APM agreed; Galwin did not respond.
11 On 4 May 2005 Galwin's solicitor wrote to Main advising that Galwin no longer agreed to the issues the subject of the completion agreement being referred to expert determination. The basis for Galwin withdrawing its agreement was that the dates in the completion agreement for the expert determination process had changed substantially.
12 On 5 May 2005 APM's solicitor wrote stating that it was not open to Galwin to resile from the completion agreement and that the expert determination should proceed.
13 On 5 May 2005 Main wrote to Galwin advising that in accordance with cl 5.2.3 of the completion agreement the cut off date for the submission of questions to be sent by Main will be 16 May 2005 and that responses would be required no later than 23 May 2005 and that the determination would be provided by 3 June 2005.
14 Following Galwin's letter dated 4 May 2005, on 9 May 2005 Main wrote to Galwin advising that Main did not accept Galwin no longer agreeing to the reference to expert determination, and that Main was continuing to act as expert as required by the completion agreement.
15 On 12 May 2005 Galwin wrote to Main disagreeing with Main's letter dated 9 May and recording that the principal consultant for the project would be unavailable until 27 June 2005 and that his absence would not have been an issue if the expert determination process had been finalised as agreed on 21 February 2005. In his affidavit the sole director of Galwin, Barry Goldenberg, deposed that the consultant's input was necessary due to his role.
16 On 30 May 2005 Main wrote to Galwin seeking answers to questions for the purpose of the expert determination and additional documentation. Galwin received the letter on 3 June 2005.
17 On 6 June 2005 Galwin wrote to Main advising that it did not agree to the issues being referred to Main's expert determination on the basis that the process agreed and set out in the completion agreement had not been followed. It was stated that the agreed process was to have been substantially faster and cheaper.
18 I note that in his affidavit Goldenberg referred to correspondence from Galwin to Main in the period 21 February 2005 to 23 June 2005 in relation to the performance by Main of its functions as superintendent.
19 On 24 June 2005 Galwin commenced a proceeding at VCAT seeking orders and declarations that Galwin was no longer bound by the expert determination in the completion agreement.
20 On or around 7 July 2005 Main issued its expert determination pursuant to the completion agreement. The determination was provided under cover of a letter dated 16 June 2005. The determination was that Galwin pay APM $534,493.81 plus GST.
21 On 3 November 2005, at a directions hearing of Galwin's proceeding, the member of VCAT presiding expressed the view that VCAT did not have jurisdiction to grant the declaration sought and suggested that application be brought in the Supreme Court.
22 It was in those circumstances that on 12 December 2005 APM filed its originating motion for the determination of certain questions and a declaration that Galwin is bound by the expert determination provisions in cll 5.1 to 5.9 of the completion agreement and the determination issued on 7 July 2005. Counsel sought only the declaration.
23 Then on 19 January 2006 Galwin filed its originating motion for declarations to establish that it was not bound by the expert determination. Other declarations were sought but that mentioned represents the essence of the matter and is the relief that counsel sought.
24 The evidence was contained in affidavits. Brian James Sands, the managing director of APM, swore an initial affidavit, and then an affidavit in reply to the affidavit sworn by Goldenberg. Neither deponent was cross-examined. Counsel told me that no facts were in dispute and that, accordingly, the matter was appropriate for determination by way of originating motion. There are nevertheless some additional matters in the affidavits to which reference should be made.
25 In para 11 of his affidavit Goldenberg stated that the timeframe of one month specified in the completion agreement for the expert's determination was indicative of the emphasis that Galwin placed on having the disputes resolved in a timely manner. In response Sands pointed out that the time was agreed by both parties who agreed the need for quick and cost effective resolution of the disputes rather than lengthy and expensive litigation in VCAT. In fact there were substantial savings in time and costs compared with litigating in VCAT: the expert provided the determination on 7 July 2005 and charged $111,925.
26 Sands next referred to the extent of the material that Galwin provided Main in relation to its claims on 28 February 2005. Galwin provided Main with 26 separate issues which went beyond the issues contemplated in the completion agreement. Sands said that that substantially increased the scope and duration of the determination. He exhibited a copy of the material submitted by Galwin.
27 Then, between 28 February 2005 and 31 March 2005 Galwin submitted approximately two lever arch files of material to Main in its capacity of superintendent.
28 In concluding his affidavit Goldenberg stated that Galwin was disadvantaged in relation to the expert determination in that Galwin was never in a position to provide substantive responses to the questions posed by Main in the letter to Galwin dated 30 May 2005, due to the extensions of time sought by Main "and the absence of its expert Mr Warren, and did not do so". As a result, Main's determination was unbalanced. How and in what way, and with what result, it was "unbalanced" was not stated or developed. It is, moreover, to be noted that although referred to as Galwin's "expert", Warren was in fact the former superintendent to the project to which role Main was appointed by the completion agreement.
29 I mention these evidentiary matters while noting, as I have said, that there was no cross-examination and that counsel stated that there was no dispute on the facts.
30 I turn then to the submissions of counsel.
31 It is convenient to commence with the submissions of Galwin's counsel. First noting the object of the parties to minimise the expense and delay associated with litigation (stated in the Background clause quoted at [2]), counsel submitted that cl 5 prescribed the process to be undertaken by the expert in the determination process. That contemplated a determination by the end of March 2005, a period of one month or so from the making of the agreement.
32 The parties complied with the times in cll 5.2.1 and 5.2.2. Main then had until 7 March 2005 to send questions to the parties, subject to Main determining an extension in conjunction with the parties. The parties agreed to an extension to 21 March 2005.
33 It was submitted that from 21 March, when Main "unilaterally varied" the date to 31 March and later to a date to be determined, Main departed from his "instructions". By "instructions" counsel meant the process stated in cl 5 understood in light of the object of minimising expense and delay. The departure constituted a failure by the expert to carry out his functions in accordance with the completion agreement. Counsel referred to Badgin Nominees Pty Ltd v Oneida Ltd[2] for the proposition that the expert derives his authority from the appointment in accordance with which he must act.
34 It was next submitted, really in the alternative, that on Galwin withdrawing on 4 May 2005 the expert determination process could not practically be completed. That is, the consequence of the withdrawal meant that the full processes in cl 5 could not work, in particular under cl 5.2.4. In proceeding with the determination process Main thus departed from the "instructions" in cl 5. With Galwin no longer participating, the expert did not have a response from Galwin. Therefore the determination lacked balance and was not a determination contemplated by the completion agreement.
35 For either or both of these reasons, or departures from his "instructions", Main did not, to use the language in cl 5.5.1, reach his determination in accordance with the completion agreement. Counsel referred to Veba Oil Supply and Trading GmbH v Petrotrade Inc[3] for the consequence of a departure from "instructions", which is that Galwin is not bound by the determination.
36 These submissions, and those of APM, require attention to be paid to the relevant terms of the completion agreement providing for the expert determination.
37 The first point to note is that the parties referred their subject disputes to the determination of Main acting as an expert and not as an arbitrator and whose decision would be final and binding. That meant, on its proper construction, that the completion agreement was not an agreement to refer disputes to arbitration, and, in consequence, that the Commercial Arbitration Act 1984 did not apply to the reference. The distinction between the role of an arbitrator on the one hand, and an expert, valuer or certifier on the other hand, has been considered in numerous cases[4]. An arbitration is conducted in the manner of a judicial inquiry whereas a determination by an expert, certifier or valuer is not. In Legal and General Life of Australia Ltd v A Hudson Pty Ltd[5] McHugh JA said that the effect of the words "acting as an expert and not as an arbitrator" was that: