[78] Numerous authorities have accepted the third proposition. Many were referred to in Reed at 165. Others include Fletcher Construction at 826-7; Bachmann Pty Ltd v BHP Power New Zealand Ltd [1999] 1 VR 420; [1998] VSCA 40 at [28] ( Bachmann ); Baulderstone Hornibrook Pty Ltd v Qantas Airways Ltd [2000] FCA 672 at [10]; Rejan Constructions Pty Ltd v Manningham Medical Centre Pty Ltd [2002] VSC 579 at [37]."
16 If an application to restrain a beneficiary of promises under a bank guarantee from making a demand or drawing upon the guarantee falls within one of the exceptions that is outlined, then the principle that a restraint on draw downs should not be granted is avoided and the application for interlocutory relief is dealt with in accordance with the ordinary principles relating to the grant of interlocutory injunctions as enunciated in Kolback Securities Ltd v Epoch Mining NL (1987) 8 NSWLR 533 at 535 - 536.
17 The plaintiffs' contention is that cl 2.6(b) of the PDD is an express negative stipulation, breach of which will be restrained. They say that it is breached because, if the contract has been frustrated or otherwise brought to an end, nothing is owing under it, so that a demand made for payment will be for more than the money in arrears under the PDD.
18 In my view this submission is correct. If the contract be non existent, then the demands are for more than the sum stipulated in cl 2.6(b). That this is correct is illustrated by the actual decision of Austin J in Reed Constructions. There was not an express negative stipulation but, because the subjacent contract provided that the security should be available to the beneficiary only in specified circumstances, it was held there should be taken to be an implied prohibition on the beneficiary calling up the security except where there was authorisation for it to do so in the relevant provision of the deed. In this case, there is an express negative stipulation.
19 I turn then to consider the application that is made on the ordinary principles applying to interlocutory injunction applications. I have already said that, despite the fact that the first defendant's submissions to the contrary have substance, it is my view that there is a serious question to be tried as to whether the contract has been brought to an end on the basis of the doctrine of frustration. I have already also said that the question of the adequacy of damages as a remedy is in the forefront of the argument in this case.
20 On the first defendant's evidence, the first defendant is at present carrying out its activities at an operating loss. It is anxious to obtain the $9,000,000 demanded to help pay for those operations. It does seem, upon the evidence, that the $9,000,000 is likely to be absorbed in those operations or in some extension of them that the first defendant is anxious to carry out, so that the $9,000,000 will not remain available as a liquid sum to be repaid if the plaintiff's case succeeds at trial.
21 The first defendant says, however, that it has unencumbered land worth something in the vicinity of $90,000,000 and that, furthermore, the proposed subdivision having been effected, that land could, if called upon, be sold not only en globo but in the subdivided lots. The difficulty is that, valuable although this land is, it is not at all clear, on the evidence, as to whether any ready market exists for it either en globo or in relation to individual lots. The contract that the first defendant entered into for its sale and development by the plaintiffs was the complex transaction embodied in the PDD. Whether there are organisations other than that of which the plaintiffs form part ready and waiting to enter into some agreement concerning this land, or other developers interested in obtaining parts of it, is simply not shown on the evidence. I cannot form the view that the $9,000,000, if required to be repaid, would be able to be raised by the first defendant readily or in any particular time line. In those circumstances, it seems to me that damages cannot be said to be an adequate remedy in the circumstances, since it is entirely unclear how and when the damages, if assessed, would be paid.
22 A number of other matters have been agitated going to the balance of convenience. It has been said that the first defendant is carrying on operations that are worthwhile and important to the public and that the advantage to those operations and the possibility of their immediate expansion if the $9,000,000 were made available should be weighed in the first defendant's favour in assessing the balance of convenience.
23 On the other hand, although the first defendant's operations have been conducted at a loss, there is no suggestion that operations on the present scale could not continue to be carried on during the comparatively short time that it will take to resolve this matter, bearing in mind the availability of expedited hearings in this Division of the Court. The proceedings can and will be sent immediately to the Expedition List, whether or not interlocutory relief is granted, and should be able to be disposed of in a comparatively small number of months, rather than any longer period of time. Equally, whilst the availability of this money may enable the first defendant to proceed earlier with its plans of expansion, it cannot be said that there is any pressing reason for that to be done in the comparatively short time frame we are talking about.
24 It is true that the plaintiffs are not carrying out any present development activity. However, no doubt it is likely that the $9,000,000 will be used for some development activity if the present project is aborted. It would be a grave inconvenience to the plaintiffs, the $9,000,000 having been paid out by Investec, if they could not recover for a protracted period the $9,000,000 that they have deposited with Investec as the counter security for the grant of the bank guarantees.
25 In all the circumstances, I have concluded not only that damages are not to be regarded as an adequate remedy but that the balance of convenience favours the grant of the injunctive relief sought. I have come to this conclusion despite the arguments that have been put to me on behalf of the first defendant by Mr Whitford in his usual incisive manner.
26 In coming to the conclusion that I have, I have not yet considered one matter that could preclude the grant of relief and that is the adequacy of the undertaking as to damages proposed to be granted in support of the relief and, during the course of argument, I drew to the plaintiffs' attention the necessity for the plaintiffs to consider whether, and in what way, they are prepared to supplement or secure the undertaking in its usual form. I shall deal on 10 December 2008 with the question of the adequacy undertaking as to damages.
27 I order:
(1) Upon the plaintiffs by their counsel renewing the existing undertakings the existing interlocutory relief is extended up to and including 10 December 2008.
(2) Direct that material be served by the opposing parties and delivered to my Associate as follows:
(a) by the plaintiffs a firm proposal for ongoing undertakings as to damages and any evidence in support by close of business on 8 December 2008; and
(b) by the defendants any material to be relied on by close of business on 9 December 2008.
(3) Proceedings adjourned to 10 December at 10am before the Duty Judge.
(4) Proceedings placed in Expedition List on 12 December 2008.
(5) Direct that the proceedings continue on pleadings and that the plaintiffs file a further amended statement of claim on or before 12 December 2008.