PNC Lifestyle Investments Pty Ltd v REW08 Projects Pty Ltd
[2017] NSWSC 993
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2017-07-26
Before
Darke J, Mr J, Mr P
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Introduction
- The Court delivered its first judgment in these proceedings on 2 February 2017 (see PNC Lifestyle Investments Pty Ltd v REW08 Projects Pty Ltd [2017] NSWSC 27). The Court ordered that the defendant ("REW") specifically perform a contract for the sale of certain land in Schofields that was entered into in June 2014 between the plaintiff ("PNC") as purchaser and REW as vendor. The Court held that that the termination of the contract by REW was invalid (see at [83]). The Court further held that $250,000 advanced by PNC constituted both the deposit under the contract for sale and the principal sum under a related loan agreement between the parties (see at [81]-[82]).
- It was agreed at the hearing of the specific performance claim that any claim for damages by PNC would be deferred to a subsequent hearing. On 24 March 2017 directions were made for PNC to provide particulars of the loss it claims, and for the filing and service of evidence on damages. PNC provided particulars and filed an affidavit of Mr Michael Cseh, one of its directors. REW did not file any evidence. On 5 May 2017 directions were made by consent which provided for the issue of damages to be determined on the papers. Written submissions have been provided by both parties in accordance with those directions. As no party suggested that a further oral hearing was necessary, the Court will proceed to deal with the question on the papers.
- PNC claims that REW has breached the contract by failing to cause the completion date under the contract to be set, and failing to proceed to complete the contract. PNC alleges that had the breaches not occurred, the contract would have been completed in about April 2016. It seeks damages to compensate for higher construction costs it now faces as a result. PNC also claims that the delay in completion has caused it to lose rental income.
- REW resists any award of damages. It contends that PNC is only entitled to the interest payments made under the loan agreement, which it says are greater than the amount of damages that could be awarded in any event. REW also challenges the claim for lost rental income on various grounds.