© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2017] NSWSC 1721
Supreme Court of NSW
2017-07-27
Ward CJ
Original judgment source is linked above.
(8) Declare that the damage caused by the plaintiffs/cross-defendants to several large boulders on and in the vicinity of the respective rights of way in the course of road works carried out by them in or about August- September 2015 constitutes a trespass to land, by reason of it not being carried out with the consent of the defendants/cross-claimants and not within the rights conferred on the plaintiffs/cross-defendants pursuant to either of the respective rights of way. (9) Order that the damaged boulders each be replaced by the plaintiffs/cross-defendants at their cost with boulders of comparable size and appearance brought from off the plaintiffs/cross-claimants' property. (10) Reserve question of damages for trespass pending compliance with orders 6, 7 (if applicable) and 9 above. (11) Otherwise dismiss the plaintiffs' claims in the proceedings. (12) Reserve the question of costs. (13) Direct that written submissions as to costs be served within 7 days with the intent that costs will be determined on the papers. (14) Liberty to the parties to apply on 3 business days' notice for any amendment or variation of these orders and for directions in relation to the assessment of damages. In the transferred proceeding (2016/00366908) (1) Declare that the respondents have carried out work (Work) on land being Lot 20 DP 1163017 and Lot 21 DP 1163020 (the Land) being development for the purposes of a private road, or alternatively for the purposes of a dwelling house, by constructing a road surface using imported fill being the access road to their dwelling house on adjoining land within their rights of way over the Land but without development consent, when development consent was required for the carrying out of work for either purpose within the E3 Environmental Management zone applying to the land under the Wyong Local Environmental Plan 2013, contrary to 76A Environmental Planning and Assessment Act 1979 (NSW). (2) Further declare that the respondents by carrying out the Work have carried out prohibited development on the Land being development for the purposes of a waste facility, which is an innominate prohibited use under the Wyong Local Environmental Plan 2013, contrary to 76A Environmental Planning and Assessment Act 1979 (NSW). (3) Declare that the respondents have used the Land as a "waste facility" contrary to s 144 of the Protection of the Environment Operations Act 1997 (NSW) by placing, depositing and spreading on the Land material within the definition of "waste" in that Act being imported fill being building waste and crushed concrete waste derived from concrete, brick, tile and pipe and trace pieces of steel, alloy and timber (the Road Material). (4) Note and confirm the orders made in the associated (easement) proceeding (2016/00140145) in relation to the notification to the local council and Environment Protection Authority (EPA) as to the discovery of asbestos and for compliance with any direction by the EPA as to the containment or removal or part or all of the Road Material. (5) Reserve the question of costs. (6) Direct that written submissions as to costs be served within 7 days with the intent that costs will be determined on the papers. (7) Liberty to the parties to apply on 3 business days' notice for any amendment or variation of these orders and for directions in relation to any further relief to be granted following compliance with the orders made in the associated (easement) proceeding. Catchwords: REAL PROPERTY - Easements - Rights of way - Construction - Whether easement implicitly precludes grazing of cattle by servient tenement owner - Meaning of "all weather" access standard - Whether dominant tenement owner liable to contribute financially to the cost of certain works
REAL PROPERTY - Easements - Rights of way - Whether installation and closing of gates along right of way, permitting cattle to graze on right of way, and/or the presence of a metal shipping container on the right of way amounts to substantial interference with rights of the owner of the dominant tenement - Whether opening of gates along right of way amounts to unreasonable use by the dominant tenement owner of rights conferred on it under easement
ENVIRONMENT AND PLANNING - Development consent - Whether carrying out of works on right of way unlawful for failure to comply with Wyong Local Environmental Plan 2013 and s 76A of the Environmental Planning and Assessment Act 1979 (NSW)
ENVIRONMENT AND PLANNING - Pollution - Land pollution and waste - Special waste - Whether carrying out of works on right of way amounted to the use of land as a "waste facility" contrary to s 144 of the Protection of the Environment Operations Act 1997 (NSW) Legislation Cited: Contaminated Land Management Act 1997 (NSW), s 60 Environmental Planning and Assessment Act 1979 (NSW), ss 76A, 76B Environmental Planning and Assessment Regulation 2000 (NSW), Sch 1 Fences Act 1968 (Vic), s 4 Protection of the Environment Operations Act 1997 (NSW), s 48, 144, Sch 1, cl 39, 49, 50 Protection of the Environment Operations (Waste) Regulation 2014 (NSW), cll 6.1, 91, 92, 93 Wyong Environmental Plan 2013 (NSW) Cases Cited: Australia Capital Financial Management Pty Ltd v Linfield Developments Pty Ltd; Guan v Linfield Developments Pty Ltd [2017] NSWCA 99 Baypeak Pty Ltd v Lim [2005] VSC 77 Black v Garnock (2007) 230 CLR 438; [2007] HCA 31 Blacktown City Council v Hocking [2008] NSWCA 144 Breskvar v Wall (1971) 126 CLR 376 Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337; [1982] HCA 24 David Peter Buckley v David Francis Timbury [2013] NSWSC 1009 Denton v Phillpot (1990) NSW ConvR 55-543 Department of Planning and Infrastructure v Glass Recovery Services Pty Limited [2015] NSWLEC 49 Director-General, Department of Planning and Infrastructure v Glass Recovery Services Pty Limited [2015] NSWLEC 49 Environmental Protection Authority v Hardt [2006] NSWLEC 438; (2006) 148 LGERA 61 Environmental Protection Authority v Terrace Earthmoving Pty Ltd (No 3) [2016] NSWLEC 50 Farah Constructions Pty Ltd v Say-Dee Pty Ltd (2007) 230 CLR 89; [2007] HCA 22 Foxman Environmental Development Services [2015] NSWLEC 105 Gohl v Hender [1930] SASR 158 Halloran v Minister Administering National Parks and Wildlife Act 1974 (2006) 229 CLR 545; [2006] HCA 3 Hender v Gohl [1928] SASR 325 Kent v Wotton & Byrne Pty Ltd [2006] TASSC 8 Kettleton v Murray [2017] QDC 64 Kirkjian v Towers (Supreme Court (NSW), Waddell CJ in Eq, 6 July 1987, Unrep) Mouawad v The Hills Shire Council [2013] NSWLEC 165 Owners Corporation of Strata Plan 42472 v Menala Pty Ltd (1998) 9 BPR 16,337 Pettey v Parsons [1914] 2 Ch 653 Powell v Langdon (1944) 45 SR (NSW) 136 Sertari Pty Ltd v Nirimba Developments Pty Ltd [2007] NSWCA 324 Shannongrove Pty Ltd v Environment Protection Authority (2013) 84 NSWLR 688; [2013] NSWCCA 179 Short v Barrett (NSW Court of Appeal, 5 October 1990, unrep) Sinclair v Jutt (1996) 9 BPR 16,219 Stewart v Cooper [1986] TASSC 3; [1986] ANZ ConvR 631 Trewin v Felton [2007] NSWSC 851 Warringah Shire Council v Sedevcic (1987) 10 NSWLR 335; (1987) 63 LGRA 361 Westfield Management Limited v Perpetual Trustee Company Ltd (2007) 233 CLR 528; [2007] HCA 45 Texts Cited: J Gaunt, Gale on Easements (20th ed, 2016, Sweet & Maxwell) P Jackson, The Law of Easements and Profits (Butterworths, 1978) S Odgers, Uniform Evidence Law (12th ed, LawBook Co) Category: Principal judgment Parties: Robert James Pullen (Plaintiff) Alan Robert Gilbert Smedley (Defendant) Representation: Counsel: J Van Aalst (Plaintiff) C Ireland (Defendant)
Solicitors: Szabo Solicitors (Plaintiff) Coleman Greig (Defendant) File Number(s): 2016/00140145; 2016/366908 Publication restriction: Nil
INDEX Introduction [1] Summary [5] Background [18] The respective properties [18] Smedley property [19] Pullen property [29] Gates along rights of way [32] Fencing along the rights of way [42] Condition of the rights of way prior to the Pullens' road works [47] Acquisition by the Pullens of their land and subsequent development applications [56] Communications as to the construction works on the Pullens' property and road works on Right of Way "B" [58] Dispute as to the gates on the right of way being left open and as to damage to boulders [79] Further complaints as to damage to the works on the right of way, including damage to boulders [86] Issues raised by Masterton [89] Escalation of the disputes [92] Commencement of proceedings [97] Incident in relation to the gate in August 2016 [101] Request made of Mr Fernance that cattle not be agisted on right of way [104] Commencement of proceedings in the Land and Environment Court [109] Inspection of access road by building certifier [110] Nub of the present disputes [117] Relief claimed in the various pleadings [125] Issues [129] The rights of way [130] Location of respective rights of way [131] Terms of the Right of Way [132] Lay Evidence [134] Expert Evidence [149] Mr de Silva's report of November 2016 [152] Dr Martens' report of August 2016 [155] The Joint Statement of Contamination Experts - February 2017 [161] Submissions on expert evidence [168] Conclusion [170] Issues [172] 1. Proper construction of the easements [172] Legal Principles [172] (i) "Right" to graze cattle on the right of way [177] (ii) What is meant by "all weather" access standard? [184] 2. Has there been a substantial interference by the Smedleys with the Pullens' reasonable use of Right of Way "B"? [190] (i) Requirement that gates on the right of way be kept closed [190] Determination [207] (ii) allowing cattle to graze on the right of way [230] (iii) Presence of the metal shipping containers [234] Determination [240] 3. Does the conduct of the Pullens in leaving gates open on the right of way amount to unreasonable use of the right of way? [243] 4. Declaratory relief sought as to fencing on western side of right of way [259] 5. The Pullens' road works [262] (i) Are the Smedleys are liable to contribute to the works carried out on Right of Way "B" pursuant to the terms of the easement? [263] Was the existing right of way prior to the road works trafficable to an "all weather" access standard? [270] Were the works properly done with as little inconvenience and causing as little damage as possible to Lot 21? [279] Determination [298] (iii) were the road works unlawful? [300] Conclusion that asbestos was part of the road fill material [300] Significance of the finding of asbestos [312] Requirement for development consent under the EPA Act [332] Implications of the finding that the road fill was waste [339] Summary of above conclusions regarding road works [361] (ii) Are the Pullens liable for damages for trespass and/or for damage to boulders on the Smedley property? [362] 6. Relief [366] Final Observations [385] Orders [393]
Judgment
Summary
The respective properties
Smedley property
Pullen property
Gates along rights of way
Fencing along the rights of way
Condition of the rights of way prior to the Pullens' road works
Acquisition by the Pullens of their land and subsequent development applications
Communications as to the construction works on the Pullens' property and road works on Right of Way "B"
Dispute as to the gates on the right of way being left open and as to damage to boulders
Further complaints as to damage to the works on the right of way, including damage to boulders
Issues raised by Masterton
Escalation of the disputes
Commencement of proceedings
Incident in relation to the gate in August 2016
Request made of Mr Fernance that cattle not be agisted on right of way
Commencement of proceedings in the Land and Environment Court
Inspection of access road by building certifier
Nub of the present disputes
Relief claimed in the various pleadings
Issues
The Rights of Way
Location of respective rights of way
Terms of the Right of Way
Lay evidence
Expert evidence
Mr de Silva's report of November 2016
Dr Martens' report of August 2016
The Joint Statement of Contamination Experts - February 2017
Submissions on expert evidence
Conclusion
Legal Principles
(i) "Right" to graze cattle on the right of way
(ii) What is meant by "all weather" access standard?
(i) Requirement that gates on the right of way be kept closed
Determination
(ii) allowing cattle to graze on the right of way
(iii) Presence of the metal shipping containers
Determination
(i) are the Smedleys liable to contribute to the works carried out on Right of Way "B" pursuant to the terms of the easement?
(ii) are the Pullens liable for damages for trespass and/or for damage to boulders on the Smedley property?
(iii) were the road works unlawful?
(i) Are the Smedleys are liable to contribute to the works carried out on Right of Way "B" pursuant to the terms of the easement?
Was the existing right of way prior to the road works trafficable to an "all weather" access standard?
Were the works properly done with as little inconvenience and causing as little damage as possible to Lot 21?
Determination
Conclusion that asbestos was part of the road fill material
Significance of the finding of asbestos
Requirement for development consent under the EPA Act
Implications of the finding that the road fill was waste
Summary of above conclusions regarding road works
(ii) Are the Pullens liable for damages for trespass and/or for damage to boulders on the Smedley property?
Final observations
Orders
In the easement proceeding (2016/00140145) 1. Order the defendants to remove the Metal Shipping Containers off the right of way referred to in these reasons as Right of Way "B" (being the right of way on Lot 21 DP 1163020 (Lot 21) indicated on that deposited plan and created by the s 88B instrument registered on 5 April 2011 (Right of Way "B"). 2. Declare that the conduct of the plaintiffs/cross-defendants in leaving open any of the three farm gates erected across Right of Way "B", after opening and passing through those gates in the exercise of their rights under the said s 88B instrument, amounts (in the absence of sufficient reason or excuse to do so on any particular occasion, as explained in these reasons) to an unreasonable use of their rights under the said s 88B instrument and is not permitted thereby. 3. Declare that the conduct of the plaintiffs/cross-defendants in leaving open the second farm gate erected across the right of way referred to in these reasons as Right of Way "A" (being the right of way on Lot 20 DP 1163017 (Lot 20) indicated on that deposited plan and created by the s 88B instrument registered on 5 April 2011 (Right of Way "A"), (referred to in these reasons as G2), after opening and passing through that gate in the exercise of their rights under the said s 88B instrument, amounts (in the absence of sufficient reason or excuse to do so on any particular occasion, as explained in these reasons) to an unreasonable use of their rights under the said s 88B instrument and is not permitted thereby. 4. Note that the Court does not accept a fear of cattle to amount to sufficient reason or excuse to leave any of the said farming gates open after having opened them in the exercise of rights under respective s 88B instruments. 5. Declare that the placement, deposit and spreading by the plaintiffs/cross-defendants of material (the Road Material) in the period August to September 2015 on part of Right of Way "A" and on Right of Way "B", constitutes a trespass to land by reason of being carried out without the consent of the defendants/cross-claimants and not being within the rights conferred on the plaintiffs/cross-defendants pursuant to either of the respective s 88B instruments creating the respective rights of way. 6. Order that the plaintiffs/cross-defendants notify the local Council and the Environment Protection Authority (EPA) in writing within 7 days as to the discovery of the fragment of asbestos on Right of Way "A" and provide copies to those authorities of the expert reports obtained from Dr Martens and Mr de Silva and tendered in these proceedings; and that the plaintiffs/cross-defendants comply with any direction by the EPA as to the containment or removal of part or all of the Road Material and thereafter remediate the rights of way so far as possible to restore them to their former condition as they existed prior to the placement, deposit and spreading of the Road Material. 7. For the avoidance of doubt if the EPA determines that the Road Material cannot be appropriately contained and should be removed, or otherwise is not able or not prepared to determine within a reasonable time a regime for the containment or removal of the Road Material, the defendants/cross-claimants have liberty to apply on reasonable notice for the making of orders for the removal by the plaintiff/cross-defendants of the entirety of the Road Material and remediation of the land at their cost. 8. Declare that the damage caused by the plaintiffs/cross-defendants to several large boulders on and in the vicinity of the respective rights of way in the course of road works carried out by them in or about August- September 2015 constitutes a trespass to land, by reason of it not being carried out with the consent of the defendants/cross-claimants and not within the rights conferred on the plaintiffs/cross-defendants pursuant to either of the respective rights of way. 9. Order that the damaged boulders each be replaced by the plaintiffs/cross-defendants at their cost with boulders of comparable size and appearance brought from off the plaintiffs/cross-claimants' property. 10. Reserve question of damages for trespass pending compliance with orders 6, 7 (if applicable) and 9 above. 11. Otherwise dismiss the plaintiffs' claims in the proceedings. 12. Reserve the question of costs. 13. Direct that written submissions as to costs be served within 7 days with the intent that costs will be determined on the papers. 14. Liberty to the parties to apply on 3 business days' notice for any amendment or variation of these orders and for directions in relation to the assessment of damages.
In the transferred proceeding (2016/00366908) 1. Declare that the respondents have carried out work (Work) on land being Lot 20 DP 1163017 and Lot 21 DP 1163020 (the Land) being development for the purposes of a private road, or alternatively for the purposes of a dwelling house, by constructing a road surface using imported fill being the access road to their dwelling house on adjoining land within their rights of way over the Land but without development consent, when development consent was required for the carrying out of work for either purpose within the E3 Environmental Management zone applying to the land under the Wyong Local Environmental Plan 2013, contrary to 76A Environmental Planning and Assessment Act 1979 (NSW). 2. Further declare that the respondents by carrying out the Work have carried out prohibited development on the Land being development for the purposes of a waste facility, which is an innominate prohibited use under the Wyong Local Environmental Plan 2013, contrary to 76A Environmental Planning and Assessment Act 1979 (NSW). 3. Declare that the respondents have used the Land as a "waste facility" contrary to s 144 of the Protection of the Environment Operations Act 1997 (NSW) by placing, depositing and spreading on the Land material within the definition of "waste" in that Act being imported fill being building waste and crushed concrete waste derived from concrete, brick, tile and pipe and trace pieces of steel, alloy and timber (the Road Material). 4. Note and confirm the orders made in the associated (easement) proceeding (2016/00140145) in relation to the notification to the local council and Environment Protection Authority (EPA) as to the discovery of asbestos and for compliance with any direction by the EPA as to the containment or removal or part or all of the Road Material. 5. Reserve the question of costs. 6. Direct that written submissions as to costs be served within 7 days with the intent that costs will be determined on the papers. 7. Liberty to the parties to apply on 3 business days' notice for any amendment or variation of these orders and for directions in relation to any further relief to be granted following compliance with the orders made in the associated (easement) proceeding.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 13 December 2017
Pullen
Smedley
[2005] VSC 77
[2006] TASSC 8
[2017] QDC 64
[1986] TASSC 3
(2007) 230 CLR 438
(1971) 126 CLR 376
(1982) 149 CLR 337
(2006) 148 LGERA 61
(2007) 230 CLR 89
(2006) 229 CLR 545
(2013) 84 NSWLR 688
(1987) 10 NSWLR 335
(2007) 233 CLR 528