Patterson & Anor v Mamou t/as De Novo Conveyancing
[2024] NSWDC 75
At a glance
Source factsCourt
District Court of NSW
Decision date
2024-03-18
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Background
- On 1 March 2024 I delivered reasons for deciding that the defendant should pay damages to the plaintiffs for the sum of $43,800 arising out of the plaintiffs' claim of professional negligence. [1] I had assessed the plaintiffs' loss as being the sum of $146,000 ([172]). But I accepted the defendant's argument that her liability should be limited by reason of the proportionate liability provisions in Part 4 of the Civil Liability Act 2002 (NSW) and, specifically, determined that her responsibility for the plaintiffs' loss was 30%; whereas the responsibility of the concurrent wrongdoer - the building inspector - was assessed at 70% ([147]-[159]).
- I directed the parties to confer for the purpose of resolving disputes on remaining issues (including interest and costs) and if they did not agree, to supply the Court with further submissions.
- The plaintiffs abandoned the claim for interest that had been pleaded in their statement of claim. The remaining dispute concerned costs.
- The defendant seeks a special order that she pays the plaintiffs' costs (as agreed or assessed) up to 10 March 2023; and thereafter the parties bear their own costs. An alternative order sought was that there should be a 50% discount upon the plaintiffs' recovery of costs from the defendant after that date.
Evidence of the defendant's settlement offers