Pullen v Smedley
[2017] NSWSC 1721
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2017-07-27
Before
Ward CJ
Source
Original judgment source is linked above.
Judgment (68 paragraphs)
(8) Declare that the damage caused by the plaintiffs/cross-defendants to several large boulders on and in the vicinity of the respective rights of way in the course of road works carried out by them in or about August- September 2015 constitutes a trespass to land, by reason of it not being carried out with the consent of the defendants/cross-claimants and not within the rights conferred on the plaintiffs/cross-defendants pursuant to either of the respective rights of way. (9) Order that the damaged boulders each be replaced by the plaintiffs/cross-defendants at their cost with boulders of comparable size and appearance brought from off the plaintiffs/cross-claimants' property. (10) Reserve question of damages for trespass pending compliance with orders 6, 7 (if applicable) and 9 above. (11) Otherwise dismiss the plaintiffs' claims in the proceedings. (12) Reserve the question of costs. (13) Direct that written submissions as to costs be served within 7 days with the intent that costs will be determined on the papers. (14) Liberty to the parties to apply on 3 business days' notice for any amendment or variation of these orders and for directions in relation to the assessment of damages. In the transferred proceeding (2016/00366908) (1) Declare that the respondents have carried out work (Work) on land being Lot 20 DP 1163017 and Lot 21 DP 1163020 (the Land) being development for the purposes of a private road, or alternatively for the purposes of a dwelling house, by constructing a road surface using imported fill being the access road to their dwelling house on adjoining land within their rights of way over the Land but without development consent, when development consent was required for the carrying out of work for either purpose within the E3 Environmental Management zone applying to the land under the Wyong Local Environmental Plan 2013, contrary to 76A Environmental Planning and Assessment Act 1979 (NSW). (2) Further declare that the respondents by carrying out the Work have carried out prohibited development on the Land being development for the purposes of a waste facility, which is an innominate prohibited use under the Wyong Local Environmental Plan 2013, contrary to 76A Environmental Planning and Assessment Act 1979 (NSW). (3) Declare that the respondents have used the Land as a "waste facility" contrary to s 144 of the Protection of the Environment Operations Act 1997 (NSW) by placing, depositing and spreading on the Land material within the definition of "waste" in that Act being imported fill being building waste and crushed concrete waste derived from concrete, brick, tile and pipe and trace pieces of steel, alloy and timber (the Road Material). (4) Note and confirm the orders made in the associated (easement) proceeding (2016/00140145) in relation to the notification to the local council and Environment Protection Authority (EPA) as to the discovery of asbestos and for compliance with any direction by the EPA as to the containment or removal or part or all of the Road Material. (5) Reserve the question of costs. (6) Direct that written submissions as to costs be served within 7 days with the intent that costs will be determined on the papers. (7) Liberty to the parties to apply on 3 business days' notice for any amendment or variation of these orders and for directions in relation to any further relief to be granted following compliance with the orders made in the associated (easement) proceeding. Catchwords: REAL PROPERTY - Easements - Rights of way - Construction - Whether easement implicitly precludes grazing of cattle by servient tenement owner - Meaning of "all weather" access standard - Whether dominant tenement owner liable to contribute financially to the cost of certain works