Consideration
46 The parties dispute the nature of the case pleaded by the ACCC. In particular, the parties dispute whether the primary judge's conclusions concerning the involvement of Nexans in the Snowy Hydro Project Agreement and the consequences these conclusions had on the position of Prysmian aligned sufficiently with that case. Further, the parties appear to dispute how to properly characterise or understand what the primary judge actually concluded on Nexans' involvement in the implementation of the Snowy Hydro Project Agreement.
47 We therefore begin by setting out our understanding of the primary judge's conclusions concerning the nature and degree of Nexans' involvement in the Snowy Hydro Project Agreement. We then assess the extent to which these conclusions comport with the case pleaded by the ACCC at trial.
48 The key passages of the Reasons of the primary judge in relation to ground 1 are found at [201]-[202]. These are set out in full above. It is important to appreciate that these passages are not to be read in isolation. In particular, it is to be recalled that the primary judge had already concluded that Nexans was a party to the A/R Cartel Agreement and that Nexans could nevertheless have an interest in the Snowy Hydro Project even though it had not been invited to tender. Returning to [201]-[202], the primary judge reached the following conclusions:
Someone from the R Group side asked for an R preference to which the A Group agreed;
The request on the R Group side was made by Prysmian;
Nexans SA was aware of the Snowy Hydro Project;
For Nexans SA to have been a 'party' to the Snowy Hydro Project Agreement, there needed to be evidence that it consented or committed as distinct from simply knowing about it but doing nothing;
The evidence was insufficiently clear to conclude that Nexans SA did in fact make a commitment in that regard.
49 Further, at [203], his Honour came to the view that he could see:
… no reason why my conclusion that Nexans SA was not a party to the Snowy Hydro Project Agreement means that I am precluded by the ACCC's pleading from concluding that Prysmian was a party.
50 It is apparent that the primary judge was aware of the pleading and was focusing on the question of the relevant parties to the Snowy Hydro project Agreement. As the primary judge made clear at [201], the inquiry his Honour was making was whether Nexans could be held to be a party to the Snowy Hydro Project Agreement. It was in that context that the primary judge inquired as to whether there was a meeting of minds and a commitment by Nexans.
51 In order to understand properly the meaning and implications of these conclusions, they must also be read in the context of other relevant and interrelated conclusions elsewhere in the primary judge's Reasons. Some of this context has already been referred to by us. In particular, the primary judge stated at [200] that 'Nexans SA could not commit to doing an act or refraining from doing an act' in respect of the Snowy Hydro Project. This was because Nexans SA was never going to engage in the public tender process (Reasons, [200]). It was in that context that his Honour considered at [201] that 'a party which was never going to be the particular allottee nevertheless had such an interest in the allocation that its consent was necessary'. His Honour thus considered that a participant's explicit consent was necessary for it to 'commit' to a particular instance in circumstances where that participant was never otherwise going to be a potential allottee. This stands to reason. If a participant was never going to be engaged or interested in a given tender (in a direct commercial sense), such a participant would be unlikely to engage in the kinds of conduct that would otherwise demonstrate it being a party to that given instance, such as submitting a tender in accordance with the Price Guidance or choosing to refrain from submitting a bid.
52 Beyond that, the primary judge did not articulate any conclusions stating or implying that Nexans SA had removed itself entirely from the typical operation of the A/R Cartel Agreement for the purposes of the Snowy Hydro Project. In our view, this is significant. It would be erroneous to conflate, on the one hand, a participant's non-involvement in the typical A/R Cartel Agreement altogether in a given instance with, on the other hand, a participant's tacit non-involvement in a given instance due to a lack of direct commercial interest. In particular, a participant may fail to 'commit' itself in an instance where it has no direct commercial interest. However, it does not necessarily follow that the participant has therefore eschewed the A/R Cartel Agreement entirely. Rather, in such circumstances, it is conceivable that a participant could essentially observe the procedures of the A/R Cartel Agreement - including through a certain passivity or acquiescence - but could nonetheless decline to 'commit' itself to the given instance of conduct.
53 In that connection, we also consider it significant that the primary judge posed '[t]he question [of] whether the parties considered they would undertake the process envisaged by the A/R Cartel Agreement in the circumstances identified in the agreement', and concluded that '[t]here is abundant evidence that they did' (Reasons, [173]). The primary judge therefore concluded the participants (including Nexans) understood themselves to be generally bound by the A/R Cartel Agreement. Additionally, the primary judge appeared to accept that there was a specific procedure for instances of disagreement where a project was not subject to the A/R Cartel Agreement (Reasons, [59], [93] and [173]), which did not appear to have been activated by Nexans.
54 Accordingly, when the primary judge concluded that Nexans SA did not 'commit' itself to the Snowy Hydro Project Agreement, this did not imply a finding that Nexans SA abdicated the A/R Cartel Agreement entirely in that instance. Such an implication would not be consonant with the abovementioned conclusions in the Reasons that the participants considered that they would undertake the process envisaged by the A/R Cartel Agreement. Nor would it be consonant with the existence of a specific procedure for instances of disagreement where a participant wished effectively to suspend its ordinarily operation, and which does not appear to have been activated for the Snowy Hydro Project Agreement.
55 The documentary evidence surveyed and cited by the primary judge supports this understanding. In particular, although Nexans SA was not invited to tender for the Snowy Hydro Project, Mr Jay of Nexans was nonetheless the addressee of the A Group's email request for allocation of 12 September 2003 and the A Group's email acceptance of the R Groups request for allocation of 24 September 2003. The reasonable inference can be drawn from this correspondence that Mr Jay of Nexans continued to facilitate the process envisaged by the A/R Cartel Agreement (including as the 'window' for the R Group) despite Nexans itself not specifically 'committing', as such, to the particular instance in question.
56 In this regard, it is important to recall the role of Mr Jay as found by the primary judge. It is true that primary judge found that Mr Jay (among others) was not an employee of Nexans SA and was not granted any delegation of power by the Board of Nexans SA or the chief executive officer (Reasons, [148] and [238]). His Honour concluded at [240] that:
I do not think that there can be any doubt that Mr Romand, a senior executive, and Mr Jay were acting on behalf of a Nexans company and that that company was a major company in the Nexans Group of companies. The alternatives seem to be their employer, Nexans France, or Nexans SA. The question is whether they were acting for Nexans France or Nexans SA. …
57 However, Mr Jay also acted, as we have just mentioned, as the so-called 'window' for the R Group (Reasons, [52], [54], [86], and [115]). This is not to conclude that Mr Jay was necessarily an agent of the R Group in any technical or legal sense; just that the participants acted on the basis that Mr Jay would be the relevant natural person to act between the two Groups on behalf of the R Group.
58 In summary, we understand the primary judge to have concluded that Nexans SA did not 'commit' to the Snowy Hydro Project Agreement. This was because Nexans SA had no direct commercial interest in that instance (and thus was never going to be a participant in the sense of following the Price Guidance issued for that project), and did not otherwise provide explicit consent to committing to that instance. Importantly, however, we also understand the primary judge to have concluded that Nexans SA would have undertaken the process envisaged by the A/R Cartel Agreement to the extent relevant and applicable (Reasons, [173]). To that extent, the evidence suggested that Mr Jay of Nexans continued to facilitate the process envisaged by the A/R Cartel Agreement acting in the way we have described on behalf of the R Group.
59 We turn now to whether these conclusions comport with the case pleaded by the ACCC before the primary judge. We recall, in that regard, the appellant's contention that, according to the ACCC's pleadings, it was fundamental to the ACCC's case against Prysmian at trial was the proposition that Prysmian acted together with Nexans. For the appellant, their mutual participation was a necessary integer to the existence and operation of the A/R Cartel Agreement and the making of any agreement "pursuant to" or "giving effect" to it, and nowhere did the ACCC contend that Prysmian alone (or, for that matter, Nexans alone) reached some sui generis agreement with the A Group members (see Further Amended Statement of Claim, [34]). Further, mutual participation was required within the R Group by Nexans and Prysmian (see Further Amended Statement of Claim, [35]).
60 Looking at the pleading in [34] of the Further Amended Statement of Claim, reference is made therein to the arrival of an arrangement and understanding between two groups. We consider that in the context of the allegations and the findings of the primary judge, this arrangement and understanding was in fact reached. The essence of the complaint concerned the allocation to a member of the R Group of the Snowy Hydro Project as an R Preference and pursuant to the processes of the A/R Cartel Agreement (to which Nexans was a participant). The allocation was confirmed to the R Group through Mr Jay.
61 Turning attention to the pleading in [35] of the Further Amended Statement of Claim, this aspect of the ACCC's case in respect of the Snowy Hydro Project Agreement flowed from its pleading in respect of the A/R Cartel Agreement generally that 'if a project was given an A Preference or R Preference, the members of the A Group or the R Group respectively would then agree between themselves as to which of them would be the Allottee' (Further Amended Statement of Claim, [16.10] emphasis added). The pleadings do not prescribe further the specific form that such an 'agreement' must take, and in our view the nature and extent of any such 'agreement' will logically rest on the particular circumstances of a given instance. In the case of the Snowy Hydro Project Agreement, the ACCC submitted that (Applicant's Amended Outline of Closing Submissions, [30.9]):
… sometime between 12 September 2003 (Tab 318) and 24 September 2003 (Tab 319) Mr Jay agreed with a representative from Prysmian that Prysmian would be the R Group's allottee in respect of the Snowy Hydro project pursuant to the A/R Cartel and that Mr Jay communicated this to Mr Osada and sought an R preference. On 12 September 2003 the A representatives were seeking 'preference' in respect of the project. By 24 September, however, it was agreed that the R representatives would be given preference. A powerful inference arises that there must have been some communication between the R representatives, and then between Mr Jay and Mr Osada, confirming the R preference prior to the email which resulted in the rejection of the request for an A preference by Mr Osada.
62 This contention of the ACCC suggests that the internal agreement within the R Group to seek an R Preference for the Snowy Hydro Project and the internal agreement that Prysmian would be the allottee would have essentially been part of the same transaction or correspondence in this instance. In our view, this is not an unreasonable approach for the purposes of the Snowy Hydro Project Agreement. The fact that only one member of the R Group was invited to tender and had any direct commercial interest in that project would likely attenuate the nature and extent of any internal R Group agreement on its allocation. Indeed, in those circumstances, it is entirely plausible that the very fact of agreeing to seek a preference for the R Group for that tender would likely also discharge the internal agreement on which member of R Group would be allocated such a preference if granted. Further, such an understanding would accord with the evidence of Mr Osada that '[a]s quotes or tenders for a cable project could generally only be submitted by those Participants contacted and invited by a customer to submit a price in relation to the project, arrangements were reached as to which of those Participants contacted by the customer should be the successful tenderer', and further, that allocation determinations within groups seemed to pertain to "who, of those who had received inquiries from the customer, would win the project" (Osada Affidavit, [17] and [20] emphases added).
63 According to the primary judge's findings, 'someone from the R Group side asked for an R preference' and 'the request on the R Group side was made by Prysmian' (Reasons, [201]). It seems to us that the primary judge therefore considered - consistent with the pleadings of the ACCC - that the R Group agreed that Prysmian would be the allottee. The documentary evidence in the form of the 24 September Osada-Jay Email records an understanding on the part of A Group that the request for a preference originated from the R Group, as do Mr Osada's personal 'position sheets' on all cartel activities and notes from an A/R Cartel meeting on 27 November 2003 (see Reasons, [67] and [72]). It can also be reasonably inferred from the documentary evidence in the form of both the 12 September Osada-Jay Email and the 24 September Osada-Jay Email that the request was progressed through the usual channels used by the R Group, namely Mr Jay of Nexans.
64 If Nexans did not agree to the allocation to Prysmian of the Snowy Hydro Project within the R Group, then it would not make sense for Nexans to agree to seeking an R Preference in the first place, nor for Mr Jay to be complicit in the correspondence that characterised the such a preference as being from the 'R Group'. It would also be discordant with Mr Jay's inclusion of the Snowy Hydro Project on the 'position sheets' of A/R Cartel projects that were distributed to the cartel participants (see Reasons, [62]-[66]).
65 Accordingly, and contrary to the submissions of the appellant, we are satisfied that the primary judge's findings regarding Nexans' involvement are consistent with the ACCC's Further Amended Statement of Claim. Indeed, not only did the ACCC not contend that Nexans was invited to tender for the Snowy Hydro Project, but it also appeared to accept that Nexans' involvement was essentially limited to observing the procedural aspects of the A/R Cartel Agreement. In particular, we note the following submissions put by the ACCC (see transcript, p 3, lines 2-30; p 4 lines 2-4):
Nexans, having made or arrived at the Snowy Hydro project agreement… did not thereafter participate in the Snowy Hydro tender as it occurred, but instead it appears, and the commission will invite your Honour to draw the inference, that some arrangement or understanding was entered into between Nexans and Prysmian, they being the European R Group representatives in the A/R Cartel. …
Some arrangement was entered into between them, inferentially, that Prysmian would be the successful tenderer for the Snowy Hydro transaction in 2003, and Nexans did not, it appears, take any further interest in that transaction and did not itself submit a bit. So whilst it made the agreement in the ways that I will come to in more detail later in this opening, your Honour, it did not do anything, it appears to give effect to it. …
…Nexans, it appears, was not interested in this particular transaction or, alternatively, had entered into some arrangement with Prysmian that it should have this particular contract …
66 For the avoidance of doubt, our findings in this regard should not be taken to mean that Nexans 'gave effect' to the A/R Cartel Agreement in respect of the Snowy Hydro Project Agreement. Such a question is not before us on appeal, and it is not inevitably the case that undertaking the process envisaged by the A/R Cartel Agreement equates to 'giving effect' to that agreement in a given case. Rather, whether this is so would depend on the nature of the alleged conduct in a given case and whether it meets the requirements of the legal standard under s 45 of the Act. We express no views in that regard on appeal, and nothing before us suggests the primary judge's findings should be disturbed.
67 We consider our foregoing considerations to be sufficient in discharging the first ground of appeal in favour of the respondent. However, we will nonetheless address the broader issue of whether the primary judge's findings undermined the due process that ought to have been afforded to the respondent at first instance, given that this was a main focus of dispute between the parties on appeal.
68 The appellant suggests that the approach of the primary judge reflected such a departure from the case run by the ACCC that it was denied natural justice. According to the appellant, if it had anticipated a case run on the basis of Nexans not 'committing' to the Snowy Hydro Project Agreement, it would likely have responded differently, for instance in terms of the evidence led or submissions made.
69 Relevant guidance on the principles applicable to due process in this regard was provided by the Full Court in Betfair Pty Ltd v Racing New South Wales (2010) 189 FCR 356 at [50]-[52] (this aspect of the matter was not taken on appeal to the High Court). The Full Court outlined the relevant principles in the following paragraphs, which we adopt for the present case:
[50] Pleadings provide a structure for a proceeding for the purpose of the attainment of justice. The pleadings identify the material facts upon which the parties rely and the issues the parties seek to have determined. Because the pleadings require the parties to identify all material facts and issues, the pleadings provide the benchmark for discovery before trial and the admissibility of evidence at trial. Parties are required to plead the material facts upon which the party relies and the issues which that party seeks to have resolved for the further purpose of giving the opposing party fair notice of the case to be met at trial thereby minimising any risk of injustice by taking the opposing party by surprise. Pleadings incidentally are the record of the proceeding for the purpose of any subsequent arguments relating to res judicata or issue estoppel or any like issue.
[51] At trial a party is entitled to have the opposing party confined to that party's pleadings because the first party is entitled to come to trial to meet only the issues raised on the pleadings. However, if the first party does not seek to so confine the opposing party but allows the other party to raise other material facts and issues for the determination of the Court, then in our opinion the Court is permitted and possibly obliged to decide the proceeding on the further material facts and issues raised and addressed at trial: Banque Commerciale at 296-297; Gould and Birbeck and Bacon v Mount Oxide Mines Ltd (in Liquidation) (1916) 22 CLR 490 at 517. If it were otherwise, the party who has failed to plead all of the material facts or issues upon which the party's case relies, but has brought those material facts or issues to the attention of his or her opponent at trial, would be denied natural justice if at the end of the trial the Court decided the proceeding on the pleadings without notice to that party. The first party in those circumstances would have been denied the opportunity to apply to amend those pleadings so as to formalise what was in fact addressed at the trial.
[52] Pleadings are a means to an end and not an end in themselves (Banque Commerciale per Dawson J at 292-3). As early as 1916 Isaacs and Rich JJ said, in Gould and Birbeck and Bacon v Mount Oxide Mines Ltd (in Liquidation) (1916) 22 CLR 490 (at 517):
Undoubtedly, as a general rule of fair play, and one resting on the fundamental principle that no man ought to be put to loss without having a proper opportunity of meeting the case against him, pleadings should state with sufficient clearness the case of the party whose averments they are. That is their function. Their function is discharged when the case is presented with reasonable clearness. Any want of clearness can be cured by amendment or particulars. But pleadings are only a means to an end, and if the parties in fighting their legal battles choose to restrict them, or to enlarge them, or to disregard them and meet each other on issues fairly fought out, it is impossible for either of them to hark back to the pleadings and treat them as governing the area of contest.
70 In addition, it is to be recalled that in deciding whether a point was taken at trial, 'no narrow or technical view should be taken' (see Water Board v Moustakas (1988) 180 CLR 491 at 497 per Mason CJ, Wilson, Brennan and Dawson JJ).
71 We do not accept the appellant's proposition that a 'commitment' on the part of Nexans was 'fundamental' or 'essential' to the case it faced, such that natural justice was denied. Regardless of our findings above that Nexans did indeed appear to follow the process envisaged by the A/R Cartel Agreement, it is not apparent to us that Nexans' participation assumed such an importance. The ACCC did not plead that Nexans was invited to participate in the Snowy Hydro Project tender. The ACCC's pleading focused on the fact that Nexans and Prysmian agreed on allocation matters in accordance with the process envisaged by the A/R Cartel Agreement.
72 The primary judge was entitled to proceed to make the findings he did regarding the involvement of Nexans. The appellant itself led no evidence at trial disputing this aspect, despite submitting that it should not be inferred that Nexans SA did anything at all in relation to the Snowy Hydro Project (see Reasons, [196]). The primary judge noted generally that 'the onus was on Prysmian to explain the absence of relevant witnesses from the witness box and it did not discharge that onus' (Reasons, [43]). We do not consider that the findings of the primary judge in respect of Nexans' involvement in the Snowy Hydro Project Agreement and his Honour's ultimate conclusions arising from these findings gave rise to a denial of natural justice to the appellant.
73 In conclusion, we reject the appellant's proposition that the primary judge's findings were inconsistent with the case pleaded by the ACCC, or gave rise to a denial of natural justice to the appellant. Accordingly, we reject the appellant's first ground of appeal.