6.4 CONSTRUCTION OF SLABS
6.4.1 General The construction of slab footing systems including slab-on-ground, footing slab, stiffened slab with deep edge beam, stiffened raft and waffle raft shall comply with the requirements of Section 5 and of this Clause. For Class H and E sites additional requirements are given in Clause 6.6.
The methods given for sloping sites assume that landslip is not a design consideration. Where landslip is possible the design shall be given individual consideration.
6.4.2 Filling Filling used in the construction of a slab, except where the slab is suspended, shall consist of controlled fill or rolled fill as follows:
(a) Controlled fill is material that has been placed and compacted in layers by compaction equipment within a defined moisture range to a defined density requirement. Except as provided below, controlled fill shall be placed in accordance with AS 3798.
Sand fill up to 0.8 m deep, well compacted in not more than 0.3 m thick layers by a vibrating plate or vibrating roller, shall be deemed to comply with this requirement. A satisfactory test for sand fill not containing gravel sized material is the achievement of a blow count of 7 or more per 0.3 m using the penetrometer test described in AS 1289.F3.3.
Non-sand fill up to 0.4 m deep, well compacted in not more than 0.15 m layers by a mechanical roller, shall be deemed to comply with this requirement. Clay fill shall be moist during compaction.
(b) Rolled fill consists of material compacted in layers by repeated rolling with an excavator. Rolled fill shall not exceed 0.6 m compacted in layers not more than 0.3 m thick for sand material or 0.3 m compacted in layers not more than 0.15 m thick for other material.
NOTE: The depths of fill given in this Clause are the depths measured after compaction.
6.4.3 Foundation for Slabs The foundation shall satisfy the following:
(a) Topsoil containing grass roots or other organic material shall be removed from the area on which the slab is to rest.
(b) On sites subject to wind or water erosion, the foundation of the edge beam or footing shall be protected.
(c) The slab, including edge and internal beams, shall be founded as follows:
(i) Slab panels, edge beams, internal beams and load support thickenings are to be supported on natural soil with an allowable bearing pressure not less than 50 kPa.
(ii) Slab panels, internal beams and load support thickenings are to be founded on controlled or rolled fill compacted in accordance with Clause 6.4.2.
(iii) Edge beams shall not be founded on rolled fill. Edge beams may be founded on controlled fill compacted in accordance with Clause 6.4.2(a). This fill shall continue past the edge of the building by at least 1 m and shall be retained or battered beyond this point by a slope not steeper than two horizontal to one vertical.
(iv) Edge footings not tied to a footing slab (see Figures 3.2 and 3.3(b)) shall be founded in natural soil with an allowable bearing pressure of 100 kPa or may be founded on controlled sand fill on a Class A or S site.
(d) The base of edge beams and footings may be stepped or sloped not more than 1 in 10.
(e) A blinding layer of sand is not required but where used shall comply with Clause 6.4.2 if deeper than 100 mm.
6.4.4 Treatment of sloping sites The treatment of slabs on cut-and-fill sloping sites shall comply with one of the following methods:
(a) The site shall be cut and filled and the fill (see Figures 6.1(a) and 6.1(b)) shall continue past the edge of the house by at least 1 m and shall be retained or battered beyond this point by a slope protected from erosion and not steeper than two horizontal to one vertical. The interior of the slab shall be founded on compacted material, satisfying Clause 6.4.3(c). The edge beams shall be founded on natural soil or on controlled fill or may be supported by piers designed in accordance with engineering principles.
(b) The site shall be cut and filled with fill material that satisfies Clause 6.4.3(c) and the fill shall be retained at the edge in accordance with Clause 6.4.5 as shown in Figure 6.1(c).
(c) The slab and beams may be stepped in combination with methods in Items (a) or (b) above to reduce the extent of excavation or fill. At the change in elevation, the step shall comply with the following:
(i) The ground behind the step shall be properly drained and the slab shall be waterproofed.
(ii) Care shall be taken that Clause 5.3.4 is satisfied.
(iii) Steps in stiffened rafts shall be designed to preserve the structural continuity of the system.
(iv) Steps in slabs for Class A and Class S sites shall comply with Figure 6.2 where the height of the step is less than 1.2 m. The masonry retaining wall shown in Figure 6.2 shall comply with Clause 6.4.5(b). Steps in beams shall comply with the principles of Clause 5.4.3.