Pine v Casello Constructions Pty Ltd
[2005] FCA 1854
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2005-11-23
Before
North J
Source
Original judgment source is linked above.
Judgment (4 paragraphs)
REASONS FOR JUDGMENT 1 Before the Court are two applications under s 187AD(1)(a) of the Workplace Relations Act 1996 (Cth) (the Act) in relation to a contravention by Casello Constructions Pty Ltd, the respondent, of s 187AA(1) of the Act. 2 The respondent is a subcontractor carpentry company which has admitted to having paid some of its employees during work stoppages on 5 August 2003 and 6 August 2003. The employees were engaged in industrial action as defined by the Act and it is therefore accepted that the respondent was in breach of s187AA(1) of the Act. 3 The industrial action on 5 August 2003 was taken in response to the death of a labourer, Mr. Andrew Schouten, on a construction site in Shepparton. On 1 August 2003, Mr. Schouten died when a crane he was working near struck overhead powerlines. Mr. Schouten's death resulted in a safety audit being conducted at the Three Towers and Concept Blue sites in accordance with the On-site Fatalities Policy and Procedure of the Construction, Forestry, Mining and Energy Union (CFMEU) on 5 August 2003. As a result of Mr Schouten's death and the implementation of the On-site Fatalities Policy and Procedure, employees of the respondent stopped work at these two sites. On 5 August 2003, 17 employees stopped work at the Three Towers site for four and a half hours and four employees stopped work on the Concept Blue site for six and a half hours. On 6 August 2003, four employees stopped work for three hours on the Concept Blue site. The stoppage related to the employers failure to agree to pay workers for the initial stoppage on 5 August 2003. The contravention alleged is the payment by the respondent to the 21 employees amounting to a total of approximately $2000. 4 A number of cases have been decided by the Court in relation to almost the same circumstances, namely the payment by subcontractors to employees on 5 August 2003 on construction sites during work stoppages during a safety audit following a death in the industry. In Ponzio v D and E Air Conditioning Pty Ltd [2005] FCA 964 (D and E Air Conditioning) it was said at [21] that, whilst the factors to be considered in each case might be derived from the authorities, each case must be determined on its own facts. 5 The starting point in this case must be that the respondent agreed that it has contravened the Act. The industrial laws of Australia should be obeyed, but the circumstances of each case will determine the appropriateness of the penalty to be imposed. Therefore, although the contravention of the Act is not in issue, it is necessary to consider the particular circumstances of the respondent's conduct. 6 Mr O'Grady, who appeared as counsel for the applicant, argued the respondent was aware the employees were engaged in industrial action and deliberately made the payment. Mr O'Grady suggested the appropriate penalty in this case should be in the region of $1000 or approximately $50 for each of the 21 employees involved. 7 The circumstances, however, bear a slightly different complexion. Mr. Cassar, the director of the respondent, approached the head contractor, Multiplex to seek advice on the policy to be followed in light of the stoppages which affected every Multiplex site and not just the sites presently in question. Mr Cassar then took his lead from Multiplex. This was a rational and practical approach to a difficulty which had arisen on a site governed by a head contractor. Whilst the solution was not lawful, the respondent's conduct was understandable. Mr Cassar has since taken steps to ensure this mistake will not be repeated. On 7 and 14 November 2005, Mr Cassar undertook a two day course relating to his obligations under the Workplace Relations Act. Furthermore, on 26 May 2005 Mr Cassar notified all employees in writing of the policy of the respondent in the following terms: I have instructed our site foreman that any stop work on site for whatever reason and duration, must be reported immediately to me. Further, it is imperative that the information recorded on employee's time sheets provides an accurate and full account of the work performed or activities undertaken. Finally we must state Casello's policy on payment for industrial action. In the future, Casello will not pay any employee who has ceased work without management's authority or participated in industrial action. The only possible exception to this is where there is a genuine safety issue whereby employees are at risk of immediate personal danger in there immediate work area.