© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2019] NSWCA 150
Court of Appeal (NSW)
2019-05-31
Bell P, Payne JA, White JA, Darke J
Original judgment source is linked above.
Solicitors: Sachs Gerace Broome (Appellant) Day Legal (Respondents) File Number(s): 2019/134106 Decision under appeal Court or tribunal: Supreme Court of New South Wales Jurisdiction: Equity Division Citation: [2019] NSWSC 449 Date of Decision: 24 April 2019 Before: Darke J File Number(s): 2019/8599
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
[This headnote is not to be read as part of the decision] The appellant appealed from the orders of a judge of the Equity Division requiring that he specifically perform a contract for the sale of land, in which he was the purchaser. The stipulated date of completion was 11 October 2018, but a dispute supervened and the contract did not proceed to completion. The dispute concerned Special Condition 49 of the contract, which provided: "Notwithstanding clause 35, the vendor discloses works have been carried out in accordance with the Development Approval annexed to the contract, however, the lower staircase requires replacement. The vendor agrees to ensure the replacement of the lower staircase is carried out in accordance with the Development Approval prior to settlement. The vendor warrants that all Development Consent Conditions will be satisfied on or before completion and will provide an occupation certificate to the purchaser prior to settlement. The purchase cannot make a claim or requisition or rescind or terminate in respect of this work." Only some of the work authorised by the Development Approval had been completed. The stairs were replaced so as to be in accordance with the Development Approval and an interim occupation certificate was issued in respect of internal demolition and the renovation done to the stairs only. The primary judge, on the purchaser's cross-claim, held that Special Condition 49 did not require the vendors to complete the balance of the works permitted by the Development Approval. The primary judge did not accept that the warranty that all Development Consent Conditions would be satisfied on completion required the completion of the balance of the works, holding that the consent was permissive and not mandatory, and that to the extent that there was a warranty that the works would be in compliance with the conditions of the consent that warranty applied only to works that had in fact been carried out. His Honour further found that the vendors' obligation to provide an occupation certificate prior to settlement was satisfied by the provision of an interim certificate, rather than only a final occupation certificate. On appeal, the issues were: (i) Whether the first sentence of the clause amounted to a disclosure that all of the permitted works had been carried out; (ii) Whether the clause required provision of a final, rather than interim, occupation certificate; (iii) Alternatively, whether, given the limited scope expressed on the face of the interim certificate, it authorised the purchaser to occupy lawfully the whole of the premises or only the stairs. The Court of Appeal (White JA, Bell P and Payne JA agreeing at [1] and [2] respectively), dismissing the appeal, held: As to Issue 1: The first sentence of the clause ought to be construed as disclosing that any works in fact done had been done in accordance with the Development Approval, except in one respect - the lower staircase (at [34]); As to Issue 2: In the case of an alteration to a portion of an existing building, it is incorrect to proceed on the assumption which underpinned the purchaser's submission that a final occupation certificate could only be issued once all of the work the subject of the development approval was completed (at [41]), and in any event Special Condition 49 cannot be read as requiring only a final occupation certificate (at [42]); As to Issue 3: The interim occupation certificate was not confined only to authority to occupy the staircase. The occupation certificate, when read in light of the relevant record of inspection, demonstrated that the certifier was satisfied that all works undertaken pursuant to the development consent were compliant (at [79]-[81]) and authorised occupation of all areas for which an occupation certificate may have been required (at [92]). Further, the issues relevant to whether the occupation certificate authorised occupation of the whole of the building were not ventilated at trial and should not be permitted to be raised on appeal (at [84]-[91]).
Judgment
and as amended by the conditions of this consent. (b) In the event of any inconsistency between the approved plans and supplementary documentation, the plans will prevail. (2) DESIGN MODIFICATIONS The design of the building must be modified as follows: (a) The proposed removal of the existing window on the primary Forbes Street façade is not approved, and is to be deleted. (b) The alignment of the rear wall of the proposed ground floor extension is to match the angled alignment of the first floor rear wing addition. (c) The eave extending from the rear wall of the proposed ground floor rear addition is to be deleted and replaced with a lightweight shading device separate from the roof form. (d) The proposed ensuite adjoining existing bed 2 is to avoid contact the existing fireplace and chimney breast which are to be retained. (e) A Schedule of Materials, Colours and Finishes is required. The modifications are to be submitted to and approved by Council's Area Planning Manager prior to the issue of a Construction Certificate. ... (27) OCCUPATION CERTIFICATE TO BE SUBMITTED An Occupation Certificate must be obtained from the Principal Certifying Authority and a copy submitted to Council prior to commencement of occupation or use of the whole or any part of a new building, an altered portion of, or an extension to an existing building."
The primary judge's reasons
Extent of vendors' obligation to carry out works
Sufficiency of occupation certificate
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 20 June 2019
Pollak
Yapp
(1982) 149 CLR 337
(2017) 261 CLR 544
(2014) 251 CLR 640
(1940) 63 CLR 201
(2005) 221 CLR 522