[It was noted that House amendments were made in the other house, being the Legislative Assembly, which considered the second reading speech on 9 February 2006]
... The first house amendment extends the range of disputed variations that can be claimed under the legislation.
... The amendment will no longer require the parties to agree that the work has been carried out or the goods and services supplied and that the person was directed to carry out the work or supply the goods and services. This will provide certainty that the adjudicator will be able to determine whether this has occurred.
The amendment also provides for a cap on considerations under the construction contract to which a claim for disputed variation may be dealt with under the act. This will apply to claims for disputed variations where the consideration under the construction contract at the time that the contract is entered into is $5 million or less
In the case where a consideration is $5 million or less, claims may be made until claims for disputed variations reach 10 per cent of the consideration.
Claims made above that percentage are to be dealt with under the construction contract. The amendment also provides that considerations under the contract that are for $150,000 or less are not limited by the 10 per cent rule.
The amendment provides a safeguard for where the contract does not have a dispute resolution clause. In this case the act is to apply no matter what the consideration under the contract is.
[On a motion that the bill be read a second time in the Legislative Council, the second reading speech, including the following extracts, were incorporated into Hansard]
... The bill will enable some disputed variations to be dealt with under the act. This is where the variation results from a direction being given by the person for whom the work is being undertaken or the goods and services provided. These changes are aimed at avoiding uncertainties that have been experienced in other jurisdictions
In the case where a contractor has been directed to carry out the work the act will now apply to claims for disputed variations where the consideration under the construction contract at the time that the contract is entered into is below $5 million.
Claims for disputed variations in contracts below $5 million are considered to be suitable for assessment and interim decision within the time normally allowed by the security of payment scheme for the respondent to assess (10 days) and for the adjudicator to review (10 days).
The effect of the $5 million cap is that disputed variations in contracts in the small contracting sector and almost all the subcontracting sector would be subject to the scheme. Disputed variations on large contracts, initiated by building owners and big contractors will be exempt from the scheme.
This addresses the concern that such disputes on major contracts should not be subject to the security of payment scheme and the normal contract methods of dispute resolution should continue to apply.
In the case where the consideration under the construction contract is between $150,000 and $5 million, claims may be made in relation to disputed variations until the claims reach 10 per cent of the consideration under the construction contract.
Where the construction contract does not have a dispute resolution clause which includes the disputes under new section 10A(3)(c), then the act is to apply. This will ensure that contractors do not find that they have no means of dealing with disputes in this regard. The act becomes the fail-safe mechanism.
I emphasise that the limitation on the application of the act to the consideration under the contract only applies to disputed variations. Claims for payments in respect of consideration under the construction contract where there is no dispute remain subject to the scheme for all values of considerations under the construction contract.