(iii) The Period between the 2002 Court Orders and the 2004 Court Orders
46 On 29 November 2002, the Council notified the Respondent of its refusal of his development application for the reasons stated in the notification.
47 Following enquiry from the Council's Solicitors, the Respondent's Solicitor on 4 July 2002 advised that the Respondent did not intend to appeal the Council's refusal of the development application and would "accordingly be carrying out appropriate re-instatement works".
48 By letter dated 4 July 2002, the Respondent notified the Council of the reinstatement works that he proposed to undertake in order to comply with the Court's Orders made on 13 March 2002.
49 By letter dated 22 July 2002 the Council's Solicitors advised the Respondent's Solicitor that "much of the development proposed includes works which fall beyond that which the Court orders require". The letter continued:
We note that all other works proposed by your letter dated 4 July 2002, those being for the construction of retaining walls, brush fencing, repairs to the existing pergola, re-instating fill/lawn and steps down to the eastern boundary, are not permitted until they are assessed by way of a development application submitted to Council.
Pursuant to the Court Orders the only works permitted is the removal of the illegal fill so that the site is substantially in the same condition as it was immediately prior to the development. This removal of fill must only be done under the guidance of a geotechnical engineer because of the safety issues involved in relation to the property at No 72 Pittwater Road.
We also hereby give notice to your client that Council will be issuing an Order to install a pool safety fence under the provisions of the Swimming Pools Act 1992 and Swimming Pools Regulations 1998.
50 By letter dated 13 December 2002 the Council's Solicitors advised the Respondent's Solicitor that they had been instructed "to move the Court for orders that your client is in contempt of Court, if within 28 days from 20 December 2002, the reinstatement works have not been carried out".
51 The Respondent's Solicitor responded by letter dated 23 January 2003, including the following advice:
In your letter to us dated 22 July 2002 you stated that the schedule of proposed reinstatement works submitted by our client went beyond the works ordered by the Court on 13 March 2002. In particular, you submitted that the only work permitted pursuant to the Court order was the removal of fill under the guidance of a geotechnical engineer. We request that the Council specify which particular items under our client's proposed schedule of work are unacceptable and to provide reasons why they do not constitute reinstatement.
In our view, the removal of fill in itself is not sufficient to comply with the Court order to reinstate the site of the development substantially to the condition it was in immediately prior to the development (refer to order 2 of the Court dated 13 March 2002). Reinstatement must involve replacement of the structure demolished as part of the works the subject of the proceedings. Our instructions are that a retaining wall is essential to securing our client's land.
52 Thereafter, correspondence ensued in which the parties' respective Solicitors attempted to settle the disputed question as to the precise nature of the reinstatement works that were required by the Court's Orders of 13 March 2002 to be undertaken.
53 This exchange of correspondence included the Council's Solicitors' letter dated 14 July 2003 to the Respondent's Solicitors written in contemplation of an on-site meeting between the parties and their technical advisers "to attempt to fully resolve all outstanding matters in these proceedings". The letter concluded with the following paragraph:
In conclusion, the Council wishes to provide your client with a final opportunity to comply (at least in spirit) with the intention of the Court Order dated 13 March 2002. However, if we are unable to facilitate a satisfactory compromise, our client has instructed us to commence contempt proceedings in respect of the breach of the Court Order. We also note that the issue of costs was reserved in respect of the proceedings and if the Council is forced to bring the matter before the Court by way of contempt proceedings, we are instructed to seek costs in relation to the whole of the proceedings.
54 By letter dated 21 July 2003, the Respondent's Solicitor advised the Council's Solicitors as follows:
We refer to our meeting with you on 16 July 2003 with our respective clients and consultants.
Referring to the numbered paragraphs of your letter dated 14 July 2003 we confirm agreement at the meeting as follows:
1. the area to the south east of the swimming pool is to be landscaped and retained as shown in the attached diagram such that the fill adjacent to the swimming pool will be reduced in height to a level generally the same as the top concrete step on the adjoining property at No 9 Amelia Place;
2. the fill between the swimming pool and No. 9 Amelia Place will be reduced in height by 500mm;
3. no planter boxes are proposed at this stage;
4. see paragraph 1 above;
5. there was agreement that the south eastern corner of the property should be planted with low to medium shrubs to provide privacy along the fence line with 9 Amelia Place;
6. all damaged fences on neighbouring properties will be replaced on the rear common boundary;
7. it was agreed that the matter of the lower portion of the retaining wall adjoining 9 Amelia Place was not affected by the works the subject of the court proceedings, and could be resolved separately between the neighbours;
8. a pool safety fence will be located generally in the location of the fence which was removed as part of the landscaping works (as had always been our client's intention).
As advised our client's engineer anticipates being able to provide a sketch by 30 July 2003 of the agreed works.
Please confirm council's agreement to the above settlement in principle.
55 By letter dated 26 August 2003, the Respondent's Solicitor further advised as follows:
We refer to our letter dated 21 July 2003. As we have had no reply, we presume that our record of the agreement made at the conciliation meeting set out in that letter is not disputed.
On that basis, our client's engineer and landscape contractor have prepared the attached plans to record the agreed works:
(a) drawing number BSOL-921 prepared by Tihanyi Consulting Engineers dated July 2003; and
(b) Landscape Sketch Plan prepared by Living Colour Landscapes dated 17 August 2003.
Once council confirms its' agreement to those plans as recording the agreed reinstatement works to satisfy the consent orders already made in the proceedings, we are instructed our client will complete those works.
56 By letter dated 4 September 2003, the Council's Solicitors called for the submission of amended plans to provide additional detail on some specified issues and to eliminate from the scope of the proposed works, works which were said to require separate development consent.
57 This letter was followed by a letter dated 28 October 2003 which stated inter alia:
The Court Order dated 13 March 2002 required your client to undertake remediation works. We are instructed that those works have not been completed. Moreover, the Council considers that the amenity of Dr Wild's property (ie 9 Amelia Place) is being unreasonably compromised by your client's failure to complete the remediation works contemplated by the Court Order.
Given that your client's breach of the Court Order dated 13 March 2002 constitutes a potential contempt of Court, we are instructed that if we have not been provided with the relevant documentation by 4 November 2003, we are instructed to file and serve a Notice of Motion for contempt.
58 By letter dated 27 November 2003, the Council's Solicitors notified the Respondent's Solicitor in the following terms:
As noted in our facsimile to you dated 28 October 2003, the Council considers that this matter needs to be resolved one way or the other. In this regard, we still wish to pursue a compromise in the form contemplated by the without prejudice agreement of 16 July 2003. However, failing such a resolution, we are instructed to file and serve a Notice of Motion for contempt. If this course is ultimately taken, we put you on notice that the Council will also make an application for costs in respect of the whole of the proceedings.
59 Following the passage of further correspondence the Council's Solicitors by letter dated 16 December 2003 notified the Respondent's Solicitor as follows:
If we have not received a satisfactory response to the proposed meeting, and details of the author of the landscape plan, by 4.00pm, 19 December 2003, we will assume that your client is no longer interested in resolving these proceedings. In those circumstances, we are instructed to file and serve a Notice of Motion for contempt. If this course is taken, we put you on notice that the Council will also make an application for costs in respect of the whole of the proceedings.
60 On 18 February 2004 the Respondent's Solicitor submitted to the Council's Solicitor further amended plans in respect of the reinstatement works.
61 However, the ongoing process of negotiations came to an abrupt end when on 31 March 2004 the Council's Solicitors wrote to the Respondent's Solicitor as follows:
We refer to the above proceedings and the Court Order dated 13 March 2002 (the Court orders ).
Court Orders
In essence, the Court Orders deal with two distinct matters. Firstly, your client was required to undertake Interim Stability Measures to stabilise the boulder retaining wall on the southern boundary of the Property and the retaining wall on the eastern boundary of the Property. We note our instructions that the Interim Stability Measures were carried out by your client.
Secondly, in the event that Development Application No. N180/02 was refused ( Development Application ), your client was required to undertake Reinstatement Works. We are instructed that the Council refused the Development Application on 6 June 2002.
Mechanism for determining the scope of the Reinstatement Works
In circumstances where the Development Application was refused, the Court Orders provided that your client was to provide to the Council particulars of the proposed Reinstatement Works.
On 4 July 2002 , the Council received a letter from your client providing particulars of proposed Reinstatement Works. On 22 July 2002 , we wrote to you in relation to the adequacy of the proposed Reinstatement Works (as proposed by your client in his letter of 4 July 2002). In our letter we clearly outlined that the only works proposed to be undertaken by your client which were permitted by the Court Orders was the removal of the fill and retaining structures.
Further, the Court Orders provided that once the Reinstatement Works had been approved by the Council, your client was to complete the approved Reinstatement Works within 60 days. Accordingly, the Council approved Reinstatement Works should have been completed within 60 days of 22 July 2002.
Reinstatement Works other than those approved by the Council
Any proposed works contemplated in your client's letter of 4 July 2002, other than the Council approved Reinstatement Works, are beyond the terms of the Court Orders.
Whilst we are instructed that the Council accepts that the Court Orders may not require your client to reinstate the Property in situ, the Court Orders clearly do not empower your client to undertake landscaping works which are unrelated to the Reinstatement Works required by the Court Orders and that would otherwise require the prior consent of the Council.
We are instructed that the works proposed by your client in his letter of 4 July 2002 (other than the removal of the fill and retaining structures) relate to landscaping works aimed at achieving greater amenity for your client. We are further instructed that those works will detrimentally effect the amenity of your client's neighbours at 9 Amelia Place.
In our view, no reasonable interpretation of the Court Orders could lead to a conclusion that the Court Orders were to facilitate your client to undertake further landscaping works (or retain unauthorised works) aimed at achieving greater amenity for him to the detriment of his neighbours.
Re-listing of matter
As you are aware, the parties have been engaged in without prejudice discussions since March 2003 in an effort to resolve these matters. In our view, the discussions have been unsuccessful and we are now instructed to have the matter re-listed before His Honour Bignold J, and to seek directions that the parties' experts confer in accordance with the Court's Expert Witness Practice Direction 2003.
In this regard, we are currently preparing a Notice of Motion and affidavit which we intend to file and serve within the next two (2) days. Further, we are instructed to seek an order that your client pay the Council's costs in relation to the whole of the proceedings.
62 The Respondent's Solicitors responded by letter dated 2 April 2004 in the following terms:
We refer to your letter of 31 March 2004 which comes as some surprise to our client.
The works to be carried out to our client's property were settled by way of the mediated agreement made on site on 16 July 2003 (as documented by our letter dated 21 July 2003).
Plans detailing those works were provided on 26 August 2003. The fact that the levels were agreed at the 16 July 2003 meeting is confirmed in the letter from Mr Ambrosis of GHD Longmac of 24 November 2003. Furthermore, a file note taken by Ms Urquhart of our office of her telephone conversation with you of 14 January 2004, records that when she asked you why Council never replied to the summary of the mediated agreement in our 16 July 2003 letter, you answered with words to the effect that the reason that you did not reply was that you essentially agreed with what (was) in the fax .
Additional detail requested by the Council's experts has been provided (most recently by way of the amended plans dated 18 February 2003).
Our client is also frustrated by the ongoing delay in resolving this matter, particularly as he has expended significant time and money in preparing the plans now with Council reliance on the agreement reached.
Your 31 March 2004 letter refers to adverse amenity impacts on 9 Amelia Street but does not particularise them. Rather than return the matter to Court please particularise:
(a) what the alleged adverse impacts are;
(b) how your client submits the 18 February 2004 plans differ from the mediated agreement of the 16 July 2003 meeting; and
(c) what changes to the 18 February 2004 plans the Council submits are required.
In circumstances where our respective clients' experts are communicating well, there is no identified issue in dispute, and the Council has not identified any matter of concern, we cannot see the utility in returning the matter to Court with the resulting expense.
If Council does return the matter to Court without identifying the issues in concern and the orders it will be seeking, then we will tender this letter on the issue of our client's costs.
63 This prompted the following reply from the Council's Solicitors dated 5 April 2004:
The matters to which you refer relate to without prejudice negotiations that have been taking place between the parties since March 2003. We do not intend to provide you with further details of our client's position as we do not consider that there is any ambiguity as to what was agreed between the parties.
As we have already indicated to you, our client considers the without prejudice negotiations to be at an end. However, if your client is willing to:
1 provide the Applicant with the material it has been seeking since July 2003; and