20A By issuing the Apache Force Majeure Notice, by failing to withdraw the whole of the Apache Force Majeure Notice and in sending the 22 December 2010 letter (together the 'Apache Northwest Conduct'), Apache Northwest conveyed the following unqualified representations ('Representations'):
(a) Apache Northwest, Tap and Kufpec had no obligation to supply gas to YPFPL under the GSA from areas outside the Harriet Field;
(b) that the fact there was insufficient gas in the Harriet Field to supply YPFPL as required under the GSA constituted an act of force majeure; and
(c) the Apache Force Majeure Notice was valid.
Particulars of (a) to (c)
(i) The Representations are express and implied.
(ii) To the extent they are express, they are in writing and contained in the Apache Force Majeure Notice and the 22 December 2010 letter.
(iii) To the extent the Representations are implied, they are to be implied from the GSA, the Apache Force Majeure Notice, the failure of Apache Northwest to withdraw the whole of the Apache Force Majeure Notice and the 22 December 2010 letter.
(iv) Further particulars may be provided prior to trial.
20B In and from at least July 2011, Apache Energy conducted meetings and discussions with Stage 2 Bidders on behalf of Apache Northwest and Apache Corp in relation to a potential settlement of the GSA proceeding and entry into a new gas sale agreement, in which Apache Energy:
(a) offered (on behalf of Apache Northwest and Apache Corp) to compromise the GSA proceeding on terms that a new gas sale agreement be entered into with Apache Energy for gas at USD $2/GJ until July 2015, USD $5/GJ for the next five years to July 2020, gas capped at 87TJ/day and no gas thereafter;
(b) asserted that the GSA proceeding would be resolved in favour of Apache Corp and Apache Northwest, resulting in the effective termination of the GSA; and
(c) did not qualify, withdraw or resile from the Apache Northwest Conduct or the representations,
(together, the 'Apache Energy Conduct').
Particulars
(i) The meetings and discussions occurred in around July 2011 between representatives of Apache Energy (on behalf of Apache Northwest and Apache Corp) and representatives of the Stage 2 Bidders (except for Apache Energy). At various of those meetings, Apache Energy offered to compromise the GSA proceeding on terms that a new gas sale agreement be entered into with Apache Energy for gas at USD $2/GJ until July 2015, USD $5/GJ for the next five years to July 2020, gas capped at 87TJ/day and no gas thereafter [SAL.001.008.3866; ANZ.603.105.3874], an offer that was 'so un-commercial' that it effectively prevented other bidders from making binding, unconditional bids for the Shares (CFLA.001.001.0936]. At no stage during any of those meetings did Apache Energy qualify, withdraw or resile from the Conduct or the Representations. Instead, Apache Energy adopted the Conduct and the Representations to further its own purposes and those of the Apache group of companies.
(ii) In a meeting with representatives of Orascom in around July or August 2011, a representative of Apache Energy said words to the effect that its legal dispute with YPFPL would be resolved in Apache's favour, resulting in the effective termination of the GSA [SAL.010.004.1920].
(iii) Discussions between Sinofert and Apache Energy in around July were referred to in Flagstaff Partners document dated 21 July 2011 entitled 'Project O - Second Round Offer Clarifications Discussion with Sinofert' which states that 'The uncertainty regarding the GSA was too great a risk for Sinofert to accept and without resolution of this dispute, they would be unable to contemplate providing a final bid for this business... recent discussions with Apache indicate that Apache were proposing a settlement that would adversely affect the value of the business for ANZ/PPB such that the value implied by Sinofert's bid on this basis would be a fraction of what was required to be recovered (i.e. London offer)' [SAL.010.004.1696].
20C By engaging in the Apache Energy Conduct, Apache Energy conveyed the Representations.
Particulars
Pankaj repeats the particulars to paragraph 20B.
20D Each of:
(a) the Apache Northwest Conduct;
(b) the Apache Energy Conduct; and
(c) the Representations,
was misleading or deceptive or likely to mislead or deceive in that they were false, inaccurate, incorrect as:
(d) Apache Northwest, Tap and Kufpec were obliged to supply gas to YPFPL under the GSA from areas outside the Harriet Field;
(e) the fact there was insufficient gas in the Harriet Field to supply YPFPL as required under the GSA did not constitute an act of force majeure; and
(f) the Apache Force Majeure Notice was invalid.
20E Further or alternatively, by reason of the matters set out in paragraphs 20A to 20C above, each of Apache Northwest and Apache Energy represented that it had a reasonable basis for making the Representations ('Basis Representation').
20F At the time of making the Representations and the Basis Representation, each of Apache Northwest and Apache Energy was or ought to have been aware:
(a) of the express terms of the GSA, which had the features pleaded in paragraph 10O(i) above;
(b) of the terms that are usually included in a field depletion contract (ie, a contract only for the supply of such gas as remained in or could be extracted from a specific field), including the terms pleaded in paragraph 10O(i) above, and of the fact that such terms were absent from the GSA;
(c) that Apache Northwest, Tap and Kufpec were obliged to supply gas to YPFPL under the GSA from areas outside the Harriet Field;
(d) that the fact there was insufficient gas in the Harriet Field to supply YPFPL as required under the GSA did not constitute an act of force majeure; and
(e) that the Apache Force Majeure Notice was invalid.
Particulars of (a) to (c)
(i) The matters set out in paragraphs (a) and (c) were obvious on the face of the GSA.
(ii) At the time of making the Representations and the Basis Representation, Apache Northwest and Apache Energy were experienced operators in the gas supply industry and must have been familiar with the terms usually present in a field depletion contract.
Particulars of (d) to (e)
(iii) These matters were obvious from the matters set out in paragraphs (a) to (c), and Apache Northwest and Apache Energy must have been aware of them. Further and alternatively, Apache Northwest and Apache Energy's knowledge of these matters is to be inferred from the following matters.
(iv) Before the GSA was executed, Apache Energy (acting on behalf of Apache Corp and Apache Northwest) provided the Letter of Comfort pleaded at paragraph 10H [PPB.012.010.6186], which relevantly stated that 'wholly owned subsidiaries of Apache Energy were participants in a number of other joint ventures in respect of other gas fields [ie, outside the Harriet Field], the uncontracted proven reserves for which totalled 607PJ'. This statement is inconsistent with a belief that:
(A) the GSA required Apache Northwest to supply gas only from the Harriet Field;
(B) the fact there was insufficient gas in the Harriet Field to supply YPFPL as required under the GSA constituted an act of force majeure;
(C) that the Apache Force Majeure Notice was valid.
20G By reason of the matters pleaded in paragraph 20F above, each of Apache Northwest and Apache Energy did not have a reasonable basis for making any of the Representations or the Basis Representation.
20H By reason of the matters pleaded in paragraphs 20F to 20G above, the Basis Representation was misleading or deceptive or likely to mislead or deceive.