in
April 1984 whereby he agreed to assume responsibility
for the earlier contract with the first appellant,
provide the respondent with appropriate advice from
time to time, and supervise the work; that he was
paid $3,000; and that by November 1984 the second
appellant had abandoned the work; the respondent
then accepted the termination of the Agreement.
(iii) The claims made against the first appellant
The respondent's case was that the appellants were
qualified architects and were therefore competent to
give advice as to costs; the appellants professed to
have skill and expertise in regard to the letting and
supervision of building contracts; the appellants
knew that the respondent had accepted their advice as
to the cost of $80,000 on the basis that the
respondent became an "owner/builder" and retained the
first appellant to supervise and administer contract
works and construction; and that the second
appellant knew the respondent was acting on that
advice in embarking on the project.
(iv) The claims against the second appellant
It was said that the second appellant aided and
abetted the first appellant in its alleged
contraventions of the Trade Practices Act and was
knowingly concerned in the contravention; and that
the second appellant gave negligent advice.
(v) Discussion of the principles
The judge referred to the authorities in the areas of
(i) negligent misstatement and (ii) the duty owed by
an architect. His Honour said:
"There is no doubt that when an architect gives an
estimate, it must not only be an honest and
carefully considered estimate but it must also be
given after due consideration of the facts
involved in the particular case."
(vi) Reference to the "Practice Notes"
The judge then said:
"The Royal Australian Institute of Architects
apparently prepares what are called 'Practice
Notes' to be used by architects as general
guidelines in the course of their work, even
though there is no rule binding on architects that
they must be observed. In particular, parts of
Practice Note 3 provide a general guide on the
question of estimates:
2. The Architect's responsibility in the matter
of estimates must be clearly understood by
all concerned with the direction of a job.
When a budget limit is stated by a client,
the architect is obliged to design within
this limit. If the lowest tender is
seriously in excess of the budget, and for
this reason the project is abandoned, it is
likely that the architect will be unable to
recover fees. Even if this does not happen,
the architect may be involved in
considerable expense in amending documents
to meet the budget limitation.
3.(a) The RAIA Conditions of Engagement provide as
part of the architect's basic service the
provision of estimates of cost at schematic
design stage, design development stage and
contract document stage.
The degree of accuracy required, and
therefore the type of estimate (i.e. square
or cubic basis, approximate quantities,
etc.) should be decided in accordance with
the circumstances of the case and the nature
of the project and agreed with the client.
It also provides a 10% margin for estimates as
reasonable. Furthermore the Agreement provides
under the heading 'Architect's Responsibility and
Authority':
B1.01 The architect shall perform the services
referred to in this agreement. In the
performance of those services the architect
shall exercise reasonable skill and care in
conformity with the normal standards of the
practice of the architecture.
It thus seems clear that an architect is under a
duty to take reasonable care to ensure that any
estimate of the cost of a building being designed
is reasonably accurate. The architect is also
bound to take into account any increases in costs
which the time taken in the construction might
involve. The evidence in this case establishes
for me that the estimate of $80,000 was wildly
inaccurate and that the house at no stage had a
chance of being constructed to any reasonable
state of occupation for any price even close to
$80,000."
The appellants submit, for reasons to be given later,
that it was not open to his Honour to have regard to
the "Practice Notes".
(vii) Conclusions on liability
The judge said:
"I find that the completed project on the plans
prepared was said by the first (appellant),
through the second (appellant), to cost of the
order of $80,000, excluding architects' and
engineer's fees, and prime cost, furniture or
furnishing items, on the basis that the
(respondent) was licensed as an owner/builder and
the second (appellant) supervised the
construction. This was misleading and deceptive
conduct and a false representation within the
meaning of sections 52 and 53 of the Act. I find
that the (respondent) was induced by the first
(appellant), through the second (appellant), to
proceed with the plans because the (appellants)
said the construction would cost $80,000. The
advice that it could and would be built for that
price was negligent. The failure to design the
house to that cost was a breach of contract. The
second (appellant) aided and abetted the first
(appellant) and was knowingly concerned in its
breaches of the Act. He was in breach of his
contract to continue with and supervise the
construction of a house which would cost $80,000
and negligently advised the (respondent) that it
could and would be constructed for that price.
Both (appellants) are liable to pay damages to the
(respondent)."
(viii) Damages
After returning to the authorities, his Honour
concluded that the measure of damages for negligent
misstatement is the same as under s.82(1) of the
Trade Practices Act, "i.e. the court is to put the
person injured in the same position as would have
existed if the person had not sustained the wrong for
which compensation is now being awarded."
(vii) Quantum of damages
The judge said:
"In a case marked by much vagueness, inconsistency
and generality across the spectrum of issues, the
quantification of damages wins the first prize.
As I see it, the (respondent's) claim for damages
can essentially be divided into two main
categories:
1. Construction costs - occasioned by additional
construction costs in excess of the original
estimate of $80,000
2. Additional financing costs - occasioned by the
additional loans incurred by the (respondent)
to fund the project
....
The (respondent) submitted a schedule of damages
but did not identify the evidence said to support
the assertions contained in it...The matters
requiring attention include:
1. Completion costs - alleged to be of the order
of $50,000
2. Interest on borrowed funds to date - alleged
to be of the order of $50,000 (but which seem
to me to be closer to $40,000)
3. Future interest - estimated to be $24,000 (but
which I do not understand)
4. The exclusion of architect's fees - said to
have been paid in the sum of $6,000 (which
seems to be factually correct, but which I
have found not to be comprised within the
$80,000 estimated cost)
5. The exclusion of engineer's fees (as far as I
can see there has been no evidence or estimate
provided but I have likewise found these to
have been excluded from the $80,000 cost)
6. The quantum and relevance to damages of any
overcapitalisation of the site
7. The interrelationship between the $80,000
estimated cost and the debt to State Bank -
i.e. how much of the debt was brought about by
the (appellants') conduct?
8. The costs of the borrowings from the Bank
relevant to this matter
9. The quantum if any of inflation on the costs
of completion
10. The claim for interest on any award of damages
11. Any question concerning apportionment between
the (appellants).
Except for item 11 (and possibly 7) of this list,
it seems to me that these are all very much
matters for calculation of what flows from the
finding that the (appellants) are liable to pay
damages to the (respondent)."
The judge then directed, in accordance with O.38 r.
1, that the amount which the appellant should be
ordered to pay be ascertained by a Registrar.