Neither a progress certificate nor a payment of moneys shall be evidence that the subject WUC has been carried out satisfactorily. Payment other than final payment shall be payment on account only."
12 "WUC" is defined in cl 1 of the contract to mean the work which the contractor is or may be required to carry out and complete under the contract and includes variations, remedial work, construction plant and temporary works.
13 "Item" is defined in cl 1 to mean an item in Annexure Part A. Item 28 of that Annexure provides that the times for progress claims are the 14th and 28th days of each month which are for WUC done to the 1st and 14th days of each month respectively.
14 The first defendant subcontracted out to Merrmac Pty Ltd ("Merrmac") certain of the works under the contract.
15 On 28 February 2008 Merrmac rendered an invoice to the first defendant for $476,868.67 plus GST described as "Claim 7".
16 On the same day the first defendant made a progress payment claim pursuant to the provisions of s 13 of the Act for $958,553.53 ("the payment claim"). The total was comprised of a number of separate line items. One of these was for $476,868.67 plus GST in respect of Merrmac's Claim 7.
17 The payment claim was directed both to the plaintiff and to the Superintendent under the contract.
18 The Superintendent did not within 14 days after receiving the payment claim issue a progress certificate.
19 It follows that under cl 37.2 of the contract the payment claim was deemed to be the relevant "progress certificate", and the plaintiff became bound under cl 37.2 to pay the amount less any deductions provided by the provision.
20 On 5 March 2008 the plaintiff took out of the hands of the first defendant the whole of the work remaining to be completed under the contract pursuant to cl 39.4 of the contract.
21 On 13 March 2008 the plaintiff replied to the payment claim by providing a payment schedule as contemplated by s 14 of the Act. The payment schedule indicated that the plaintiff owed the first defendant nothing but that the first defendant owed it $40,557.53. The payment schedule dealt with each of the line items in the payment claim including Merrmac's Claim 7.
22 On 17 March 2008 the plaintiff and Merrmac entered into a deed of agreement ("the deed"). The deed recorded the subcontract arrangements between the first defendant and Merrmac, including that there had been a variation revising the scope of the works to be performed by Merrmac, the fact that the remaining work had been taken out of the hands of the first defendant and that the first defendant had failed to make payment to Merrmac for moneys due and owing with respect to the performed works including part of the amended variation.
23 The deed further recorded that the value of the works including the variation and the amount which was owing by the first defendant to Merrmac was $176,907.67 plus GST and that, in addition, Merrmac had acquired material for the works invoiced in the sum of $398,500 plus GST for which Merrmac had not paid and which materials had been delivered to the site.
24 Clause 2 of the deed provided that the plaintiff would pay to Merrmac on or before 18 March 2008 the sum of $176,907.67 plus GST and would pay into Merrmac's solicitors' trust account on or before 20 March 2008 the sum of $398,500 plus GST.
25 Under cl 3 of the deed the plaintiff undertook to pay Merrmac for the unperformed works in accordance with the terms of its subcontract with the first defendant, in accordance with progress claims to be made by Merrmac pursuant to the Act and to be addressed to "Simon's c/o Plaza West" at the plaintiff's address.
26 On 31 March 2008 the first defendant made an adjudication application pursuant to s 17(1) of the Act for the amount of the payment claim, namely $958,553.53 (including GST). Of that amount $575,406.67 plus GST (the sum of the amounts referred to in clause 2 of the deed) was referrable on the face of the claim to Merrmac.
27 Paragraphs 31 to 40 of the adjudication application were in the following terms:
Payment Clause
31. The payment clause under the Contract is set out below:
37.1 Progress claims
The Contractor shall claim payment progressively in accordance with Item 28.
An early progress claim shall be deemed to have been made on the date for making that claim.
Each progress claim shall be given in writing to the Superintendent and shall include details of the value of WUC done and may include details of other moneys then due to the Contractor pursuant to provisions of the Contract.
37.2 Certificates
The Superintendent shall, within 14 days after receiving such a progress claim, issue to the Principal and the Contractor :
a) a progress certificate evidencing the Superintendent's opinion of the moneys due from the Principal to the Contractor pursuant to the progress claim and reasons for any difference (' progress certificate' ); and
b) a certificate evidencing the Superintendent's assessment of retention moneys and moneys due from the Contractor to the Principal pursuant to the Contract.
If the Contractor does not make a progress claim in accordance with Item 28, the Superintendent may issue the progress certificate with details of the calculations and shall issue the certificate in paragraph (b).
It the Superintendent does not issue the progress certificate within 14 days of receiving a progress claim in accordance with subclause 37.1, that progress claim shall be deemed to be the relevant progress certificate.
The Principal shall within 7 days after receiving both such certificates, or within 21 days after the Superintendent receives the progress claim, pay to the Contractor the balance of the progress certificate after deducting retention moneys and setting off such of the certificate in paragraph (b) as the Principal elects to set off. It that setting off produces a negative balance, the Contractor shall pay that balance to the Principal within 7 days of receiving written notice thereof.
Neither a progress certificate nor a payment of moneys shall be evidence that the subject WUC has been carried out satisfactorily. Payment other than final payment shall be payment on account only.
32. The Payment Claim was a payment claim under the Act and a progress claim under the Contract.
33. The Payment Claim was clearly served on the Superintendent. However, whilst Plaza West has responded by serving the Payment Schedule, the Superintendent has not issued any Payment Certificate in respect of the Payment Claim.
34. This has a severe consequence for the Respondent. This is because clause 37.2 of the Contract provides that if the Superintendent does not issue a payment certificate within the time stipulated by the Contract (14 days), the progress claim is deemed approved and the Principal must pay the amount of the progress claim as if that amount appeared in a payment certificate.
35. As such, by reason of the Contract, the approved value of the Payment Claim is deemed to be for its full value.
36. This has an important consequence under section 9 of the Act, which relevantly provides:
The amount of a progress payment to which a person is entitled in respect of a construction contract is to be:
(a) the amount calculated in accordance with the terms of the contract; and
(b) …
37. As such, an adjudicator is bound to value the Payment Claim in accordance with the Contract. Due to the Superintendent's failure to certify, the full amount of the Payment Claim is deemed approved under the Contract.
38. Simons expects that Plaza West will rely upon a letter from the Superintendent to Simons dated 12 February 2008 (see Tab 13 ). However, such letter is factually incorrect as to the voidness of the progress certification procedure under the Contract and fails to recognise the dual scheme of the Act, where the one claim can have consequences under the Act and under the relevant construction contract. Indeed, the consequences of a claim may be different under a construction contract that (sic) those under the Act.
39. By reason of the Superintendent's failure to issue a payment certificate in respect of the Payment Claim the amount due and payable by the Respondent under the Contract, and by reason of section 9, under the Act, is the full amount claimed in the Payment Claim.
40. It is appropriate to deal with and dismiss each of the purported reasons for non payment in turn."
28 The adjudication application also supported each of the line items in the payment claim.
29 On 8 April 2008 the plaintiff lodged with the adjudicator an adjudication response pursuant to s 20 of the Act. Paragraphs 25 to 31 of the adjudication response were in the following terms:
"25. As to paragraph 13, Plaza West acknowledges that no direct payment has been made by it to Simon's Earthworks in relation to the Payment Claim dated 28 February 2008 for $958,553.53 including GST. However, $524,555.54 of the Payment Claimant (sic) is in respect of the Payment Claim dated 28 February 2008 of Merrmac made against Simon's Earthworks. As of 20 March 2008, Plaza West has paid all of that $524,555.54 to Merrmac or its solicitors' Trust Account pursuant to an agreement dated 17 March 2008 between Plaza West and Merrmac. In fact, as noted in the chronology, Plaza West has paid an additional $108,392.90 into the Trust Account of the solicitors for Merrmac. A copy of the receipts for the payments is attached.
26. The amount claimed by Simon's Earthworks must accordingly be reduced by the $524,555.53 (sic) paid by Plaza West direct to Merrmac because the payment has reduced the amount outstanding on the Payment Claim dated 28 February 2008 of Merrmac against Simon's Earthworks to nil.
Jurisdiction
27. As to paragraph 23, Plaza West does not know if the Adjudication Application is made in accordance with the time permitted by the Act because it does not know when the application was lodged with the nominating authority. If the Application was lodged on 31 March 2008, Plaza West acknowledges that the Application will be within time. If it was lodged on or after 1 April 2008, being the date the Application was served on Plaza West, the Application will be out of time.
Payment Clause
28. Plaza West disputes the assertion in paragraph 32 that the Payment Claim was a claim under the Act and under the contract for the following reasons:
a. The Payment Claim is expressed to be made under the Act. Furthermore, it is not expressed to be made under the contract. Nor is there any reference in the claim to the payment claim clause under the contract, namely clause 37 of the General Conditions of Contract.
b. The Payment Claim is addressed to Plaza West. That is as required by the Act. Furthermore, the Payment Claim is not addressed to the Superintendent. It is merely copied to the Superintendent.
c. The submission that a progress claim could be made under both the Act and the contract is untenable for the following reasons:
i. Section 34(2)(a) of the Act specifically provides that any provision of a contract that modifies the operation of the Act is void. The Act requires that the party liable to pay must issue the Payment Schedule. By way of contrast, clause 37.2 however requires the Superintendent to issue the payment certificate. The provisions are inconsistent. By reasons of section 34(2)(a) of the Act, clause 37.2 is void.
ii. Further to the preceding sub-paragraph, a Superintendent, acting as an independent certifier, cannot issue a Payment Schedule on behalf of the party liable to pay the claim. That is because the independent role of the Superintendent means that it cannot be said that the Superintendent can act as the agent of the Respondent in issuing a Payment Schedule.
iii. In the alternative, the objective of the Act is not to create two sets of administrative arrangements instead of one (namely that under the contract) for making and processing progress claims. Rather it is to create an alternative statutory procedure for making and processing progress claims.
iv. Furthermore, if it were possible to make a claim under both the Act and the contract, a claim for the same amount could produce inconsistent payment obligations because the assessment of the claim in each case must be by different persons (namely the Principal under the Act and the Superintendent under the contract). Parliament cannot have intended such an outcome.
v. In the alternative, on a proper construction of the contract, the parties, as reasonable commercial parties, must be taken to have intended that in the event Simon's Earthworks chose to make a payment claim under the Act, the payment provisions of the contract would cease to have effect. That is consistent with the joint Judgment of 5 Justices of the High Court of Australia in Pacific Carriers Limited v BNP Paribas (2004) 218 CLR 451. At paragraph 22 their Honours identified the fundamental rules of construction which must be applied. The Judgment states at paragraph 22:
"…the meaning of commercial documents is determined objectively…The construction …is determined by what a reasonable person in the position of (a party to the contract) would have understood them to mean [at the time the contract is made]. That requires consideration, not only of the text of the documents, but also the surrounding circumstances known to (both parties to the contract), and the purpose and object of the transaction…
…In a commercial contract it is certainly right that the court should know the commercial purpose of the contract and this in turn presupposes knowledge of the genesis of the transaction, the background, the context, the market in which the parties are operating".
vi. A reasonable person in the positions of the parties would not adopt a construction of the contract which meant (a) administrative burden on the parties would be increased because two processes could apply for making and processing of progress claims instead of one and (b) inconsistent payment obligations could arise.
vii. Furthermore, compliance by the Superintendent with the Act by not invoking the inconsistent provisions of the contract would have "severe consequences" for the Respondent (to quote from paragraph 34 of the Claimant's Submissions) if the Claimant's submission were to be adopted. That is because compliance by the Superintendent with the Act would produce an outcome of inconsistent payment obligations notwithstanding that the Respondent had also complied with the Act and served a Payment Schedule providing, with reasons, for payment of less than the amount claimed. According to the claimant, the Respondent would then be obliged under the terms of the contract to pay the full amount claimed notwithstanding it had done everything required of it under the Act to avoid that default position. Clearly such a proposition is untenable.
d. Not surprisingly, no authority is cited by the Claimant in support of its submission.
29. It follows Plaza West rejects the assertions in paragraphs 34 to 37 of the Claimant's Submissions. The amount payable is to be determined under section 9(b) of the Act.
30. In response to paragraph 38, Plaza West notes that the paragraph contains mere assertion. Plaza West repeats its submissions at paragraph 28 above.
31. By reason of the foregoing, Plaza West rejects as untenable the submission in paragraph 39 of the Claimant's submissions."
30 The adjudication response went on to deal with the line items in the claim.
31 On 17 April 2008 the adjudicator determined that the amount of the payment claim to be paid by the plaintiff to the defendant, that is the adjudicated amount, was $958,553.53 (including GST).
32 It is necessary to set out a significant part of the adjudication determination:
" Claim under the Contract and the Act
10. The Respondent observes at paragraph 28, that they take issue with the assertion of the Claimant that the Payment Claim is made both under the contract and the Act. In my view this is a crucial and unfortunate view. The Claimant has agitated that the Respondent has provided a Payment Schedule, in compliance with the Act, but has failed to provide a Progress Certificate as required by the Contract. For the avoidance of doubt, it is relevant to note that the Payment Claim was served on both the Superintendent and the Respondent.
11. It has been recognised by the courts for some period of time that the Act has created a dual track system. The grounds raised by the Respondent in objection to this appear to be as follows:
11.1. claim does not mention clause 37 of the Contract which requires the Superintendent to issue a Progress Certificate, while the Act requires the Payment Schedule to be issued by the Respondent (ie the person liable to pay).
Determination - The Act has been interpreted to apply the law of agency and to recognise that the Superintendent may issue the Payment Schedule for and on behalf of the Respondent. However, it appears from the terms of the contract that the Respondent can not issue a Progress Certificate. I form this view on the explicit and mandatory form of words used in clause 37.2 of the contract.
11.2 claim not addressed to Superintendent, merely copied.
Determination - The contract provides at clause 37.1 that 'Each progress Claim shall be given in writing to the Superintendent and shall include …' That provision does not require it to be specifically addressed to the Superintendent. In my view it contemplates the claim being addressed to the principal yet provided to the Superintendent. If I am incorrect in this view it does not matter because the clause simply does not support the submission of the Respondent.
11.3 the Act is not intended to be a duplicate system.
Determination - This is not correct. The Act is intended to create a duplicate system, which in some cases will prevail over the contract and in other matters be subordinate.
11.4 a claim under the Act and the contract cannot produce duplicate liability.
Determination - this is correct as only one party can be liable to pay the claim, that party being the Respondent, however so constituted. It is not the situation that the Superintendent would become liable unless they had contracted separately, in which case the principal would not be liable. In any event the Superintendent is not named as the Respondent and the issue is moot.
11.5 making a claim for payment under the Act extinguishes the payment provisions of the contract.
Determination - The Act does not contain the level of detail to allow it to be the sole source of a Payment Claim, one of the basic and essential requirements of a claim is to have a construction contract in place between the parties. The learned judges of the High Court in Pacific Carriers v BNP Paribas (2004) 218 CLR 451 were not contemplating the Act in that judgment and it is distinguishable to the extent it is being relied on by the Respondent in their submissions. By way of example the High Court considered the application of the Act in Coordinated Construction Co Pty Ltd v J.M. Hargreaves (NSW) Pty Ltd & Ors [2006] HCA Trans 9 (3 February 2008), and made no observation of the type proposed. Further and expressly, the Act requires specific consideration of the contract with regard to matters such as valuation and interest. I do not accept this submission. If I am wrong in this regard I am in any event satisfied that a reasonable person on (sic) the position of the parties would be aware that they had a contractual burden to provide a Progress Certificate and a Payment Schedule. This is a broadly understood obligation, particulalrly (sic) amongst parties capable of performing the work contemplated under this contract. Examples of the provision of both documents in the single bundle of documents can be found in the reasons of the Court of Appeal in Baulderstone Hornibrook Pty Ltd v Queensland Investment Corporation [2007] NSWCA 9.
11.6 the Respondent suggests that the dual system places an onerous burden of complying with two regimes and an outcome of inconsistent payment obligations.
Determination - I do not accept that submission. While the public policy elements of the 'onerous obligations' are outside my scope as an Adjudicator, it is my view it does not create the duplicate payment obligations as suggested at paragraph 28(c)(vii) of the submissions. I have formed this view as the Act or the contract has primacy with regard to different matters; by way of example:
11.6.1 the Act requires a Respondent to advise their intention with regard to payment and reasons for non payment (if that is their view) within 10 business days or such shorter time as the contract may allow (see section 14(4)(b)). This creates a clear guideline to contracting parties that regardless of what term they put into a contract, if the claim is made under the Act the response cannot be provided later than 10 business days in the event that a claim is made under the Act. If a Superintendent observes the Payment Claim is made under the Act, they should serve the Progress Certificate this document could also fulfil the role of the Payment Schedule.
11.6.2 even where the contract may award a specific rate of interest or preclude the awarding of interest on delinquent payments the Act requires it to be awarded and also establishes minimum rates for such interest (see section 11(2) of the Act).
Conclusion Claim under the Contract and the Act
12. I have included this somewhat detailed appraisal of the submissions of the Respondent as it was a matter that they could not reasonably contemplate, however, this does not mean that the submission of the Claimant was disguised or fell outside the scope of the Payment Claim as discussed in decisions of the Court in John Holland Pty Limited v Cardno MBK (NSW) Pty Limited & Ors [2004] NSWSC 258 or Energy Australia v Downer Construction (Australia) Pty Ltd and 2 ors [2006] NSWSC 52. I have also provided this level of detail as it is essential in light of the submission of the Claimant that it seeks to rebuff, that submission is that the effect of clause 37.2 of the contract is that a failure to provide a Progress Certificate will convert the Payment Claim into the Progress Certificate and create a liquidated liability.
13. I accept that the application is compliant with the basic and essential requirements of the Act.
Reasons
14. The Respondent has provided clear reasons for withholding payment for each of the individual elements of the Payment Claim, however before dealing with those submissions, it is relevant to consider the more sweeping submission of the Claimant identified above in the final sentence of paragraph 12 above.
Deemed Valuation
15. Clause 37 of the contract details the obligations and processes regarding payment. Clause 37.2 includes the following unnumbered sub-clause:
If the Superintendent does not issue the progress certificate within 14 days of receiving a progress claim in accordance with subclause 37.1, that progress claim shall be deemed to be the relevant progress certificate .
16. The Claimant submits that this clause should have its ordinary meaning and that the claim must be valued in accordance with section 9(a) of the Act. The impact of these submissions is that the full sum claimed must be valued in full for the purposes of the Progress Certificate. The Respondent resists these submissions saying in paragraphs 28 through 31 that it must fail. I have dealt above with most of the submissions made in paragraph 28. It is relevant to deal now with the remaining objections made to this submission of the Claimant.
Paragraph 28(d) no authority cited
17. There is no requirement for a party making a submission to provide an authority for a submission, though some guidance can reduce confusion and time expended unnecessarily. Having made this observation it is relevant for Adjudicators to consider relevant judicial pronouncements when applying section 22(2)(a) and 22(2)(b) of the Act. In this regard the following judgments are relevant: Main Roads Construction Pty Ltd v Samary Enterprises Pty Ltd [2005] VSC 388 a judgment of Habersberger J, who in that matter considered an identical clause to the one in issue. I return to the learned judges (sic) views later.
18. To the limited extent this is a reason for withholding payment it is not accepted.