Was there an inconsistency between clauses 28 and 42?
29It was agreed by the parties before me that should this Court find that clauses 28 and 42 could run together, there was no inconsistency.
30Magistrate Bone concluded that clauses 28 and 42 of the contract were irreconcilable and were inconsistent with each other.
31Clause 28 is headed "Unregistered plan" and is a clause in the standard form contract. Clause 28.2 asserts that the vendor must do "everything reasonable" to register the development plan within six months of the contract date. Clause 28.3 provides for the consequences if the development plan is not registered within six months and gives the purchaser an unqualified right to rescind and the vendor a qualified right of rescission subject to the terms of cl 28.2. There is no compulsion on either party to exercise its rights prior to the expiration of the six-month period.
32Clause 42 a special condition is headed "Sunset date" and provides the discretionary right for either party to rescind the contract if, after 18 months from the contract date, the development plan is still not registered. Between the time of six months and 18 months after signing the contract, the purchaser retains an unqualified right to rescind the contract pursuant to cl 28.3 subject to any argument of waiver or estoppel.
33Navaroo Constructions submits that the source of the inconsistency is the purported conferral of a right to rescind at two different but irreconcilable points in time. The contract cannot be rescinded after six months, it was submitted, yet also confer a right to rescind at 18 months. If rescission has occurred at the first point in time, there is no utility to the second point in time, it serves no purpose. It was further submitted that this would leave no room for the operation of the specially negotiated clause and would deprive Navaroo Constructions of the opportunity to take the benefit of the full 18-month period for registration which had been negotiated between the parties. Such a result would be inconsistent with the well-established principles that the specially negotiated terms should be given precedence.
34In oral submissions, counsel for Navaroo Constructions put forward argument as to the operation of the contract. It was submitted that there are four essential elements to the way in which cl 28 works. They are firstly, that the contract is conditional on the plan being registered; secondly, that there is a duty on the vendor to register the plan; thirdly, there is a right of rescission; and fourthly, that once the plan is registered, there will be completion in accordance with cl 34. Counsel further submitted that clauses 41 and 42 of the special conditions also dealt with those same four elements and an inference could be drawn that a special regime applied to the registration of the plan which had been negotiated by the parties. While cl 33 listed the agreed changes to the clauses in the standard form contract, it did not include any change to cl 28, an inference could be drawn that there was no need to deal with cl 28 in cl 33 as they had dealt with everything necessary in relation to registration of the plan in the special conditions, that is, clauses 41 and 42.
35Clause 41.4 provides that the vendor must seek registration of the plan by the Registrar General and do all things necessary to achieve the registration of the plan "as expeditiously as possible". Clause 29.1 provides that completion of the contract is conditional on an event, in this case, the registration of the plan. Emphasis was placed by counsel for Navaroo Constructions on cl 21.2 which states:
"21.2 If there are conflicting times for something to be done or to happen, the latest of those times applies."
36It was submitted for Navaroo Constructions that if there is inconsistency within the contract as to the time by which something is to happen, then cl 21.2 applies. Thus, where cl 28 provides for the contract to be rescinded after six months and cl 42 provides for rescission after 18 months, by virtue of cl 21.2, the period after which the contract can be rescinded should the plan remain unregistered is 18 months.
37However, neither cl 28 nor cl 42 positively assert a time by which the conditional event upon which the contract relies, the registration of the plan, is to be done or happen. Clauses 28 and 42 simply provide a mechanism to end the contract if registration of the plan has not yet occurred at two different points in time. Therefore, in my view, there is no conflicting time as referred to in cl 21.2, for which something is to be done or happen such that the later time would apply.
38If a party elected to rescind the contract under either Clause 28.3 or 41 the machinery for doing so is set out in Clause 19.
39Counsel for the Parrys submitted that the Magistrate held that the provisions were irreconcilable because both involved the exercise of a discretion, not that they conferred a right to rescind at two different times. It is submitted that both clauses 28 and 42 were agreed by the parties and are not irreconcilable. Special condition cl 33 amended and deleted 10 clauses of the standard form contract. It is submitted that this reflects this agreement as, if cl 28 was to be amended or excluded, it would have been included in the amendments listed in cl 33.
40In oral submissions, counsel for the Parrys submitted that cl 41 could work equally well with cl 28. Clause 41.4 states that the vendor must do all things necessary to achieve registration of the plan "as expeditiously" as possible, the six-month period for registration aligning more closely with that requirement than did the 18-month period in cl 42. It was further submitted that cl 42 does not provide a positive assertion to lengthen the time available to the vendor to register the plan to 18 months.
41The six-month deadline for registration was 24 August 2011. On 29 August 2011, the Parrys informed Navaroo Constructions that they were rescinding the contract under the terms of cl 28.3. At this time, cl 42.1 was not operative, it only becoming operative if: (a) 18 months had passed since signing the contract; and (b) the plan was still not registered.
42If, at any time between six and 18 months the plan remained unregistered, only cl 28 operated to provide a mechanism to rescind the contract because registration had not yet occurred. If the plan was registered between six and 18 months from the date of the contract, cl 34, which details the mechanism for completion, became operative and the right to rescind under either cl 28.3 or cl 42.1 expired. Once the plan was registered, neither clause 28 nor 42 had any further operation. Neither party argued that Clause 42.2 may have provided a way out for the vendor after the six month period had elapsed. But as 42.2 appears under the heading "Sunset Clause" it would seem to be effective only after 18 months had passed, as referred to in 42.1.
43Magistrate Bone placed emphasis on the fact that cl 42.1 did not put an end to the transaction as by agreement both parties could continue the contract beyond 18 months if the plan was still unregistered. His Honour stated that if cl 42.1 could stand with cl 28.3, it merely provided a second, but not final, opportunity for either party to end the contract. As a result, his Honour found that clauses 28 and 42 were inconsistent and cl 42 should prevail. It is true that under the terms of this contract if neither party took steps to rescind the contract it would remain on foot. But I do not think that makes it inconsistent.
44Counsel for Navaroo Constructions submitted that the operation of clauses 28 and 42 together make the operation and performance of the contract uncertain and would leave a vendor such as Navaroo Constructions in a position where it would not know whether to perform the contract within six months or I8 months. However, cl 41.4 places the onus on the vendor to do everything necessary to achieve registration of the plan as soon as possible. Completion of the contract cannot take place until the plan is registered and until that occurs, the operation and performance of the contract would necessarily remain uncertain. Once registration occurs, the right to rescind either under cl 28.3 or cl 42.1 can no longer be exercised by either party.
45In my view, clauses 28 and 42 operate at different points in time. However, this does not make them inconsistent. The fact that after a period of 18 months has passed and the plan remains unregistered, the contract may continue if neither party chooses to rescind the contract under cl 42.1, also does not make them inconsistent. Clauses 28 and 42 are capable of operating together and do different work. In Rivat at [47], his Honour Hamilton J said:
"[W]hilst clearly inconsistent provisions of the printed form must be treated as excluded by the typed provisions, the operation of the printed clauses should be preserved so far as is possible. The Court should not lightly accede to a submission that the typed provision covers the field and excludes in whole the corresponding printed clause, if parts of that provision can coexist with the typed clause and still be given effect."
46Clause 28 provides that the purchaser is not locked in to the purchase beyond six months. The vendor can also get out of the contract at six months if, despite having done all it reasonably could, the plan is not registered. Clause 42 allows both parties a second chance to exit the contract if the plan remains unregistered after 18 months or the vendor finds themselves in a position such that they are unable or unwilling to register the plan.
47The fact that the contract included cl 33 that specifically amends the printed clauses and did not include any amendment to cl 28 also lends weight to the conclusion that cl 28 was intended to continue to operate.