The alleged representations
70Parkview submits that, alternatively, BankWest represented to Parkview that BankWest "held the retention moneys under the Building Contract which had been deducted from payments made to Parkview in respect of the Progress Claims made by Parkview" (Amended Technology and Construction Reply par 3(a)).
71First it is submitted that in dealing directly with Parkview in respect of the ANZ Guarantee, BankWest impliedly represented to Parkview that "the retention monies existed and were held or controlled by it". Parkview submits that "[t]he implication was that the monies were held available or at least had been earmarked in the sense that BankWest had promised to make them available when the time came to pay them out."
72I do not accept this submission. In my opinion, BankWest's conduct conveyed no more than a representation that it was authorised by its customer, Fortia, to receive the ANZ Guarantee and, in return, draw down $1.2 million under the Facility and make that sum available to Parkview by way of bank cheque. That was true.
73Second, Parkview submits that further representations arose by reason of two letters sent by BankWest's QS.
74Mr Emile Tabet, a director of Parkview, gave evidence that: -
"In about August 2009 I entered into negotiations with representatives of Fortia concerning claims for variations which had been made by Parkview and which had not yet been approved or paid. I sought confirmation that there was sufficient funds available from BankWest to cover the contract works and variations."
75On 27 August 2009, Mr Jon Drane from Fortia, wrote to Mr Tabet: -
"I confirm discussions with Paul Elphick [BankWest's QS] today where he will issue a letter confirming adequate funds exist to cover your contract works and approved variations. This will be in full light of the bank and be copied to the bank and Fortia."
76On 31 August 2009, BankWest's QS wrote to Fortia (with a copy to Parkview and BankWest) as follows: -
"Further to your request of confirmation of funds to complete the approved construction works we confirm the following:
The approved contract sum with Parkview as at 20 August 2009 inclusive of CVA No. 32 is $47,696,881.34 excluding GST.
We confirm there is [sic] sufficient funds within the current BankWest facility for value of works up to and including CVA No. 32.
As instructed we shall copy this letter to Parkview (Emile Tabet) and BankWest (Louise Lester) for their information."
77Parkview submitted that by this letter, BankWest, by its QS, represented to Parkview that, not only was there sufficient "head room" (to use a word mentioned in oral submissions) in the Facility to enable Fortia to fund the Project to the then approved contract sum of $47,696,881.34, but that BankWest would make that money available to Parkview, when Parkview became entitled to receive it, whether Fortia "formally asks for that or not".
78I do not read the 31 August 2009 letter this way. It seems to me that the natural reading of the letter, particularly the third paragraph, conveys no more than that the amount currently undrawn under the Facility would be sufficient to fund the works. There is no suggestion that this was not the case.
79In that sense it was responsive to Mr Tabet's enquiry as to whether there were "sufficient funds available from BankWest to cover the contract works and variations".
80Furthermore, Mr Tabet did not understand the letter as conveying a representation that BankWest would advance funds sufficient to fund the cost of the Project, come what may.
81Mr Tabet gave this evidence: -
"Q: ...you wanted confirmation that the BankWest facility was sufficient to meet the currently anticipated cost of the Project?
A: Correct.
Q: And insofar as payment of the retention was concerned, you told us a moment ago that your understanding was that Fortia would be able to draw down the retention from its BankWest facility and pay it to you when it needed to; yes?
A: Yes.
Q: At practical completion and final completion?
A: Yes.
Q: And you viewed this letter as some confirmation and comfort that notwithstanding that the cost of the project had increased through approved variations, the terms of their facility with BankWest were such that they would still be able to do that?
A: Yes.
Q: They would, when required, be able to borrow enough money from BankWest to pay you your retentions; correct?
A: It should be in the facility...
Q: You understood that under the terms of the facility with BankWest they would be entitled to draw down the amount required to pay you your retention when they were obliged to pay it?
A: Yes."
82Later: -
"Q: And you took the trouble [in August 2009] to make sure there was enough capacity in the bank facility to cover the cost of the project, notwithstanding [an increase in costs as a result of variations]?
A: Yes.
Q: And you sought to do the same in relation to the further increase in costs of the project brought about by unanticipated external works?
A: Yes.
Q: Depending on whether there were further unanticipated expenses, Fortia's capacity to fund the works under the facility may or may not be sufficient. You knew that?
A: Yes."
83This evidence makes clear, in my opinion, that Mr Tabet, thus Parkview, did not rely upon the 31 August 2009 letter as a representation by BankWest of the kind contended for.
84On 9 October 2009, BankWest's QS wrote to Mr Tabet from Parkview and Mr Drane from Fortia attaching a "Construction Cost Financier Certification". Parkview contends that this document "certified the then retention moneys of $1,050,000 as a credit".
85The figure of $1,050,000 appeared in that certificate in a table in the following form: -
Contract Total Total Previous Value of Work Certified Value Completed Since Last Certification Drawdown To Complete Excl GST
Amount Value Of Work To Date
$ $ $ $ $
DESIGN, SUPERVISION, PRELIMINA 13,873,000 10,738,236 10,383,009 355,227 3,134,764
TRADE COSTS 31,127,000 31,941,255 29,776,957 2,164,298 -814,255
APPROVED VARIATIONS (Note vii) 4,591,498 3,116,967 2,812,348 304,619 1,474,531
SUBTOTAL 49,591,498 45,796,458 42,972,314 2,824,144 3,795,040
RETENTION (5%) CASH -2,479,575 -1,050,000 -948,616 -101,384 1,050,000
RETENTION (5) BOND (Note vii) 0 0 0 0 0
TOTAL (Excl GST) 47,111,923 44,746,458 42,023,498 2,722,760 4,845,040
GST 4,711,192 4,474,646 4,202,370 272,276
RETENTION (5%) BOND (Note vii) -235,560 -1,200,000 -1,200,000 0
TOTAL 51,823,155 48,021,104 45,026,068 2,995,036